20-F
As
filed with the Securities and Exchange Commission on October 29, 2008
UNITED STATES SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
FORM 20-F
(Mark One)
|
|
|
o |
|
REGISTRATION STATEMENT PURSUANT TO SECTION 12(b) OR (g) OF THE
SECURITIES EXCHANGE ACT OF 1934 |
OR
|
|
|
þ |
|
ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES
EXCHANGE ACT OF 1934 |
For the fiscal year ended June 30, 2008
OR
|
|
|
o |
|
TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE
SECURITIES EXCHANGE ACT OF 1934 |
OR
|
|
|
o |
|
SHELL COMPANY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE
SECURITIES EXCHANGE ACT OF 1934 |
Date of event requiring this shell company report
For the transition period from to
Commission file number: 001 31545
HARMONY GOLD MINING COMPANY LIMITED
(Exact name of registrant as specified in its charter)
REPUBLIC OF SOUTH AFRICA
(Jurisdiction of incorporation or organization)
RANDFONTEIN OFFICE PARK, CNR WARD AVENUE AND MAIN REEF ROAD,
RANDFONTEIN, SOUTH AFRICA, 1760
(Address of principal executive offices)
Khanya Maluleke, Company Secretary
tel: +27 11 411 2019, khanya.maluleke@harmony.co.za, fax: +27 11 411 2070,
Randfontein Office Park, CNR Ward Avenue and Main Reef Road, Randfontein, South Africa, 1760
(Name, Telephone, E-mail and/or Facsimile number and Address of Company Contact Person)
Securities registered or to be registered pursuant to Section 12(b) of the Act:
Ordinary shares, with nominal value Rand 50 cents per share*
(Title of Class)
American Depositary Shares (as evidenced by American Depositary Receipts),
each representing one ordinary share
(Title of Class)
Securities registered or to be registered pursuant to Section 12(g) of the Act:
Ordinary shares, with nominal value Rand 50 cents per share*
(Title of Class)
American Depositary Shares (as evidenced by American Depositary Receipts),
each representing one ordinary share
(Title of Class)
* |
|
Not for trading, but only in connection with the registration of
American Depositary Shares, pursuant to the requirements of the
Securities and Exchange Commission. |
Securities for which there is a reporting obligation pursuant to Section 15(d) of the Act: None
The number of outstanding shares of each of the issuers classes of capital or common stock as of
the close of the last full fiscal year covered by this Annual Report was:
403,253,756 ordinary shares, with nominal value of Rand 50 cents per share
Indicate by check mark if the registrant is a well-known seasoned issuer, as defined in Rule 405 of
the Securities Act.
YES þ NO o
If this report is an annual or transition report, indicate by check mark if the registrant is not
required to file reports pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934.
YES o NO þ
Indicate by check mark whether the registrant (1) has filed all reports required to be filed by
Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for
such shorter period that the registrant was required to file such reports) and (2) has been subject
to such filing requirements for the past 90 days:
YES þ NO o
Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer,
or a non-accelerated filer. See definition of accelerated filer and large accelerated filer in
Rule 12b-2 of the Exchange Act. (Check one):
|
|
|
|
|
Large accelerated filer þ
|
|
Accelerated filer o
|
|
Non-accelerated filer o |
Indicate by check mark which basis of accounting the registrant has used to prepare the financial
statements included in this filing:
|
|
|
|
|
U.S. GAAP o
|
|
International financial Report Standards as
issued
|
|
Other o |
|
|
by the International Accounting Standards
Board þ |
|
|
If Other has been checked in response to the previous question, indicate by check mark which
financial statement item the registrant has elected to follow:
Item 17 o Item 18 þ
If this is an annual report, indicate by check mark whether the registrant is a shell company (as
defined in Rule 12b-2 of the Exchange Act).
YES o NO þ
Indicate by check mark whether the registrant has filed all documents and reports required to be
filed by Sections 12, 13 or 15(d) of the Securities Exchange Act of 1934 subsequent to the
distribution of securities under a plan confirmed by a court.
YES þ NO o
USE OF TERMS AND CONVENTIONS IN THIS ANNUAL REPORT
Harmony Gold Mining Company Limited is a corporation organized under the laws of the
Republic of South Africa. As used in this Annual Report on Form 20-F, or this annual report, unless
the context otherwise requires, the term Harmony refers to Harmony Gold Mining Company Limited;
the term South Africa refers to the Republic of South Africa; the terms we, us and our
refer to Harmony and, as applicable, its direct and indirect subsidiaries as a Group; the terms
South African government and Government refer to the government of South Africa and, where the
context requires, include the South African state.
In this annual report, references to R, Rand and c, cents are to the South
African Rand, the lawful currency of South Africa, A$ refers to Australian dollars, Kina or K
refers to Papua New Guinean Kina and references to $, U.S.$ and U.S. dollars are to United
States dollars.
This annual report contains information concerning our gold reserves. While this annual
report has been prepared in accordance with the regulations contained in Securities and Exchange
Commission Guide 7, it is based on assumptions which may prove to be incorrect. See Item 3. Key
Information Risk Factors Harmonys gold reserve figures are estimated based on a number of
assumptions, including assumptions as to mining and recovery factors, future cash costs or
production and the price of gold and may yield less gold under actual production conditions than
currently estimated.
This annual report contains descriptions of gold mining and the gold mining industry,
including descriptions of geological formations and mining processes. We have explained some of
these terms in the Glossary of Mining Terms included at the end of this annual report. This
glossary may assist you in understanding these terms.
PRESENTATION OF FINANCIAL INFORMATION
We are a South African company and the majority of our operations are located in our home
country. Accordingly, our books of account are maintained in South African Rand and our annual and
interim financial statements are prepared in accordance with International Financial Reporting
Standards (IFRS) as issued by the International Accounting Standards Board (IASB). Prior to
fiscal year ended June 30, 2008, our annual financial statements
(translated into U.S. dollars) were prepared and filed with the U.S.
Securities and Exchange Commission (SEC) in accordance
with generally accepted accounting principles in the United States
(U.S. GAAP). On December 21, 2007, the SEC
adopted rules allowing foreign private issuers that file Annual Reports on Form 20-F to file
financial statements with the SEC in accordance with IFRS as issued by the IASB without
reconciliation to U.S. GAAP. As per these new rules, we changed our
basis of presentation and included in this annual report our
consolidated financial statements prepared in accordance with IFRS as issued by the IASB,
translated into U.S. dollars. All financial information, except as otherwise noted, are stated in
accordance with IFRS as issued by the IASB.
In this annual report, we also present total cash costs and total cash costs per ounce,
which have been determined using industry standards promulgated by the Gold Institute and are
non-GAAP measures. The Gold Institute was a non-profit international industry association of
miners, refiners, bullion suppliers and manufacturers of gold products that ceased operation in
2002, which developed a uniform format for reporting production costs on a per ounce basis. The
Gold Institute has now been incorporated into the National Mining Association. The guidance was
first adopted in 1996 and subsequently revised in November 1999. An investor should not consider
these items in isolation or as alternatives to production costs, cost of sales or any other measure
of financial performance presented in accordance with IFRS as issued by the IASB. While the Gold
Institute has provided definitions for the calculation of total cash costs, the calculation of
total cash costs and total cash costs per ounce may vary significantly among gold mining companies
and, by themselves, do not necessarily provide a basis for comparison with other gold mining
companies. For further information, see Item 5. Operating and Financial Review and
Prospects Costs Reconciliation of Non-GAAP Measures.
We have included the U.S. dollar equivalent amounts of certain information and transactions in
Rand, Kina and A$. Unless otherwise stated, we have translated (i) balance sheet items at the noon
buying rate of the Federal Reserve Bank of New York on the last business day of the period (R7.80
per U.S.$1.00 as at June 30, 2008 and R7.04 per U.S.$1.00 as at June 30, 2007), (ii) acquisitions,
disposals and specific items included within equity at the rate prevailing at the date the
transaction was entered into and (iii) income statement items at the average rate for the year
(R7.26 per U.S.$1.00 for fiscal 2008, R7.20 per U.S.$1.00 for fiscal 2007, and R6.36 per U.S.$1.00
for fiscal 2006). Capital expenditures for fiscal 2009 have been translated at the rates used for
balance sheet items. By including these U.S. dollar equivalents in this annual report, we are not
representing that the Rand, Kina and A$ amounts actually represent the U.S. dollar amounts, as the
case may be, or that these amounts could be converted at the rates indicated.
3
FORWARD-LOOKING STATEMENTS
This annual report contains forward-looking statements within the meaning of the United
States Private Securities Litigation Reform Act of 1995 with respect to our financial condition,
results of operations, business strategies, operating efficiencies, competitive positions, growth
opportunities for existing services, plans and objectives of management, markets for stock and
other matters. In particular, among other statements, certain statements in Item 4. Information
on the Company, Item 5. Operating and Financial Review and Prospects and Item 11. Quantitative
and Qualitative Disclosures About Market Risk are forward-looking in nature. Statements in this
annual report that are not historical facts are forward-looking statements for the purpose of the
safe harbor provided by Section 21E of the Securities Exchange Act of 1934, as amended (the
Exchange Act), and Section 27A of the Securities Act of 1933, as amended.
These forward-looking statements, including, among others, those relating to our future
business prospects, revenues and income, wherever they may occur in this annual report and the
exhibits to this annual report, are necessarily estimates reflecting the best judgment of our
senior management and involve a number of risks and uncertainties that could cause actual results
to differ materially from those suggested by the forward-looking statements. As a consequence,
these forward-looking statements should be considered in light of various important factors,
including those set forth in this annual report. Important factors that could cause actual results
to differ materially from estimates or projections contained in the forward-looking statements
include, without limitation:
|
|
|
overall economic and business conditions in South Africa and elsewhere; |
|
|
|
|
the ability to achieve anticipated efficiencies and other cost savings in connection with
past and future acquisitions; |
|
|
|
|
fluctuations in the market price of gold; |
|
|
|
|
the occurrence of hazards associated with underground and surface gold mining; |
|
|
|
|
the occurrence of labor disruptions; |
|
|
|
|
availability, terms and deployment of capital; |
|
|
|
|
changes in government regulation, particularly mining rights and environmental regulation; |
|
|
|
|
fluctuations in exchange rates; |
|
|
|
|
currency devaluations/appreciations and other macroeconomic monetary policies; and |
|
|
|
|
socio-economic instability in South Africa and other countries in which we operate. |
We undertake no obligation to update publicly or release any revisions to these
forward-looking statements to reflect events or circumstances after the date of this annual report
or to reflect the occurrence of unanticipated events.
4
PART I
Item 1. IDENTITY OF DIRECTORS, SENIOR MANAGEMENT AND ADVISORS
Not applicable.
Item 2. OFFER STATISTICS AND EXPECTED TIMETABLE
Not applicable.
Item 3. KEY INFORMATION
SELECTED FINANCIAL DATA
The selected consolidated financial data below should be read in conjunction with, and
are qualified in their entirety by reference to, our consolidated financial statements and the
notes thereto and with Item 5. Operating and Financial Review and Prospects, both included
elsewhere in this annual report. Historical results are not necessarily indicative of results to be
expected for any future period.
SELECTED HISTORICAL CONSOLIDATED FINANCIAL DATA
We
are a South African company and the majority of our operations are
located in our home country. Accordingly, our books of account are
maintained in South African Rand and our annual and interim financial
statements are prepared in accordance with IFRS as issued by the
IASB. Prior to fiscal year ended June 30, 2008, our annual
financial statements (translated into U.S. dollars) were prepared and
filed with the SEC in accordance with U.S. GAAP. On December 21,
2007, the SEC, adopted rules allowing foreign private issuers that
file Annual Reports on Form 20-F to file financial statements
with the SEC in accordance with IFRS as issued by the IASB without
reconciliation to U.S. GAAP. As per these new rules, we changed our
basis of presentation and have included in this annual report our
consolidated financial statements prepared in accordance with IFRS as
issued by the IASB, translated into U.S. dollars.
The selected historical consolidated financial data for the last five fiscal
years are, unless otherwise noted, stated in accordance with IFRS as
issued by the IASB, and has been extracted from the more detailed
information and financial statements prepared in accordance with IFRS
as issued by the IASB, including our
audited consolidated financial statements as of June 30, 2008 and 2007 and for each of the years in
the three years ended June 30, 2008 and the related notes, which appear elsewhere in this annual
report. The historical consolidated financial data at June 30, 2006, 2005 and 2004, and for each of
the years in the two years ended June 30, 2005, has been extracted from our audited consolidated
financial statements not included in this annual report as adjusted for discontinued operations and
the accounting changes described below.
During fiscal 2008, we early adopted IAS 23 (Revised) Borrowing Costs. In accordance
with the Revised Standards transitional provisions, we designated July 1, 2000 (the earliest
commencement date of current qualifying projects) as the effective date and applied the
requirements of the Revised Standard to all qualifying projects for which the commencement date of
capitalization was on or after that date.
During fiscal 2008, we classified the assets and liabilities of the Cooke operation as held
for sale and also classified the results of this operation as discontinued operations for all
periods presented below in the selected historical financial data. Discontinued operations also
include the results of the Orkney and Australian operations that were classified as held for sale
and discontinued operations during fiscal 2007. These reclassifications were done in terms of IFRS
5 Non-Current Assets held for sale and Discontinued Operations. See note 14 of the consolidated
financial statements and Item 4. Information of the Company Business International
Operations, Information of the Company Business Orkney Operations and Item 4. Information
of the Company Business Cooke Operations.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
2005 |
|
2004 |
|
|
|
|
|
|
($ in millions, except per share amounts) |
|
|
|
|
Income Statement Data |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Revenue |
|
|
1,269 |
|
|
|
1,116 |
|
|
|
937 |
|
|
|
953 |
|
|
|
955 |
|
Operating profit/(loss) |
|
|
73 |
|
|
|
154 |
|
|
|
(104 |
) |
|
|
(322 |
) |
|
|
(73 |
) |
Loss from associates |
|
|
(11 |
) |
|
|
(3 |
) |
|
|
(17 |
) |
|
|
|
|
|
|
|
|
(Loss)/profit from
continuing operations before
taxation |
|
|
(39 |
) |
|
|
156 |
|
|
|
(91 |
) |
|
|
(517 |
) |
|
|
(3 |
) |
Taxation |
|
|
(65 |
) |
|
|
(39 |
) |
|
|
(22 |
) |
|
|
87 |
|
|
|
1 |
|
(Loss)/profit from
continuing operations |
|
|
(104 |
) |
|
|
117 |
|
|
|
(113 |
) |
|
|
(430 |
) |
|
|
(2 |
) |
Profit/(loss) from
discontinued operations |
|
|
74 |
|
|
|
(66 |
) |
|
|
22 |
|
|
|
(70 |
) |
|
|
(35 |
) |
Net (loss)/profit |
|
|
(30 |
) |
|
|
51 |
|
|
|
(91 |
) |
|
|
(500 |
) |
|
|
(37 |
) |
5
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
2005 |
|
2004 |
|
|
|
|
|
|
($ in millions, except per share amounts) |
|
|
|
|
Basic (loss)/earnings per
share from continuing
operations ($) |
|
|
(0.26 |
) |
|
|
0.29 |
|
|
|
(0.29 |
) |
|
|
(1.19 |
) |
|
|
(0.01 |
) |
Diluted (loss)/earnings per
share from continuing
operations ($) |
|
|
(0.26 |
) |
|
|
0.29 |
|
|
|
(0.29 |
) |
|
|
(1.19 |
) |
|
|
(0.01 |
) |
Basic (loss)/earnings per
share ($) |
|
|
(0.08 |
) |
|
|
0.12 |
|
|
|
(0.23 |
) |
|
|
(1.38 |
) |
|
|
(0.15 |
) |
Diluted (loss)/earnings per
share ($) |
|
|
(0.08 |
) |
|
|
0.12 |
|
|
|
(0.23 |
) |
|
|
(1.38 |
) |
|
|
(0.15 |
) |
Weighted average number of
shares used in the
computation of basic
(loss)/earnings per share |
|
|
400,750,167 |
|
|
|
397,910,797 |
|
|
|
393,727,012 |
|
|
|
361,816,512 |
|
|
|
253,558,000 |
|
Weighted average number of
shares used in the
computation of diluted
(loss)/earnings per share |
|
|
402,894,248 |
|
|
|
402,382,011 |
|
|
|
393,727,012 |
|
|
|
361,817,512 |
|
|
|
254,888,334 |
|
Dividends per share |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
0.05 |
|
|
|
0.10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Other Financial Data |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash cost per ounce of gold
from continuing operations
($/oz) (1) |
|
|
591 |
|
|
|
479 |
|
|
|
440 |
|
|
|
383 |
|
|
|
339 |
|
Total cash cost per ounce of
gold ($/oz) (1) |
|
|
589 |
|
|
|
486 |
|
|
|
436 |
|
|
|
379 |
|
|
|
333 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
2005 |
|
2004 |
|
|
($ in millions) |
Balance Sheet Data |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Assets |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Property, plant and equipment |
|
|
3,531 |
|
|
|
3,484 |
|
|
|
3,263 |
|
|
|
3,385 |
|
|
|
3,731 |
|
Non-current assets
classified as held for sale |
|
|
197 |
|
|
|
182 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Other assets |
|
|
982 |
|
|
|
1,494 |
|
|
|
1,432 |
|
|
|
1,433 |
|
|
|
1,256 |
|
Total assets |
|
|
4,710 |
|
|
|
5,160 |
|
|
|
4,695 |
|
|
|
4,818 |
|
|
|
4,987 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Equity and liabilities |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total equity |
|
|
3,172 |
|
|
|
3,366 |
|
|
|
3,249 |
|
|
|
3,489 |
|
|
|
3,464 |
|
Borrowings (current and
non-current) |
|
|
525 |
|
|
|
653 |
|
|
|
500 |
|
|
|
563 |
|
|
|
461 |
|
Other liabilities |
|
|
1,013 |
|
|
|
1,141 |
|
|
|
946 |
|
|
|
766 |
|
|
|
1,062 |
|
Total equity and liabilities |
|
|
4,710 |
|
|
|
5,160 |
|
|
|
4,695 |
|
|
|
4,818 |
|
|
|
4,987 |
|
|
|
|
(1) |
|
Total cash costs and total cash costs per ounce are
non-GAAP measures. We have calculated cash costs per ounce
by dividing total cash costs, as determined using the
guidance provided by the Gold Institute, by gold ounces
sold for all periods presented. The Gold Institute was a
non-profit industry association comprised of leading gold
producers, refiners, bullion suppliers and manufacturers.
This institute has now been incorporated into the National
Mining Association. The guidance was first issued in 1996
and was revised in November 1999. Total cash costs, as
defined in the guidance provided by the Gold Institute,
include mine production costs, transport and refinery
costs, applicable general and administrative costs, costs
associated with movements in production inventories and ore
stockpiles, ongoing environmental rehabilitation costs as
well as transfers to and from deferred stripping and costs
associated with royalties. |
6
|
|
|
|
|
Ongoing employee termination
costs are included, however, employee
termination costs
associated with major restructuring and shaft closures are
excluded. Total cash costs have been calculated on a
consistent basis for all periods presented. Changes in cash
costs per ounce are affected by operational performance, as
well as changes in the currency exchange rate between the
Rand and the U.S. dollar. Because total cash costs and
total cash costs per ounce are non-GAAP measures, they
should therefore not be considered by investors in
isolation or as an alternative to production costs, cost of
sales, or any other measure of financial performance
calculated in accordance with IFRS as issued by the IASB.
While the Gold Institute has provided a definition for the
calculation of total cash costs and total cash costs per
ounce, the calculation of cash costs per ounce may vary
from company to company and may not be comparable to other
similarly titled measures of other companies. However, we
believe that cash costs per ounce is a useful indicator to
investors and management of a mining companys performance
as it provides (1) an indication of the cash generating
capacities of the mining operations, (2) the trends in cash
costs as the companys operations mature, (3) a measure of
a companys performance, by comparison of cash costs per
ounce to the spot price of gold and (4) an internal
benchmark of performance to allow for comparison against
other companies. For further information, see Item 5.
Operating and Financial Review and Prospects Costs
Reconciliation of non-GAAP measures. |
7
EXCHANGE RATES
Unless otherwise stated, balance sheet item amounts are translated from Rand to U.S.
dollars at the exchange rate prevailing on the last business day of the period (R7.80 per U.S.$1.00
as at June 30, 2008), except for acquisitions, disposals and specific items included within equity
that are converted at the exchange rate prevailing on the date the transaction was entered into,
and income statement item amounts that are translated from Rand to U.S. dollars at the average
exchange rate for the period (R7.26 per U.S.$1.00 for fiscal 2008).
As
of October 21, 2008, the noon buying rate of the Federal Reserve Bank of New York per
U.S.$1.00 was R10.67.
The following table sets forth, for the past five fiscal years, the average and period
end noon buying rates in New York City for cable transfers in Rand and, for the past six months,
the high and low noon buying rates in New York City for cable transfers in Rand, in each case, as
certified for customs purposes by the Federal Reserve Bank of New York for Rand expressed in Rand
per U.S.$1.00.
|
|
|
|
|
|
|
|
|
Fiscal Year Ended |
|
|
|
|
June 30, |
|
Average(1) |
|
Period End |
2004 |
|
|
6.89 |
|
|
|
6.23 |
|
2005 |
|
|
6.18 |
|
|
|
6.67 |
|
2006 |
|
|
6.36 |
|
|
|
7.17 |
|
2007 |
|
|
7.20 |
|
|
|
7.04 |
|
2008 |
|
|
7.26 |
|
|
|
7.80 |
|
|
|
|
|
|
|
|
|
|
Month of |
|
High |
|
Low |
May 2008 |
|
|
7.76 |
|
|
|
7.47 |
|
June 2008 |
|
|
8.12 |
|
|
|
7.70 |
|
July 2008 |
|
|
7.92 |
|
|
|
7.31 |
|
August 2008 |
|
|
7.90 |
|
|
|
7.24 |
|
September 2008 |
|
|
8.28 |
|
|
|
7.77 |
|
October 2008
(through October 21, 2008) |
|
|
10.67 |
|
|
|
8.27 |
|
|
|
|
(1) |
|
The average of the noon buying rates provided by the
Federal Reserve Bank of New York on the last day of each
full month during the relevant period. |
Fluctuations in the exchange rate between Rand and the U.S. dollar will affect the dollar
equivalent of the price of ordinary shares on the Johannesburg Stock Exchange, which may affect the
market price of the ADSs on the New York Stock Exchange. These fluctuations will also affect the
dollar amounts received by owners of ADSs on the conversion of any dividends paid in Rand on
ordinary shares.
8
CAPITALIZATION AND INDEBTEDNESS
Not applicable.
9
REASONS FOR THE OFFER AND USE OF PROCEEDS
Not applicable.
10
RISK FACTORS
In addition to the other information included in this annual report and the exhibits, you
should also carefully consider the following factors related to our ordinary shares and ADSs. There
may be additional risks that we do not currently know of or that we currently deem immaterial based
on information currently available to us. Any of these risks could have a materially adverse effect
on our business, financial condition or results of operations, leading to a decline in the trading
price of our ordinary shares or our ADSs. The risks described below may, in retrospect, turn out to
be incomplete and therefore may not be the only risks to which we are exposed. Additional risks and
uncertainties not presently known to us or that we now believe are immaterial, could also adversely
affect our businesses, results of operations or financial condition. The order of presentation of
the risk factors below does not indicate the likelihood of their occurrence or the magnitude or the
significance of the individual risks. The risks described below could occur individually or
cumulatively and intensify in case of a cumulative occurrence.
Risks Relating to Our Business and the Gold Mining Industry
The profitability of our operations, and the cash flows generated by those operations, are affected
by changes in the Rand price of gold, such that a fall in the price of gold below our cash cost of
production for any sustained period may lead us to experience losses and to curtail or suspend
certain operations.
Substantially all of our revenues come from the sale of gold. Historically, the market
price for gold has fluctuated widely and has been affected by numerous factors over which we have
no control, including:
|
|
|
the demand for gold for industrial uses and for use in jewelry; |
|
|
|
|
international or regional political and economic trends; |
|
|
|
|
the strength or weakness of the U.S. dollar (the currency in which
gold prices generally are quoted) and of other currencies; |
|
|
|
|
financial market expectations regarding the rate of inflation; |
|
|
|
|
interest rates; |
|
|
|
|
speculative activities; |
|
|
|
|
actual or expected purchases and sales of gold bullion held by central
banks or other large gold bullion holders or dealers; |
|
|
|
|
forward sales by other gold producers; and |
|
|
|
|
the production and cost levels for gold in major gold-producing
nations, such as South Africa, China, the United States and Australia. |
In addition, the current demand for and supply of gold affects the price of gold, but not
necessarily in the same manner as current demand and supply affect the prices of other commodities.
Historically, gold has retained its value in relative terms against basic goods in times of
inflation and monetary crisis. As a result, central banks, financial institutions and individuals
hold large amounts of gold as a store of value and production in any given year constitutes a very
small portion of the total potential supply of gold. Since the potential supply of gold is large
relative to mine production in any given year, normal variations in current production will not
necessarily have a significant effect on the supply of gold or its price.
11
The volatility of gold prices is illustrated in the following table, which shows the
annual high, low and average of the afternoon London Bullion Market fixing price of gold in
U.S. dollars for the past ten calendar years:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Price per ounce |
|
|
|
|
High |
|
Low |
|
Average |
Calendar Year |
|
($) |
|
($) |
|
($) |
1998 |
|
|
313 |
|
|
|
273 |
|
|
|
294 |
|
1999 |
|
|
326 |
|
|
|
253 |
|
|
|
279 |
|
2000 |
|
|
313 |
|
|
|
264 |
|
|
|
282 |
|
2001 |
|
|
293 |
|
|
|
256 |
|
|
|
271 |
|
2002 |
|
|
332 |
|
|
|
278 |
|
|
|
309 |
|
2003 |
|
|
412 |
|
|
|
322 |
|
|
|
361 |
|
2004 |
|
|
427 |
|
|
|
343 |
|
|
|
389 |
|
2005 |
|
|
476 |
|
|
|
411 |
|
|
|
434 |
|
2006 |
|
|
725 |
|
|
|
525 |
|
|
|
604 |
|
2007 |
|
|
841 |
|
|
|
608 |
|
|
|
695 |
|
2008
(through October 21, 2008) |
|
|
1,011 |
|
|
|
741 |
|
|
|
775 |
|
On
October 21, 2008, the afternoon fixing price of gold on the London Bullion Market was
U.S.$772.00 per ounce.
While the aggregate effect of these factors is impossible for us to predict, if gold
prices should fall below our cash cost of production and remain at such levels for any sustained
period, we may experience losses and may be forced to curtail or suspend some or all of our
operations. In addition, we would also have to assess the economic impact of low gold prices on our
ability to recover any losses we may incur during that period and on our ability to maintain
adequate reserves. Our cash cost per ounce of gold sold from continuing operations was U.S.$591 in
fiscal 2008, U.S.$479 in fiscal 2007 and U.S.$440 in fiscal 2006.
As the majority of our production costs are incurred in Rand and other non-U.S. currencies, and
gold is sold in U.S. dollars, our financial condition could be materially harmed by an appreciation
in the value of the Rand and other non-U.S. currencies against the U.S. dollar.
Gold is sold throughout the world in U.S. dollars, but most of our operating costs are
incurred in Rand and other non-U.S. currencies. As a result, any significant and sustained
appreciation of the South African Rand or other non-U.S. currencies against the dollar will serve
materially to reduce our revenues and overall net income.
Estimations of our gold reserves are based on a number of assumptions, including assumptions as to
mining and recovery factors, future cash costs of production and the price of gold and may yield
less gold under actual production conditions than currently estimated.
The ore reserve estimates contained in this annual report are estimates of the mill
delivered quantity and grade of gold in our deposits and stockpiles. They represent the amount of
gold which we believe can be mined, processed and sold at prices sufficient to recover our
estimated future cash costs of production, remaining investment and anticipated additional capital
expenditures. Our ore reserves are estimated based upon a number of factors, which have been stated
in accordance with SEC Industry Guide 7. Our ore reserve estimates are calculated based on
estimates of:
|
|
|
future cash costs (which in some cases are assumed to decrease significantly); |
|
|
|
|
future gold prices; and |
|
|
|
|
future currency exchange rates. |
These factors, which are beyond our control, significantly impact these ore reserve
estimates. As a result, the reserve estimates contained in this annual report should not be
interpreted as assurances of the economic life of our gold and other precious metal deposits or the
future profitability of operations.
12
Since these ore reserves are estimates based on assumptions related to the factors
detailed above, should there be changes to these, we may in the future need to revise these
estimates. In particular, if our cash operating and production costs increase or do not decrease as
assumed (whether in dollar, Rand, or other non-U.S. currencies terms, or in relative terms due to appreciation of the Rand
and other non-U.S. currencies against the U.S. dollar) or the gold price decreases, the recovery of a portion of our ore reserves
may become uneconomical. This will, in turn, will lead us to reduce our estimated reserves.
In order to maintain gold production beyond the expected lives of our existing mines or to increase
production materially above projected levels, we will need to access additional reserves through
exploration or discovery.
Our operations have limited proven and probable reserves and exploration and discovery is
necessary to maintain current gold production levels at these operations. Exploration for gold and
other precious metals is speculative in nature, is frequently unsuccessful and involves many risks,
including those related to:
|
|
|
locating orebodies; |
|
|
|
|
identifying the metallurgical properties of orebodies; |
|
|
|
|
estimating the economic feasibility of mining orebodies; |
|
|
|
|
developing appropriate metallurgical processes; |
|
|
|
|
obtaining necessary governmental permits; and |
|
|
|
|
constructing mining and processing facilities at any site chosen for mining. |
Our exploration efforts might not result in the discovery of mineralization, and any
mineralization discovered might not result in an increase in our proven and probable reserves. To
access additional reserves, we will need to successfully complete development projects, including
extensions to existing mines and, possibly, that of new mines. Development projects would also be
necessary to access any new mineralization discovered through our exploration activities around the
world. We typically use feasibility studies to determine whether or not to undertake significant
development projects. Feasibility studies include estimates of expected or anticipated economic
returns, which are based on assumptions about:
|
|
|
future gold and other metal prices; |
|
|
|
|
anticipated tonnage, grades and metallurgical characteristics of ore to be mined and processed; |
|
|
|
|
anticipated recovery rates of gold and other metals from the ore, and |
|
|
|
|
anticipated total costs of the project, including capital expenditure and cash costs. |
Actual cash costs of production, production and economic returns may differ significantly from
those anticipated by our feasibility studies for new development projects.
It can take a number of years from the initial feasibility study until development is
completed and, during that time, the economic feasibility of production may change. In addition,
there are a number of uncertainties inherent in the development and construction of an extension to
an existing mine or any new mine, including:
|
|
|
the availability and timing of necessary environmental and governmental permits; |
|
|
|
|
the timing and cost of constructing mining and processing facilities, which can be considerable; |
|
|
|
|
the availability and cost of skilled labor, power, water and other materials; |
|
|
|
|
the accessibility of transportation and other infrastructure, particularly in remote locations; |
|
|
|
|
the availability and cost of smelting and refining arrangements; and |
|
|
|
|
the availability of funds to finance construction and development activities. |
We currently maintain a range of focused exploration programs, concentrating on areas not too
distant from our operational mines, as well as a number of prospective known gold mineralized
regions around the world. During fiscal years 2008 and 2007, the bulk of exploration expenditure
was allocated to activities in South Africa, Papua New Guinea (PNG) and Australia. However, there
is no assurance that any future development projects will extend the life of our existing mining
operations or result in any new commercial mining operations.
13
The costs associated with the pumping of water inflows from closed mines adjacent to our operations
could adversely affect our results of operations.
Certain of our mining operations are located adjacent to the mining operations of other mining
companies. A mine closure may have an adverse impact on the continued operations at an adjacent
mine if appropriate preventative steps are not taken. In particular, this impact can include the
ingress of underground water where pumping operations at the closed mine are suspended. Such
ingress could result in damage to property, operational disruptions and additional pumping costs,
which would adversely affect any one of our adjacent mining operations.
The supply of electricity and increases in the cost of power may adversely affect our results of
operations and our financial condition.
Each of our mining operations is dependent on a sufficient supply of electricity. The
electricity supply was interrupted by the South African governmental entity, ESKOM, during fiscal
2008 thereby halting production at certain of our mines. This led to management restructuring
operating processes to control and reduce our consumption of electricity at all our operations.
Nevertheless, an insufficient supply of electricity may adversely affect our results of operations
and financial condition.
As a result of ESKOMs planned capital expansion program to deal with the current power
constraints, an increase in rates charged to consumers costs has been approved by the National
Energy Regulator South Africa (NERSA). More increases are anticipated in the future, which will
also be driven by increases in input costs, primarily coal. These increases will have a negative
impact on our results of operations going forward.
As we currently do not enter into forward sales, commodity, derivatives or hedging arrangements
with respect to our future gold production, we are exposed to the impact of any significant
decrease in the gold price.
As a general rule, we sell our gold at the prevailing market price. Currently, we
generally do not enter into forward sales, commodity, derivative or hedging arrangements to
establish a price in advance for the sale of future gold production, although we may do so in the
future. As a result, we may realize the benefit of any short-term increase in the gold price, but
are not protected against decreases in the gold price, and if the gold price decreases
significantly, our revenues may be materially adversely affected.
We may experience problems in identifying, financing and managing new acquisitions and integrating
them with our existing operations.
Acquiring new gold mining operations involves a number of risks including:
|
|
|
our ability to identify appropriate assets for acquisition and/or to negotiate acquisitions on
favorable terms; |
|
|
|
|
obtaining the financing necessary to complete future acquisitions; |
|
|
|
|
difficulties in assimilating the operations of the acquired business; |
|
|
|
|
difficulties in maintaining our financial and strategic focus while integrating the acquired business; |
|
|
|
|
problems in implementing uniform standards, controls, procedures and policies; |
|
|
|
|
increasing pressures on existing management to oversee a rapidly expanding company; and |
|
|
|
|
to the extent we acquire mining operations outside South Africa or Australasia, encountering
difficulties relating to operating in countries in which we have not previously operated. |
Our ability to make successful acquisitions and any difficulties or time delays in achieving
successful integration of any of such acquisitions could have a material adverse effect on our
business, operating results, financial condition and share price.
Certain factors may affect our ability to support the carrying value of our property, plant and
equipment, goodwill and other assets on our balance sheet.
We review and test the carrying value of our assets on an annual basis when events or changes
in circumstances suggest that the carrying amount may not be recoverable.
If there are indications that impairment may have occurred, we prepare estimates of expected
future cash flows for each group of assets. These estimates of future cash flows are prepared at
the lowest level for which identifiable cash flows are identified as being independent of the cash
flows of other mining assets and liabilities. Expected future cash flows are inherently uncertain,
and could materially change over time. Such cash flows are significantly affected by reserve and
production estimates, together with economic factors such as spot and forward gold prices, discount
rates, currency exchange rates, estimates of costs to produce reserves and future capital
expenditures.
14
As of June 30, 2008, we have substantial amounts of property, plant and equipment, goodwill
and other assets on our consolidated balance sheets. We have recorded impairment charges relating
to these assets and, if any one or a combination of the uncertainties described above occur,
management may be required to recognize further impairment charges, which could adversely affect
our financial results and condition.
Given the nature of mining and the type of gold mines we operate, we face a material risk of
liability, delays and increased cash costs of production from environmental and industrial
accidents and pollution.
The business of gold mining by its nature involves significant risks and hazards,
including environmental hazards and industrial accidents. In particular, hazards associated with
underground mining include:
|
|
|
Rock bursts; |
|
|
|
|
seismic events; |
|
|
|
|
underground fires; |
|
|
|
|
cave-ins or falls of ground; |
|
|
|
|
discharges of gases and toxic chemicals; |
|
|
|
|
release of radioactive hazards; |
|
|
|
|
flooding; |
|
|
|
|
pillar mining |
|
|
|
|
accidents; and |
|
|
|
|
other conditions resulting from drilling, blasting and the removal and
processing of material from a deep-level mine. |
Hazards associated with open cast mining (also known as open-pit mining) include:
|
|
|
flooding of the open-pit; |
|
|
|
|
collapse of the open-pit walls; |
|
|
|
|
accidents associated with the operation of large open-pits and rock transportation equipment; and |
|
|
|
|
accidents associated with the preparation and ignition of large-scale open-pit blasting operations. |
Hazards associated with waste-rock mining include:
|
|
|
accidents associated with operating a waste dump and rock transportation; |
|
|
|
|
pillar mining; and |
|
|
|
|
production disruptions caused by weather. |
We are at risk of experiencing any or all of these environmental or other industrial hazards.
The occurrence of any of these hazards could delay production, increase cash costs and result in
our financial liability.
The nature of our mining operations presents safety risks.
The environmental and industrial risks identified above also present safety risks for our
operations and our employees and can lead to the suspension and potential closure of operations for
indeterminate periods. For example, in October 2007, an incident occurred at the Elandsrand
operation involving a compressed pipe column which broke off below the shaft surface bank and fell
to the bottom of the men-and-material shaft, causing extensive damage to the shaft steel work and
electrical cables. The incident resulted in 3,000 workers being underground for more than 30 hours.
Mining operations were temporarily suspended for 42 days to allow for repairs to be undertaken at
the shaft. These and other safety risks, even in situations where no injuries occur, can have a
material adverse effect on our operations and production.
Our insurance coverage may prove inadequate to satisfy future claims against us.
We have third-party liability coverage for most potential liabilities, including
environmental liabilities. While we believe that our current insurance coverage for the hazards
described above is adequate and consistent with industry practice, we may be subject to liability
for pollution (excluding sudden and accidental pollution) or other hazards against which we have
not insured or cannot insure, including those in respect of past mining
15
activities. Further, we maintain and intend to continue to maintain, property and liability
insurance consistent with industry practice, but such insurance contains exclusions and limitations
on coverage. In addition, there can be no assurance that insurance will continue to be available at
economically acceptable premiums. As a result, in the future, our insurance coverage may not cover
the extent of claims against us for environmental or industrial accidents or pollution.
Our operations may be negatively impacted by inflation.
Our operations have been materially affected by inflation in recent years. At June 30,
2008, inflation in South Africa was 11.6%, a high level in recent years and may rise further. In
addition, working costs and wages especially, have increased considerably over the past three years
resulting in significant cost pressures for the mining industry. Our profits and financial
condition could also be affected adversely in the absence of a concurrent devaluation of the Rand
and an increase in the price of gold.
The socio-economic framework in the regions in which we operate may have an adverse effect on our
operations and profits.
We have operations in South Africa and PNG. As a result, changes or instability to the
economic or political environment in any of these countries or in neighboring countries could
affect an investment in us. It is difficult to predict the future political, social and economic
direction in these countries, or any other country in which we operate, and the impact government
decisions may have on our business.
Actual and potential shortages of production inputs may have an adverse effect on our operations
and profits.
Our results of operations may be affected by the availability and pricing of raw
materials and other essential production inputs. The price of raw materials may be substantially
affected by changes in global supply and demand, along with weather conditions, governmental
controls and other factors. A sustained interruption to the supply of any of these materials would
require us to find acceptable substitute suppliers and could require us to pay higher prices for
such materials. Any significant increase in the prices of these materials would increase our
operating costs and affect production considerations.
Our financial flexibility could be materially constrained by exchange control regulations as
imposed by the South African Reserve Bank (SARB).
In terms of South Africas exchange control regulations, the export of capital from South
Africa is restricted. As a result, our ability to raise and deploy capital outside South Africa is
limited. In particular, we are:
|
|
|
generally not permitted to export capital from South Africa, to hold foreign
currency or incur indebtedness denominated in foreign currencies without the
approval of the South African exchange control authorities; |
|
|
|
|
generally not permitted to acquire an interest in a foreign venture without the
approval of the South African exchange control authorities and first having
complied with the investment criteria of the South African exchange control
authorities; |
|
|
|
|
generally required to repatriate to South Africa profits of foreign operations; and |
|
|
|
|
limited in our ability to utilize profits of one foreign business to finance
operations of a different foreign business. |
These restrictions could hinder our normal corporate functioning, including our ability
to make foreign investments and procure foreign currency denominated financings in the future.
Since 1995, certain exchange controls in South Africa have been relaxed. The extent to
which the South African government may further relax such exchange controls cannot be predicted
with certainty, although the government has committed itself to a gradual approach to the
relaxation of exchange control. Because South Africa has a fully floating exchange rate and a
flexible interest rate policy, this could result in a rapid depreciation of the Rand exchange rate
relative to worlds currencies which could serve to stem this withdrawal and could also result in
an increase in interest rates due to the depreciation of the Rand.
We compete with mining and other companies for key human resources.
We compete with mining and other companies on a global basis to attract and retain key human
resources at all levels with the appropriate technical skills and operating and managerial
experience necessary to continue to operate our business. The global shortage of key mining
industry human resource skills, including geologists, mining engineers, metallurgists and skilled
artisans has been exacerbated in the current environment of increased mining activity across the
globe. There can be no assurance that we will attract and retain skilled and
16
experienced employees and, should we lose any of our key personnel, our business may be harmed and
our results of operations and financial condition could be adversely affected.
Since our South African labor force has substantial trade union participation, we face the risk of
disruption from labor disputes and new South African labor laws.
Despite a history of positive and constructive engagement with labor unions, there are
periods during which the various stakeholders are unable to agree on dispute resolution processes.
Disruptive activities on the part of labor, which normally differ in intensity, then become
unavoidable. Due to the high level of union membership among our employees, we are at risk of
having, and have experienced in recent years, production stoppages for indefinite periods due to
strikes and other disputes. Significant labor disruptions have affected our operations and
financial condition before and we are not able to predict whether or not we will experience
significant labor disputes in the future.
South African employment law sets out minimum terms and conditions of employment for
employees. Though these minimum terms and conditions may be improved by agreements between us and
the trade unions, the prescribed minimum terms and conditions forms the benchmark for all
employment contracts.
We are required to submit a report in terms of South African employment law detailing the
progress made towards achieving employment equity in the workplace. In the event this report is not
submitted, we could incur substantial penalties.
Developments in South African employment law may increase our cash costs of production or
alter our relationship with our employees and trade unions, which may have an adverse effect on our
business, operating results and financial condition.
We may suffer adverse consequences as a result of our reliance on outside contractors to conduct
our operations.
A portion of our operations are currently conducted by outside contractors. As a result,
our operations are subject to a number of risks, including:
|
|
|
negotiating agreements with contractors on acceptable terms; |
|
|
|
|
the inability to replace a contractor and its operating equipment in the event that either
party terminates the agreement; |
|
|
|
|
reduced control over those aspects of operations which are the responsibility of the contractor; |
|
|
|
|
failure by a contractor to perform in terms of its agreement with us; |
|
|
|
|
interruption of operations in the event that a contractor ceases to operate due to insolvency
or other unforeseen events; |
|
|
|
|
failure of a contractor to comply with applicable legal and regulatory requirements, to the
extent it is responsible for such compliance; and |
|
|
|
|
contractors problems regarding management of its workforce, labor unrest or other employment
issues. |
In addition, we may incur liability to third parties as a result of the actions of its
contractors. The occurrence of one or more of these risks could have a material adverse effect on
our business, operational results and financial condition. See Directors, Senior Management and
EmployeesEmployees.
HIV
& AIDS poses risks to us in terms of productivity and costs.
The
incidence of HIV & AIDS in South Africa and PNG, which is forecast to increase over the
next decade, poses risks to us in terms of potentially reduced productivity, and increased medical
and other costs. If a significant increase in the incidence of HIV
& AIDS infection and HIV & AIDS-related diseases among the workforce over the next several years occurs, this may have an
adverse impact on our operations, projects and financial status.
The cost of occupational healthcare services may increase in the future.
Our operations in South Africa are subject to health and safety regulations which could
impose significant costs and burdens. The present Mine Health and Safety Act 29 of 1996 (Mine
Health and Safety Act) imposes various duties on us at our mines, and grants the authorities broad
powers to, among other things, close unsafe mines and order corrective action relating to health
and safety matters.
17
The Occupational Diseases in Mines and Works Act 78 of 1973, or the Occupational Diseases
Act, governs the payment of compensation and medical costs related to certain illnesses contracted
by persons employed in mines or at sites where activities ancillary to mining are conducted.
Occupational healthcare services are available to our employees from our existing healthcare
facilities in South Africa. There is a risk that the cost of providing such services could increase
in future depending on changes in the nature of underlying legislation and the profile of our
employees. This increased cost, should it transpire, is currently indeterminate. We have embarked
on a number of initiatives focused on improving the quality of life of our workforce, although
there can be no guarantee that such initiatives will not be adversely affected by increased costs.
Laws governing mineral rights affect our business.
We are governed by the South African Mineral and Petroleum Resources Development Act 2002
(MPRDA). See RegulationHealth and Safety MattersSouth Africa for a description of the
principal objectives set out in the MPRDA.
Under the MPRDA, tenure over established mining operations is secured for up to 30 years
(and renewable for periods not exceeding 30 years each thereafter), provided that mining companies
apply for new order mining rights over existing operations within five years of May 1, 2004 or
before the existing right expires, whichever is the earlier date and fulfill requirements specified
in the MPRDA and the Broad-Based Socio-Economic Empowerment Charter for the South African mining
industry (Mining Charter).
The Mining Charter was signed by government and stakeholders in October 2002, and
contains principles relating to the transfer, over a 10-year period, of 26% of South Africas
mining assets (as equity or attributable units of production) to Historically Disadvantaged South
Africans (HDSAs), as defined in the Mining Charter. An interim target of 15% HDSA participation
over five years has also been set and to this end, the South African mining industry has committed
to securing financing to fund participation by HDSAs in an amount of R100.0 billion within the
first five years of the Mining Charters tenure. The Mining Charter provides for the review of the
participation process after five years to determine what further steps, if any, are needed to
achieve target participation of 26%. In order to measure progress in meeting the requirements of
the Mining Charter, companies are required to complete a Scorecard, in which the levels of
compliance with the objectives of the Mining Charter can be ticked off after five and ten years,
respectively. The Mining Charter and Scorecard require programs for black economic empowerment and
the promotion of value-added production, such as jewelry-making and other gold fabrication, in
South Africa. In particular, targets are set out for broad-based black economic empowerment in the
areas of human resources and skills development; employment equity; procurement and beneficiation.
In addition, the Mining Charter addresses socio-economic issues, such as migrant labor, mine
community and rural development and housing and living conditions.
We actively carry out mining and exploration activities in all of our material mineral
rights areas. All of our South African operations have been granted their mining licenses. We
will be eligible to apply for new licenses over existing operations, provided that we comply with
the Mining Charter. We have taken steps to comply with the expected provisions of the Mining
Charter, such as promoting value-added production, exploring black empowerment initiatives and
increasing worker participation. Failure to comply with the conditions of the mining licenses could
have a material adverse effect on our operations and financial condition.
The MPRDA also makes reference to royalties payable to the South African state in terms
of the envisaged Mineral and Petroleum Resources Royalty Bill which has not yet been enacted. The
fourth draft of the Mineral and Petroleum Resources Royalty Bill was tabled in the South African
government on August 21, 2008 and provides for the payment of a royalty according to a formula
based on earnings before interest, tax and depreciation, after the deduction of capital
expenditure. This rate is then applied to revenue to calculate the royalty amount due, with a
minimum of 0.5% and a maximum of 5% for gold. It is estimated that the formula could translate to
a royalty rate of more than 2% of gross sales in terms of current pricing assumptions. The latest
proposal results in a large increase from the 1.5% rate proposed in the second draft in 2006. The
royalty is to become effective on May 1, 2009, if the Bill is passed by the South African
government in its current form. The introduction of the Mining and Petroleum Royalty Act will have
an adverse impact on the profits generated by our operations in South Africa.
In PNG, the mining license for Hidden Valley was approved in March 2005. Once production
in PNG is commenced, our PNG mining operations will be subject to royalty payments to the
government of PNG. Should we desire to expand any of our initiatives in PNG operations into
additional areas under exploration, these operations would need to convert the existing exploration
licenses prior to the start of mining, and that process could require landowner title approval.
There can be no assurance that any approval would be received. Please also see Regulation for
further information.
18
We are subject to extensive environmental regulations.
As a gold mining company, we are subject to extensive environmental regulation. We have
experienced and expect to continue to experience increased cash costs of production arising from
compliance with South African and PNG environmental laws and regulations. The MPRDA, certain other
environmental legislation and the administrative policies of the South African government regulate
the impact of our prospecting and mining operations on the environment.
Pursuant to these regulations, upon the suspension, cancellation, termination or lapsing
of a prospecting permit or mining authorization in South Africa, we will remain liable for
compliance with the provisions of the MPRDA, including any rehabilitation obligations. This
liability will continue until such time as the South African Department of Minerals and Energy
(DME) certifies that we have complied with such provisions.
In the future, we may incur significant costs associated with complying with the
increasingly stringent requirements being imposed under new legislation and regulations. This may
include the need to increase and accelerate expenditure on environmental rehabilitation and to
alter provisions for this expenditure, which could have a material adverse effect on our results
and financial condition. We may also face increased environmental costs should other mines in the
vicinity of our mines fail to meet their obligations with regard to the pumping or treatment of
water.
The South African government has reviewed requirements imposed upon mining companies to
ensure environmental restitution. For example, following the introduction of an environmental
rights clause in South Africas constitution, a number of environmental legislative reform
processes have been initiated. Legislation passed as a result of these initiatives has tended to be
materially more onerous than laws previously applied in South Africa. Examples of such legislation
include the MPRDA, the South African National Nuclear Regulator Act 1999, the South African
National Water Act of 1998 and the South African National Environmental Management Act 1998, which
include stringent polluter-pays provisions. The adoption of these or additional or more
comprehensive and stringent requirements, in particular with regard to the management of hazardous
waste, the pollution of ground and ground-water systems and the duty to rehabilitate closed mines,
may result in additional costs and liabilities.
Our PNG operations are also subject to various laws and regulations relating to the
protection of the environment, which are similar in scope to those of South Africa.
Investors in the United States may have difficulty bringing actions, and enforcing judgments,
against us, our directors and our executive officers based on the civil liabilities provisions of
the federal securities laws or other laws of the United States or any state thereof.
We are incorporated in South Africa. Each of our directors and executive officers (and
our independent registered public accounting firm) reside outside of the United States.
Substantially all of the assets of these persons and substantially all of our assets are located
outside the United States. As a result, it may not be possible for investors to enforce a judgment
against these persons or ourselves obtained in a court of the United States predicated upon the
civil liability provisions of the federal securities or other laws of the United States or any
state thereof. A foreign judgment is not directly enforceable in South Africa, but constitutes a
cause of action which will be enforced by South African courts provided that:
|
|
|
the court that pronounced the judgment had jurisdiction to entertain the
case according to the principles recognized by South African law with
reference to the jurisdiction of foreign courts; |
|
|
|
|
the judgment is final and conclusive; |
|
|
|
|
the judgment has not lapsed; |
|
|
|
|
the recognition and enforcement of the judgment by South African courts
would not be contrary to public policy, including observance of the rules
of natural justice which require that the documents initiating the United
States proceeding were properly served on the defendant and that the
defendant was given the right to be heard and represented by counsel in a
free and fair trial before an impartial tribunal; |
|
|
|
|
the judgment does not involve the enforcement of a penal or revenue law; and |
|
|
|
|
the enforcement of the judgment is not otherwise precluded by the
provisions of the Protection of Business Act 99 of 1978, as amended, of the
Republic of South Africa. |
19
Compliance with new and changing corporate governance and public disclosure requirements adds
uncertainty to our compliance policies and increases our costs of compliance.
Laws, regulations and standards relating to accounting, corporate governance and public
disclosure, new SEC regulations and other listing regulations applicable to us are subject to
change and can create uncertainty for companies like us. New or changed laws, regulations and standards could lack specificity or be
subject to varying interpretations. Their application in practice may evolve over time as new
guidance is provided by regulatory and governing bodies. This could result in continuing
uncertainty regarding compliance matters and higher costs of compliance as a result of ongoing
revisions to such governance standards.
Pursuant to Section 404 of the Sarbanes-Oxley Act of 2002, we are required to furnish a
report by our management on our internal control over financial reporting. The report in this
annual report contains, among other matters, an assessment of the effectiveness of our internal
control over financial reporting as of the end of the fiscal year, including a statement as to
whether or not our internal controls over financial reporting are effective. We are required to
have our independent registered public accounting firm publicly disclose their conclusions
regarding the evaluation.
During fiscal 2007, we identified certain material weaknesses in our internal controls
over financial reporting, in particular relating to the information technology control environment
and the financial reporting closing process which led to material adjustments being required in our
financial statements and which also negatively impacted the report issued by our independent
registered public accounting firm regarding our internal controls over financial reporting. We made
improvements to our internal control over financial reporting during fiscal 2008 to mediate these
material weaknesses, and concluded that the controls related to the remediation of the material
weaknesses previously disclosed in the 2007 Annual Report on Form 20-F were designed, in place and
operating effectively for a sufficient period of time for management to determine that each of the
material weaknesses was remediated as of June 30, 2008. See Item 15. Disclosure Controls and
Procedures.
We are committed to maintaining high standards of corporate governance and public
disclosure, and our efforts to comply with evolving laws, regulations and standards in this regard
have resulted in, and are likely to continue to result in, increased general and administrative
expenses.
Investors may face liquidity risk in trading our ordinary shares on the JSE Limited.
The primary listing of our ordinary shares is on the JSE Limited. Historically, the
trading volumes and liquidity of shares listed on the JSE have been low relative to other major
markets. The ability of a holder to sell a substantial number of our ordinary shares on the JSE in
a timely manner, especially in a large block trade, may be restricted by this limited liquidity.
See The Offer and ListingThe Securities Exchange in South Africa.
Because we have a significant number of outstanding share options and convertible debt instruments,
our ordinary shares are subject to dilution.
We have employee share option schemes as well as other share schemes. The employee share
option schemes came into effect in 1994, 2001 and 2003 respectively, and a new share scheme was
introduced in 2006. Our Board has authorized up to 14% of the issued share capital to be used for
these plans. Additionally, we have convertible uncollaterized fixed rate bonds in the amount of
U.S.$208 million which are due on May 21, 2009. These bonds may be converted into equity at the
option of the bondholder at any time after July 1, 2004 and up to and including May 15, 2009 at a
specific conversion price based on the outstanding principal amount divided by the conversion price
in effect on that date. As a result, shareholders equity interests in us are subject to dilution
to the extent of the future exercises of the options, through share schemes and convertible debt
instruments.
20
Item 4. INFORMATION ON THE COMPANY
BUSINESS
History and Development
We conduct underground and surface gold mining and related activities, including
exploration, processing and smelting. We are currently the third largest producer of gold in South
Africa, producing approximately 23.4% of the countrys annual gold output, and we ranked among the
top 10 gold producers in the world, with operations and projects in South Africa and PNG. Our gold
sales have increased from 650,312 ounces of gold in fiscal 1995 to approximately 1.9 million ounces
of gold in fiscal 2008. As at June 30, 2008, our mining operations reported total proven and
probable reserves of 50.5 million ounces, primarily from South African sources. In fiscal 2008, we
processed approximately 25.4 million tons of ore.
In fiscal 2008, approximately 95% of our total gold production took place in South
Africa, and approximately 5% in Australasia. In fiscal 2008, approximately 93% of our South African
gold came from underground mines, and approximately 7% came from our surface operations (which
include Kalgold opencast operation and Phoenix operation). For more detailed information about our
activities, see Item 4. Information on the Company Business Harmonys Mining Operations
Overview and the notes to the consolidated financial statements included in this annual report.
Mining is a highly regulated industry, and we operate under a variety of statutes and regulations.
For more detailed information about these statutes and regulations, see Item 4. Information on the
Company Regulation and Item 10. Additional Information Memorandum and Articles of
Association.
The majority of our exploration and evaluation done during fiscal 2008 has been focused
on PNG. Our PNG exploration and evaluation opportunities are handled through the international
office in Brisbane, Australia.
We were incorporated and registered as a public company in South Africa on August 25,
1950 (under registration number 1950/038232/06). We poured our first gold on September 11, 1954. In
the early 1970s, we merged with the Anglovaal mines, Merriespruit and Virginia, forming Harmony
Gold Mining Company Limited. In 1995, we were rejuvenated. We expanded from a single lease-bound
mining operation into an independent, world-class gold producer. We acquired additional mineral
rights in the Free State, Mpumalanga, Gauteng and North West provinces in South Africa when we
acquired Lydex in 1997, Evander in 1998, Kalgold in 1999, Randfontein in 2000, ARMgold in 2003 and
Avgold in 2004. In building our Australian portfolio, we acquired Hill 50 and New Hampton in
Western Australia in 2001 and 2002, respectively, and started our exploration portfolio in PNG with
projects in the Morobe province originally through our acquisition of Abelle in 2003. During
fiscal 2008, we disposed of several operations in South Africa and Australia. See Item 4.
Disposals.
Our principal executive offices are located at Randfontein Office Park, Corner of Main
Reef Road and Ward Avenue, Randfontein, 1760, South Africa and the telephone number at this
location is +27-11-411-2000.
South African Operations
In South Africa, we operate a total of 11 underground operations, one open cast mine, and
nine processing plants which are located in all of the currently known goldfields in the
Witwatersrand basin of South Africa as well as the Green Stone belt. These operations produced 1.8
million ounces in fiscal 2008, and South Africa represented approximately 94% (or 47.5 million
ounces) of our total proven and probable reserves. The deep level gold are located in four
provinces in this basin, being the Free State province, Mpumalanga, the West Rand Goldfields in
Gauteng province and the North West province. Surface operations are located in all these provinces
as well.
Ore from the shafts and surface material are treated at nine metallurgical plants in South
Africa, located near the operations (four in the Free State province, two in the North West
province, one in Mpumalanga and two in Gauteng). There are two plants on care and maintenance which
can be restarted if additional processing capacity is required (Joel and St. Helena plants in the
Free State province).
As part of our Back to Basics strategy, management reassessed and restructured the manner in
which operations are managed and evaluated. Each operation, consisting anywhere from a single
shaft to a group of shafts, is managed by a team headed up by a general manager. See Item 4.
Operational Strategy: Back to Basics and Harmonys Management Structure.
As a result of this reorganization, operations are classified as Underground or Surface,
as opposed to the previous classification of Growth, Quality, Leveraged or Surface. The
reportable segments in South Africa are as follows:
21
|
|
|
Tshepong, Phakisa, Bambanani, Doornkop, Elandsrand, Target, Evander
operations, Masimong, Virginia operations and Cooke operations
(classified as discontinued operations); and |
|
|
|
|
all other shafts and surface operations, including those that treat
historic sand dumps, rock dumps and tailings dams, are grouped
together under Other Underground or Other Surface. |
International Operations
Our interests internationally are currently mainly located in PNG and represent 6% (or 3.0
million ounces) of our total proven and probable reserves.
Our interests in Australia now consist solely of one site located at Mt. Magnet in
Western Australia. This site has been closed down and the plant has been put on care and
maintenance since December 2007. The South Kalgoorlie operational assets and tenements, which we
previously owned and which was also located in Western Australia, were sold to Dioro Exploration NL
(Dioro) on November 30, 2007.
The Mt. Magnet operations produced 77,097 ounces in fiscal 2008, compared to 136,428 ounces in
fiscal 2007. The decrease was due to the mine being placed on care and maintenance in December
2007. The South Kalgoorlie operations produced 27,778 ounces in fiscal 2008, compared to 88,371
ounces in fiscal 2007. The results for 2008 are for the five months up to the sale to Dioro. Ore
from the underground and surface material were treated at the two metallurgical plants in Australia
(one at Mt. Magnet and, prior to it being sold, at South Kalgoorlie). We classified the Western
Australia operations as held for sale in April 2007. These operations also met the criteria to be
classified as discontinued operations.
In July 2007, we entered into an agreement with Dioro pursuant to which Dioro acquired our
South Kalgoorlie assets. The total purchase price was A$45 million (U.S.$39.8 million), consisting
of both a cash and share component. The share component entailed the issuance of 11.4 million Dioro
shares valued at A$20 million (U.S.$17.7 million), and a cash component of A$25 million (U.S.$22.1
million). The transaction was subject to various conditions precedent, including a minimum capital
raising by Dioro of A$35 million (U.S.$30.9 million) by the completion date. On November 30, 2007,
all conditions precedent were satisfied, and the transaction was completed and accounted for on
that date.
During
fiscal 2008, we entered into an agreement with Monarch Gold Mining
Company (Monarch Gold) for the sale of our Mount
Magnet operations. The Mount Magnet
operations include Hill 50, Great Fingall, St George, Star and Big Bell mines, and comprises a
resource inventory of 2.7 million ounces of gold, tenements covering approximately 62,000 hectares,
166 exploration license blocks and a 2.7 million ton a year
capacity plant. However, subsequent to year-end, we were advised
that Monarch had placed itself in voluntary administration and, on
August 1, 2008, the Administrator indicated that Monarch will not
proceed with the proposed purchase and consequently the purchase
agreement has been terminated. We have since resumed
management of the Mt. Magnet operation which is still classified as
held for sale. See Recent Developments
In PNG, we, through our wholly-owned PNG-based subsidiaries, Morobe Consolidated Goldfields
Limited (Morobe) and Wafi Mining Limited (Wafi), own development and exploration prospects in
the Morobe Province. Following the end of fiscal 2008, Newcrest Mining Limited (Newcrest)
acquired a 30.01% interest in our PNG assets and tenements (See Recent Developments). We, in a
joint venture with Newcrest, are in the process of building the Hidden Valley mine, with project
completion expected by the middle of calendar 2009.
In addition, we completed a number of stand alone pre-feasibility studies (PFS) in
Golpu during the June 2007 quarter and in Wafi during the December 2007 quarter, which included the
Wafi gold resources and examined the development of three production scenarios:
|
|
|
Golpu stand alone (an update of the Golpu PFS scenario); |
|
|
|
|
Golpu + Link Zone (high grade lenses within Zone B); and |
|
|
|
|
Golpu + Link Zone + Non-Refractory gold ore (NRG1); |
The June 2007 PFS reports were subject to Harmony Gate Reviews (Gate Reviews) and a
Competent Persons Report (CPR). Neither the Gate Reviews nor the CPR identified any fatal flaws
in the PFS reports. However, a number of outstanding issues were identified and the December 2007
PFS report are still subject to the Gate Review process. The returns projected by the June 2007
studies did not meet the
22
requirements,
and it was decided then not to immediately proceed to the feasibility stage. Further studies are planned
for fiscal 2009 to address outstanding issues and to investigate alternative production scenarios
which may improve projected returns. PNG represents approximately 6% (or 2.99 million ounces) of
our proven and probable reserves.
Strategy
During fiscal year 2008, we endeavoured to focus on three key aspects all of which we have
delivered on during the year under review.
|
|
|
First, we undertook to review our operational performance and maintain
a clear operational focus. This entailed developing an understanding
of what our operations were capable of delivering, devising and
putting in place the plans to ensure delivery, and holding management
responsible for that delivery. |
|
|
|
|
Second, we assessed our assets, to focus our attention on those
operations that were core to the business and had the ability to be
profitable. At the same time, we identified and initiated joint
ventures we believed where these assets could better cater for the
medium- and longer-term health of the company and bring about greater
value. |
|
|
|
|
Finally, we undertook to improve the financial viability of the
business and to substantially overhaul the balance sheet. In so doing,
we focused on improving operational performance, combined with the
sale of non-core assets and partnering in joint ventures. We undertook
to identify opportunities to sustain and grow production. While our
exploration work in PNG continues, we are also about to begin with
some organic exploration work at Evander in South Africa. This element
of our strategy is at an early stage and will be an area of increased
attention during the year ahead. |
We believe that the following strengths provide us with a competitive advantage:
Leading market position in the attractive gold industry
|
|
|
We believe that our size and leading market position enables us to
undertake exploration and simultaneously develop multiple projects
around the world, as well as secure capital on competitive terms. |
|
|
|
|
The global gold industry offers a number of attractive industry
fundamentals from which we benefit. This includes the absence of
available substitutes, relatively high barriers to entry, and
increasing gold producer concentration. |
|
|
|
|
We are developing new mines at a planned lower cost per ounce than our
current operations, which we believe will help make them robust enough
to survive any margin squeeze and to withstand any reversal in the
gold price. We expect the gold price to continue its upward trend in
the medium term |
Significant reserves with long mine lives
|
|
|
Our ore reserves as of June 30, 2008 amounted to 50.5 million ounces
of gold spread across our assets in South Africa and PNG. This ore
reserve base is sufficient to support our existing production profile
in excess of 10 years at current production levels. Year-on-year
depletion accounted for a decrease of 1.9 million ounces in the
reserves. Corporate activity, the exclusion of operations held for
sale, restructuring of certain shafts and geological related changes
accounts for a further decrease of 5.7 million ounces of reserves. On
the positive side there is a net addition of 4.4 million ounces of
reserves from surface stockpiles. |
|
|
|
|
Of our 50.5 million ounces of reserves, 38.3 million ounces are
classified as above infrastructure and 12.2 million ounces are
classified as below infrastructure (reserves for which capital
expenditure has still to be approved). |
Highly attractive project pipeline
|
|
|
We have a diverse portfolio of gold development projects spread across South
Africa and PNG. These projects include Elandsrand, Doornkop, Tshepong and Phakisa
in South Africa, and Hidden Valley in PNG, which, when developed, could deliver up
to 1.4 million ounces of additional production by 2012. |
23
|
|
|
We believe the relatively higher grade of these South African deposits and/or
lower cost base will result in these ounces being produced at highly competitive
cash costs. This in turn may result in a reduction in our overall cash cost
position as these new projects are commissioned. |
|
|
|
|
In addition to these projects, we have a number of additional development
prospects that are being considered and progressed, including the processing of
sand dumps and tailings dams in our Mega Dumps projects, the processing of rock
dumps, and developing the Wafi/Golpu copper/gold deposit in PNG, which, when all
developed, could increase production by 1.0 million ounces per annum. |
|
|
|
|
We have also expanded our exploration skill base, evidenced by our progress in PNG. |
|
|
|
|
We formed Rand Uranium (Proprietary) Limited (Rand
Uranium), to which we will transfer our
Cooke assets to optimize the value of our uranium deposits. |
Positive gold market outlook
|
|
|
In the midst of volatile tumultuous global investment markets, the
gold market has demonstrated great resilience and a positive upside.
The price performance throughout fiscal 2008 supports our positive
outlook for gold and, given our operational imperatives, we will seek
to contain costs, increase output and optimize our margins. |
|
|
|
|
The gold price hit a high of U.S.$1,030 per ounce on March 17, 2008
and, while it was a more subdued U.S.$772 per ounce as of
October 21,
2008, this is 3% higher than it was for the same time the previous
year. |
|
|
|
|
We believe the fundamental drivers behind increased demand and
decreased new supply of gold will remain in the future, which will in
turn support a higher gold price over this period. As an unhedged gold
producer, we will benefit from a rising gold price environment. |
Increased focus on earnings margins and cost
|
|
|
Our aim remains to return to profitability. At an operational level we
have put in place an intensive process of business planning, with
benchmarks and targets we believe to be realistic. |
|
|
|
|
We are committed to lower our cost base and extensively benchmark our
costing parameters both internally among our operations, and
externally against other gold producers. Stringent cost cutting and
cost control programs have been implemented. |
|
|
|
|
We are confident that the benefits of our restructuring process and
ongoing cost focus will be sustained in the long term, and as a
result, our ability to withstand any future adverse market conditions
has been significantly enhanced. |
Conservative balance sheet and low gearing
|
|
|
We maintain a conservative gearing policy and seek to fund ongoing
capital expenditure (excluding growth projects) through cash generated
from existing operations. |
|
|
|
|
Our low level of gearing should provide us with the ability to utilize
debt to fund capital and development expenditure requirements for our
new projects. |
Experienced management team with significant industry expertise
|
|
|
Our senior management team consists of experienced mining executives
with extensive industry backgrounds combined with geological and
metallurgical expertise. |
|
|
|
|
Our senior management team has a proven track record in developing and
managing the operations under its control, and has demonstrated an
ability to optimize underperforming assets as well as developing new
projects around the world. |
24
Leading Black Economic Empowerment strategy
|
|
|
We are proud to be a South African company and fully embraces the
countrys transformation initiatives. We are 16% owned by African
Rainbow Minerals Limited (ARM Limited), a black empowerment company in which
our chairman, Patrice Motsepe, owns an interest. |
|
|
|
|
We believe that we have gone beyond the requirements of the Mining
Charter by ensuring that our HDSA partners are truly empowered, that
we are largely managed by a HDSA Board, and that we continue to engage
with black shareholders and/or partners to find more opportunities to
invest in BEE transactions and involve HDSA partners. |
|
|
|
|
We will continue to embrace empowerment as part of our growth strategy
and we acknowledge that empowerment forms a fundamental part of our
business into the future. |
Strategy of organic growth
Our organic growth strategy is focused on the extraction of high-quality ounces and developing
and operating our long-life mines. Through our back to basics approach of disciplined mining, we
aim to reduce costs and increase productivity. Our dedicated and participative management team
endeavours to meet production targets, reduce costs and optimize the orebodies for the benefit of
all our stakeholders.
Organic growth focused on high quality ounces
|
|
|
Our extensive experience and established track record of successfully identifying,
exploring and developing our own projects is a core component of our value
creation strategy. |
|
|
|
|
Our ongoing exploration program is focused on both on-mine exploration, which
targets resources within the economic radius of existing mines, and new mine
exploration, which targets promising early to advanced stage projects around the
world. |
|
|
|
|
We are currently expanding our production base in South Africa and PNG, with a
focus on developing new mines at competitive cash costs and upgrading the overall
quality of our portfolio. |
|
|
|
|
We currently have a diverse project pipeline, comprising five projects that are
well advanced and, if all developed, could deliver up to 1.4 million ounces of
low-cost production by 2012. These projects include Elandsrand New Mine, Doornkop
South Reef, Tshepong Sub 66 and Sub 71 Declines and Phakisa in South Africa, and
Hidden Valley in PNG, which, if all developed, would contribute to a reduction in
our overall cash costs per ounce when they come on-stream. |
|
|
|
|
In addition to these projects, we have a number of additional development
prospects that are being progressed, including surface sand dumps, rock dumps and
tailings dams, reviewing the potential of our uranium deposits, and developing the
Wafi/Golpu copper/gold deposit in PNG, which, when an investment decision is taken
by the board to develop them once feasibility studies are complete, could increase
production by up to 1.0 million ounces. |
|
|
|
|
We have also expanded our exploration skill base, evidenced by our progress in PNG. |
Operational Strategy: Back to Basics:
Our operational strategy is underpinned by the back to basics strategy of disciplined
mining, cost control, ore reserve management and efficiency.
Safety
We have dedicated a significant amount of attention to our safety initiatives during the year,
and have seen improvements. These initiatives have been a key part of our restructuring and
refocusing initiative, and also part of the broader transformation of the workplace.
The commitment to zero fatalities starts at the top of the company and has filtered to every
level through a conscious and programmatic
25
effort. The second round of a comprehensive safety
auditing program was completed in June 2008 including physical workplace audits, fall of ground regulations audits,
shaft audits and metallurgical audits. Key non-negotiable principles that have been agreed upon
include:
|
|
|
management to lead by example; |
|
|
|
|
continuous verbal communication with all team members; |
|
|
|
|
visible creation of awareness of safety-related issues; |
|
|
|
|
award and recognize safety achievements; and |
|
|
|
|
the involvement of all stakeholders. |
While the workforce is motivated to become involved in taking responsibility for their own
safety and that of their colleagues, a key management focus has been to improve underground
conditions. In this respect, emphasis has been placed on those areas that are deemed to be of the
highest potential risk, namely, shaft infrastructure and physical conditions in the workplace.
Again, in respect of the latter, the focus is on compliance with standards, the monitoring and
management of ground conditions and logistics to and from the workplace.
Empowered management teams
|
|
|
At each mining site, we have
established small, multi-disciplinary, focused management teams
responsible for planning and implementing the mining operations at the
site. Each of these teams is accountable for the results at its
particular site and reports directly to the Board. |
Active involvement and management
|
|
|
Annual operational goals and targets, including cost, volume and grade
targets are established in consultation with our executive committee
for each mining site. Each management team develops an operational
plan to implement the goals and targets for its mine site. Members of
our executive committee review and measure the results at each mining
site on a regular basis throughout the year. |
Focus on increased productivity
|
|
|
Gold mining in South Africa is labor intensive, accounting for about
50% of our South African operating costs. To control these costs, we
structures our operations to achieve maximum productivity with the
goal of having 60% of our workforce directly engaged in stoping, or
underground excavation, and development rock breaking activities. |
Commitment to cost control
|
|
|
We are committed to reducing our cost base and, to this end, we
benchmark our costing parameters both internally among our operations
and externally against other gold producers. |
Proactive maintenance practices
|
|
|
We apply a principle of appropriate maintenance which allows us to
spend capital commensurate with the life of a specified operation.
This principle ensures safe operation and reduces capital that may be
used ineffectively on mines that have a limited life. |
Implementation of new systems
|
|
|
We have implemented cost accounting systems and strict ore accounting
and ore reserve management systems to measure and track costs and ore
reserve depletion accurately, so as to enable us to be proactive in
our decision-making. |
Increasing consistency at our operations
|
|
|
We are committed to increasing the consistency of our operations, in
terms of both gold ore grades and production levels, in order to
extract optimal value from our orebodies. To achieve this, we are
continuing with our intensive program to significantly improve the
mining flexibility of our operations by increasing our development
expenditure and focusing on comprehensive ore |
26
|
|
|
reserve management. We have made significant progress on this objective, as evidenced by our
development rates. |
|
|
|
|
We are currently reviewing potential opportunities in respect of
certain deposits and assets which we may develop independently of our
core gold business, and in particular, our uranium assets, of which
the underground resources are not currently reflected on our balance
sheet or reserve statement. |
Selected acquisitions that diversify our operations and complement our competitive strengths
|
|
|
We have a long track-record of acquisitions, having completed over 25
transactions and successfully integrating each of these operations
into the Company. |
|
|
|
|
We possess broad and extensive gold mining experience gained through
the development and operation of both surface, opencast mines and
mechanized, underground mines. This breadth of expertise provides us
with a competitive advantage when evaluation acquisition
opportunities. |
Targeted disposals that will upgrade our overall portfolio quality
|
|
|
We have accumulated a diverse portfolio of assets, a number of which
are nearing the end of their productive lives for us and are
considered non-core to our business. However, these assets may be of
higher value to smaller producers who are less concerned about short
mine lives, and can still profitably operate these assets for a number
of years. |
|
|
|
|
As a result, we believe our disposal strategy will create value
through the targeted sale of these assets, which for us have
relatively higher cost bases and/or shorter mine lives. See
Disposals below. |
Initiatives that target specific opportunities
|
|
|
We acknowledge significant capital expenditure and a commitment to a
long time horizon are required to develop our projects into new mines.
However, we firmly believe that this is the foundation of our future,
and to this end, have made substantial investments in our major
projects both in South Africa and PNG. |
Principal Investments
We have concluded several other strategic transactions within and outside South Africa in
the last three fiscal years, which are summarized below.
On February 27, 2008, the Group acquired a 32.4% interest in Pamodzi Gold Limited (Pamodzi)
after disposing of its Orkney assets. See Item 4. Disposals.
In March 2007, we concluded negotiations with Rio Tinto plc (Rio Tinto) in which we
purchased Rio Tintos rights to the royalty agreement entered into prior to our acquisition of the
Hidden Valley and Kerimenge deposits in PNG. The remaining condition precedent, which was to obtain
approval of the relevant PNG minister on the recommendation of the Mining Advisory Council that the
royalty rights may be transferred to us, was met in March 2008. Our cost of U.S.$22.5 million was
met through the issue of shares and a cash payment of U.S.$2.5 million. The effect of the
transaction will be to reduce the cost of gold produced at Hidden Valley and all further extensions
to the project, mine life and reserves will be free of this royalty.
On December 8, 2006 we exchanged our Western Areas Limited (Western Areas) shares in
exchange for Gold Fields Limited (Gold Fields) ordinary shares. See Item 4. Disposals. We
received 15.7 million Gold Fields shares, issued at R135.02 (U.S.$19.15) per share, for our 44.9
million Western Areas shares. During the fiscal years 2008 and 2007, we disposed of our interest
in Gold Fields. See Item 4. Disposals.
On June 21, 2006, we announced that we acquired 37.8% of the issued share capital of Village
Main Reef Gold Mining Company Limited (Village) for an amount of R458,775 (U.S.$0.1 million). The
equity stake was purchased from ARM Limited at a price of SA 20 cents per share. Due to the fact
that the acquisition surpasses the 35% mark, we were obliged under the securities Regulation Code
on Takeovers and Mergers to extend an offer to the remaining shareholders of Village to acquire all
of their shares at the same price at which it acquired the
27
37.8% stake. On August 14, 2006, we
announced that minority shareholders holding 3,163 shares in Village (being 0.08% of the shares in respect of which the offer was made) had accepted its
offer. At June 30, 2008, we held 2,295,663 shares, representing 37.83% of the issued share capital
of Village. See Item 7. Related Party Transactions.
On March 9, 2006, we announced that we acquired a total of 44.9 million shares in Western
Areas for R2 billion (U.S.$321 million), representing a 29.2% stake. This was done by acquiring
37.37 million shares from Allan Gray and buying a total of 7.62 million shares on the open market.
To finance this acquisition, we entered into a term loan facility of R1.0 billion
(U.S.$280.8 million) with Rand Merchant Bank (RMB), for the purpose of partially funding the
acquisition of the 29.2% stake in Western Areas. See Item 7. Related Party Transactions.
Disposals
See Item 8. Recent Developments for post year-end disposals.
On February 27, 2008, we disposed of our Orkney operations to Pamodzi in exchange for 30
million listed ordinary shares, the market value of which was R345 million (U.S.$46.5 million).
On November 30, 2007 the South Kalgoorlie operations were sold to Dioro in exchange for 11.6
million listed ordinary shares, the market value of which was U.S.$17.5 million (A$20 million), as
well as a cash of U.S.$18.7 million (A$21 million). A loss of U.S.$8.76 million (A$9.8 million),
net of tax, was realized.
On August 24, 2007, the Group disposed of the remaining 13,095,079 ordinary Gold Fields
shares. The proceeds amounted to R1,310 million (U.S.$182.9 million), resulting in a loss of R459
million (U.S.$63.2 million).
In April 2007, the surface assets and metallurgical plant at Deelkraal was sold to Ogoerion
Construction CC for R98 million (U.S.$13.7 million). It was agreed that the purchase price be paid
in installments over a 24-month period.
In a range of transactions between January 22, 2007 and February 12, 2007, we disposed of
1,150,000 Gold Fields shares for U.S.$19.7 million. The total cost of these shares was
U.S.$21.4 million, resulting in a loss of U.S.$1.7 million. During May and June 2007, a further
1.5 million shares with a cost of U.S.$28.3 million were disposed of for U.S.$25.1 million,
resulting in a loss of U.S.$3.2 million.
On December 8, 2006, we disposed of our interest in Western Areas in exchange for ordinary
shares in Gold Fields. This was in terms of an offer by Gold Fields whereby every 100 Western
Areas Shares were exchanged for 35 Gold Fields shares.
On October 19, 2006, Randfontein 4 Shaft was sold to Simmer & Jack Limited for an amount of
R60 million (U.S.$8.5 million).
On March 31, 2006, we disposed of the entire share capital of Buffalo Creek Mines (Pty)
Ltd for A$24 million (U.S.$17.2 million). According to the agreement the A$24 million
(U.S.$17.2 million) was to be settled as follows: (i) A$4.3 million (U.S.$3.1 million) to be paid
in cash; (ii) 1,907,892 shares in GBS Gold International, valued at A$5 million (U.S.$3.6 million);
(iii) A$5 million (U.S.$3.6 million) to be paid in cash in September 2006; (iv) Shares in GBS Gold
International, equal in value to A$4.4 million (U.S.$3.1 million), to be issued in September 2006;
and (v) A$5.4 million (U.S.$3.8 million) to be paid in cash in September 2007. The net asset value
of Buffalo Creek Mines (Pty) Ltd was A$20.1 million (U.S.$14.2 million), resulting in a profit of
A$3.1 million (U.S.$3 million). Final settlement was received as per contract in September 2007.
On January 18, 2006, we disposed of our investment in Atlas Gold Limited for
A$0.2 million (U.S.$0.15 million). The investment of 500,000 shares was carried at a total cost of
A$0.1 million (U.S.$0.07 million), resulting in a profit of A$0.1 million (U.S.$0.07 million).
On December 29, 2005, we disposed of our investment in San Gold Corporation for R19
million (U.S.$3.1 million). The investment was carried at a total cost of R20 million (U.S.$3.2
million), resulting in a loss of R1 million (U.S.$0.1 million).
On November 16, 2005, we disposed of the remaining portion of the Gold Fields investment
purchased in fiscal 2005 for R2.4 billion (U.S.$361.8 million). The process was concluded through
market disposals which began on November 10, 2005 and an open market offering on November 15 and
16, 2005. The investment was acquired at a cost of R2.1 billion (U.S.$316.4 million), resulting in
a profit of R307 million (U.S.$45.4 million).
Hedging Policy
We have consistently maintained a policy of not entering into forward sales, commodity,
derivatives or hedging arrangements to establish a
28
price in advance for the sale of our future gold
production, although we may do so in the future. As a result of this policy, Board approval is required when hedging
arrangements are to be entered into.
Where any such gold hedging position is acquired, our policy is to eliminate any such
positions existing within acquired companies as soon as this can be achieved through sound,
commercially advantageous transactions. There may, however, be instances where certain hedge
positions in acquired companies need to be kept in place for contractual or other reasons. In line
with this policy, we have historically closed out hedging arrangements inherited through our
acquisitions. Our revenues are sensitive to the exchange rate of the Rand and other non-U.S.
currencies to the U.S. dollar, as all the revenues are generated by gold sales denominated in U.S.
dollars. We do not enter into forward sales, commodity, derivatives or other hedging arrangements
to establish a Rand to U.S. dollar exchange rate in advance for the sales of our future gold
production, although we may do so in the future.
In May 2007, we closed out the remainder of our Australian hedge book, which we inherited
with the acquisition of the Hill 50 mine. In these transactions, some 220,000 ounces were closed
out at an average spot rate of A$809/ounce, for a total cost of A$72.8 million (U.S.$60.0 million).
As a result, we are completely unhedged.
Description of Mining Business
Exploration
Exploration activities are focused on the extension of existing orebodies and
identification of new orebodies, both at existing sites and at undeveloped sites.
Our gold-focused exploration program has two components:
|
|
|
on-mine exploration, which looks for resources within the economic radius of existing mines, and |
|
|
|
|
new mine exploration, which is the global search for early to advanced stage projects. |
Once a potential orebody has been discovered, exploration is extended and intensified in
order to enable clearer definition of the orebody and the potential portions to be mined.
Geological techniques are constantly refined to improve the economic viability of prospecting and
mining activities.
We conduct exploration activities on our own or with joint venture partners. As at June
30, 2008, our prospecting interest in South Africa measured 28,039 hectares (69,286 acres), 220,600
hectares (545,114 acres) in PNG and 97,491 hectares (240,906 acres) in Australia. We spent
U.S.$28 million on exploration in fiscal 2008 and the bulk of exploration expenditure was allocated
to activities in PNG and South Africa. In fiscal 2009, we intend to carry out exploration in PNG
and South Africa.
Mining
The mining process can be divided into two main phases: (i) accessing the orebody and
(ii) mining the orebody. This basic process applies to both underground and surface operations.
|
|
|
Accessing the orebody. |
|
|
|
|
In our South African underground mines, access to the orebody is by
means of shafts sunk from the surface to the lowest economically and
practically mineable level. Horizontal development at various
intervals of a shaft (known as levels) extends access to the horizon
of the reef to be mined. On-reef development then provides specific
mining access. Horizontal development at various intervals of the
decline extends access to the horizon of the ore to be mined. The
declines are advanced on a continuous basis to keep ahead of the
mining taking place on the levels above. In our open-pit mines, access
to the orebody is provided by overburden stripping, which removes the
covering layers of topsoil or rock, through a combination of drilling,
blasting, loading and hauling, as required. |
|
|
|
|
Mining the orebody. |
|
|
|
|
The process of ore removal starts with drilling and blasting the
accessible ore. The blasted faces are then cleaned, and the ore is
transferred to the transport system. In open-pit mines, gold-bearing
material may require drilling and blasting, and is usually collected
by bulldozers or shovels to transfer it onto trucks, which transport
it to the mill. |
In our South African underground mines, once ore has been broken, train systems collect
ore from the faces and transfer it to a series of ore passes that gravity feed the ore to hoisting
levels at the bottom of the shaft. The ore is then hoisted to the surface in dedicated conveyances
and
29
transported
either by conveyor belts directly or via surface railway systems or roads to the treatment plants. In addition to ore, waste rock broken
to access reef horizons must similarly be hoisted and then placed on waste rock dumps.
Processing
We currently have nine operational metallurgical plants and two metallurgical plants on
care and maintenance in South Africa. We also have a metallurgical plant at the Hidden Valley
project in PNG. The principal gold extraction processes we use are carbon in leach, or CIL, and
carbon in pulp, or CIP.
The gold plant circuit consists of the following:
|
|
|
Comminution. |
|
|
|
|
Comminution is the process of breaking up the ore to expose and
liberate the gold and make it available for treatment. Conventionally,
this process occurs in multi-stage crushing and milling circuits,
which include the use of jaw and gyratory crushers and rod and tube
and ball mills. Our more modern milling circuits include semi- or
fully-autogenous milling where the ore itself is used as the grinding
medium. Typically, ore must be ground to a minimum size before
proceeding to the next stage of treatment. |
|
|
|
|
Treatment. |
|
|
|
|
In most of our metallurgical plants, gold is extracted into a leach
solution from the host ore by leaching in agitated tanks. Gold is then
extracted onto activated carbon from the solution using the CIL or CIP
processes. |
Gold in solution, at one of our plants, is recovered using zinc precipitation. Recovery
of the gold from the loaded carbon takes place by elution and electro-winning. Cathode sludge or
dore bars produced from electro- winning is now currently sent directly to Rand Refinery. Most of
the South African plants no longer use smelting to produce rough gold bars (dore). Our South
African zinc precipitation plants continue to smelt precipitate to produce rough gold bars. These
bars are then transported to the Rand Refinery which is responsible for refining the bars to a
minimum of good delivery status.
In fiscal 2006, we operated the only independent gold refinery and fabrication plant in
South Africa. In fiscal 2006, approximately 84% of our South African gold production was refined at
our refinery and the remainder was refined at the Rand Refinery, which is owned by a consortium of
the major gold producers in South Africa. Since July 2006, all of our gold produced in South Africa
has been sent to the Rand Refinery, as a decision was made to close the Harmony Refinery for
economic reasons. The Australian gold production for fiscal years 2006 to 2008 was refined in
Australia at an independent refiner, AGR Matthey.
The South African government has emphasized that the production of value-added fabricated
gold products, such as jewelry, is an important means for creating employment opportunities in
South Africa and has made the promotion of these beneficiation activities a requirement of the
Mining Charter described in Item 4. Information on the Company Regulation Mineral Rights. We
support jewelry ventures in South Africa.
Harmonys Management Structure
We have a de-centralized management structure that is based on small, empowered
management teams led by General Managers at each of our operations. In South Africa, the General
Managers report to Alwyn Pretorius and Tom Smith, the Chief Operations Officers, and are
responsible for business optimization, ore reserve optimization, and for developing a business
culture at the operations. They also focus on long-term viability and growth of the operations. The
General Managers are supported by an Ore Reserve Manager, a Business Analyst and a Human Resources
Leader in ensuring the growth and long-term sustainability of the operations, and additional
expertise and skill is obtained from the Mining Managers, Engineers and Human Resource Managers who
also report to the respective General Managers.
Capital Expenditures
Capital expenditures for continuing operations incurred for fiscal 2008 totalled U.S.$500
million, compared with U.S.$320 million for fiscal 2007 and U.S.$205 million for fiscal 2006. The
increase in capital expenditure in fiscal 2008 compared with 2007 was primarily related to the
development of the PNG assets, which accounted for 66% of the project capital expended. Capital was
also expended on the Doornkop South Reef Project, Tshepong Sub 66 and 71 Declines, Phakisa and the
Elandsrand New Mine. During fiscal 2007, the increased development in PNG accounted for 45% of the
project capital expended in the year. This was also the primary reason for the increase in capital
expenditure in fiscal 2007 compared with fiscal 2006. Expenditure was also incurred at Doornkop
South Reef Project, Phakisa, Tshepong Sub 66 Decline and Elandsrand New Mine.
30
The focus of our capital expenditures in recent years has been underground development and
plant improvement and upgrades. Several of these projects will be completed during fiscal 2009. The
remainder of the projects will still require a great deal of capital expenditure over the next two
to three years until they are substantially completed. During fiscal 2008, various funding options
were investigated. These included entering into a partnering deal for the PNG assets. The
transaction was concluded after year end. See Item 4. Recent Developments.
Capital expenditure for discontinued operations, including the non-cash portion, incurred for
fiscal 2008 totaled U.S.$42 million, compared with U.S.$61 million for fiscal 2007 and U.S.$60
million for fiscal 2006.
We have budgeted approximately U.S.$379 million for capital expenditures in fiscal 2009.
Details regarding the capital expenditures for each operation are found in the individual mine
sections under Business Harmonys Mining Operations. We currently expect that our planned
operating capital expenditures will be financed from operations and new borrowings as needed.
However, if we decide to expand major projects such as the Poplar Project and the Rolspruit Project
at Evander beyond our current plans, we may consider alternative financing sources. See
Item 4.Information on the Company Business Harmonys Mining Operations Evander Operations.
Reserves
As at June 30, 2008, we have declared proven and probable reserves of 50.5 million
ounces, broken down as follows: 47.5 million ounces in South Africa and 3.0 million ounces in PNG.
Of our 50.5 million ounces of ore reserves, 12.2 million ounces are classified as below
infrastructure (that is, reserves for which capital expenditure has yet to be approved). There has
been a 3.2 million ounces year-on-year negative variance in ore reserves due to the following
reasons:
|
|
|
normal depletion of 1.9 million ounces; |
|
|
|
|
corporate activity, the exclusion of operations held for sale, restructuring
of certain shafts and geological-related changes resulting in a decrease of
5.7 million ounces; and |
|
|
|
|
a net addition of 4.4 million ounces of ore reserves from surface stockpiles. |
We use the South African Code for the Reporting of Exploration Results, Mineral Resources
and Ore Reserves (SAMREC Code), which sets out the internationally recognized procedures and
standards for reporting of mineral resources and ore reserves. We use the term ore reserves
herein, which has the same meaning as mineral reserves, as defined in the SAMREC code. Our
reporting of its PNG Ore Reserves complies with the Australian Code for the Reporting of Mineral
Resources and Ore Reserves (JORC) of the Australian Institute of Mining and Metallurgy. This
code is materially the same as SAMREC. In reporting of reserves, we have complied with Industry
Guide 7 of the U.S. Securities and Exchange Commission.
For the reporting of Ore Reserves at our South African and PNG operations, we use a gold
price of U.S.$750 per ounce. An exchange rate of R7.46 per U.S. dollar is used for South Africa and
for PNG an exchange rate of U.S.$0.80 per Australian dollar is used giving a gold price of R180,000
per kilogram and AU$850 per ounce, respectively. These gold prices have also been used in mine
planning.
In order to define that portion of a measured and indicated mineral resource that can be
converted to a proven and probable ore reserve at our underground operations, we apply the concept
of a cut-off grade. This is done by defining the optimal cut-off as the lowest grade at which an
orebody can be mined such that the total profits, under a specified set of mining parameters, are
maximized. The cut-off grade is determined using our Optimizer computer program which requires the
following as input:
|
|
|
the database of measured and indicated resource blocks (per shaft section); |
|
|
|
|
an assumed gold price which, for this ore reserve statement, was taken as R180,000 per kilogram; |
|
|
|
|
planned production rates; |
|
|
|
|
the mine recovery factor (MRF) which is equivalent to the mine call factor (MCF) multiplied
by the plant recovery factor; and |
|
|
|
|
planned cash costs (cost per tonne). |
31
Rand per tonne cash costs of the mines are historically based, but take into account
distinct changes in the cost environment, such as the future production profile, restructuring,
right-sizing, and other cost reduction initiatives which we expect in the aggregate to lead to
lower unit costs, and for below-infrastructure ounces, an estimate of capital expenditure.
The block cave reserve at Golpu (PNG) used the PCBC computer program to define the optimal
mine plan and sequencing.
The open pit reserve at Hidden Valley (PNG) is constrained by the capacity of the tailings
storage facility with Whittle optimisation program guiding the most efficient mine design given
this constraint.
The ore reserves represent that portion of the measured and indicated resources above
cut-off in the life-of-mine plan and have been estimated after consideration of the factors
affecting extraction, including mining, metallurgical, economic, marketing, legal, environmental,
social, and governmental factors. A range of disciplines which includes geology, survey, planning,
mining engineering, rock engineering, metallurgy, financial management, human resources management,
and environmental management have been involved at each mine in the life-of-mine planning process
and the conversion of resources into reserves. The ore flow-related modifying factors used to
convert the mineral resources to ore reserves through the life-of-mine planning process are stated
for each individual shaft. For these factors, historical information is used, except if there is a
valid reason to do otherwise. Because of depth and rock engineering requirements, some shafts
design stope support pillars into their mining layouts which accounts for approximately 7% to 10%
discounting. Further discounting relates to the life-of-mine extraction to provide for unpay and
geological losses.
Our standard for narrow reef sampling with respect to both proven and probable reserve
calculations for underground mining operations in South Africa is applied on a 6 meter by 6 meter
grid. Average sample spacing on development ends is at 2 meter intervals in development areas. For
the massive mining at the Target operations, our standard for sampling with respect to both proven
and probable reserves are fan drilling with B sized diamond drill holes (43mm core) sited at 50
meter spaced sections along twin access drives. The Kalgold open cast operations are sampled on
diamond drill and reverse circulation drill spacing of no more than 25 meters on average. Surface
mining at South African operations other than Kalgold involves recovering gold from areas
previously involved in mining and processing, such as metallurgical plants, waste rock dumps and
tailing dams (slimes and sand) for which random sampling is used.
The PNG resources are hosted in large porphyry or related mesothermal geological systems. Data
is gained through diamond drilling using PQ down to NQ sized core. The core is cut in half, one
half sampled at a maximum of 2 meter intervals and the other half stored in designated core storage
facilities. Drill spacing is typically on less than 20 meter centres for Measured category, 20 to
40 meter centres for the Indicated category and greater than 40m for Inferred category material.
Assaying for gold is by fire assay and various methods are used for copper and other elements. All
assays informing the resource calculation are analysed at a NATA accredited commercial laboratory.
Some sample preparation is done at the mine site laboratory. Extensive QA/QC work is undertaken and
data is stored in electronic database.
32
Our mining operations reported total proven and probable reserves as of June 30, 2008 are set out
below:
Ore reserve statement (Imperial) as at June 30, 2008(2)
Gold
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROVEN |
|
PROBABLE |
|
TOTAL |
|
|
Tons |
|
Grade |
|
Gold(1) |
|
Tons |
|
Grade |
|
Gold(1) |
|
Tons |
|
Grade |
|
Gold(1) |
Operations |
|
(million) |
|
(oz/ton) |
|
(Moz) |
|
(million |
|
(oz/ton) |
|
(Moz) |
|
(millions) |
|
(oz/ton) |
|
(Moz) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
South Africa Underground |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tshepong |
|
|
6.64 |
|
|
|
0.177 |
|
|
|
1.18 |
|
|
|
19.32 |
|
|
|
0.176 |
|
|
|
3.39 |
|
|
|
25.96 |
|
|
|
0.176 |
|
|
|
4.57 |
|
Phakisa |
|
|
0.09 |
|
|
|
0.217 |
|
|
|
0.02 |
|
|
|
21.87 |
|
|
|
0.243 |
|
|
|
5.30 |
|
|
|
21.96 |
|
|
|
0.242 |
|
|
|
5.32 |
|
Bambanani |
|
|
3.15 |
|
|
|
0.283 |
|
|
|
0.89 |
|
|
|
1.09 |
|
|
|
0.268 |
|
|
|
0.29 |
|
|
|
4.24 |
|
|
|
0.279 |
|
|
|
1.18 |
|
Doornkop |
|
|
0.37 |
|
|
|
0.118 |
|
|
|
0.04 |
|
|
|
1.11 |
|
|
|
0.124 |
|
|
|
0.14 |
|
|
|
1.48 |
|
|
|
0.123 |
|
|
|
0.18 |
|
Elandskraal |
|
|
4.83 |
|
|
|
0.186 |
|
|
|
0.90 |
|
|
|
39.56 |
|
|
|
0.195 |
|
|
|
7.73 |
|
|
|
44.39 |
|
|
|
0.194 |
|
|
|
8.63 |
|
Masimong |
|
|
4.01 |
|
|
|
0.147 |
|
|
|
0.59 |
|
|
|
1.09 |
|
|
|
0.155 |
|
|
|
0.17 |
|
|
|
5.1 |
|
|
|
0.148 |
|
|
|
0.76 |
|
Virginia operations |
|
|
5.92 |
|
|
|
0.127 |
|
|
|
0.75 |
|
|
|
2.63 |
|
|
|
0.144 |
|
|
|
0.38 |
|
|
|
8.55 |
|
|
|
0.132 |
|
|
|
1.13 |
|
|
Evander |
|
|
3.08 |
|
|
|
0.202 |
|
|
|
0.62 |
|
|
|
8.12 |
|
|
|
0.163 |
|
|
|
1.32 |
|
|
|
11.20 |
|
|
|
0.173 |
|
|
|
1.94 |
|
Evander(below infrastructure) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
57.24 |
|
|
|
0.213 |
|
|
|
12.21 |
|
|
|
57.24 |
|
|
|
0.213 |
|
|
|
12.21 |
|
Target |
|
|
9.22 |
|
|
|
0.214 |
|
|
|
1.97 |
|
|
|
12.72 |
|
|
|
0.179 |
|
|
|
2.28 |
|
|
|
21.94 |
|
|
|
0.194 |
|
|
|
4.25 |
|
Other underground |
|
|
0.90 |
|
|
|
0.144 |
|
|
|
0.13 |
|
|
|
2.14 |
|
|
|
0.149 |
|
|
|
0.32 |
|
|
|
3.04 |
|
|
|
0.145 |
|
|
|
0.45 |
|
Total S.A. Underground |
|
|
38.21 |
|
|
|
0.185 |
|
|
|
7.09 |
|
|
|
166.89 |
|
|
|
0.201 |
|
|
|
33.53 |
|
|
|
205.10 |
|
|
|
0.198 |
|
|
|
40.62 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
South Africa surface |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kalgold |
|
|
12.46 |
|
|
|
0.026 |
|
|
|
0.33 |
|
|
|
1.79 |
|
|
|
0.037 |
|
|
|
0.07 |
|
|
|
14.25 |
|
|
|
0.028 |
|
|
|
0.39 |
|
Free Gold |
|
|
803.16 |
|
|
|
0.007 |
|
|
|
5.68 |
|
|
|
77.39 |
|
|
|
0.010 |
|
|
|
0.80 |
|
|
|
880.55 |
|
|
|
0.007 |
|
|
|
6.47 |
|
Total S.A. Surface |
|
|
815.62 |
|
|
|
0.007 |
|
|
|
6.01 |
|
|
|
79.18 |
|
|
|
0.011 |
|
|
|
0.87 |
|
|
|
894.80 |
|
|
|
0.008 |
|
|
|
6.88 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PNG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Hidden Valley and Kaveroi |
|
|
3.64 |
|
|
|
0.067 |
|
|
|
0.24 |
|
|
|
24.46 |
|
|
|
0.059 |
|
|
|
1.46 |
|
|
|
28.10 |
|
|
|
0.060 |
|
|
|
1.70 |
|
Hamata |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.33 |
|
|
|
0.074 |
|
|
|
0.32 |
|
|
|
4.33 |
|
|
|
0.074 |
|
|
|
0.32 |
|
Golpu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
54.63 |
|
|
|
0.018 |
|
|
|
0.97 |
|
|
|
54.63 |
|
|
|
0.018 |
|
|
|
0.97 |
|
Total PNG |
|
|
3.64 |
|
|
|
0.067 |
|
|
|
0.24 |
|
|
|
83.42 |
|
|
|
0.033 |
|
|
|
2.75 |
|
|
|
87.06 |
|
|
|
0.034 |
|
|
|
2.99 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Grand total |
|
|
857.47 |
|
|
|
0.016 |
|
|
|
13.34 |
|
|
|
329.49 |
|
|
|
0.113 |
|
|
|
37.15 |
|
|
|
1,186.96 |
|
|
|
0.043 |
|
|
|
50.49 |
|
|
|
|
(1) |
|
Gold oz figures are fully inclusive of all mining dilutions and gold losses, and are reported as mill-delivered tons and head grades. Metallurgical recovery factors have not been applied to the reserve figures stated above. The approximate metallurgical recovery factors for the table above are as follows: Elandskraal 96%; Free State 95%; Randfontein 95%; Evander 97%; Kalgold 90%; Freegold 96%; Target 97%; PNG 93%. In order to derive the appropriate plant recovery factors for ore reserve estimates a
process have been followed where realistic assumptions based on historical performance have been applied. There may be short term fluctuation either positive or negative which can lead to small discrepancies between actual and planned recovery factors. |
|
(2) |
|
Cut-off grades are calculated per individual shaft, each having its own unique cost structure, ore flow and recovery factors, which are entered into our Optimizer software for a cut-off calculation per shaft and expressed in oz/t units. |
33
In addition to the gold reserves, we also report our equity reserves for silver, copper and
molybdenum from our PNG operations. Metal prices are assumed at U.S.$12/oz for silver,
U.S.$2.40/lb for copper and U.S.$20/lb for molybdenum.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
SILVER |
|
|
|
|
|
|
|
|
Proven |
|
|
|
|
|
|
|
|
|
Probable |
|
|
|
|
|
|
|
|
|
Total |
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
Tons |
|
Grade |
|
Silver oz |
|
Tons |
|
Grade |
|
Silver oz |
|
Tons |
|
Grade |
|
Silver oz |
PNG |
|
(millions) |
|
(oz/ton) |
|
(millions) |
|
(millions) |
|
(oz/ton) |
|
(millions) |
|
(millions) |
|
(oz/ton) |
|
(millions) |
Hidden Valley and
Kaveroi |
|
|
3.64 |
|
|
|
1.197 |
|
|
|
4.36 |
|
|
|
24.46 |
|
|
|
1.077 |
|
|
|
26.35 |
|
|
|
28.10 |
|
|
|
1.093 |
|
|
|
30.71 |
|
GRAND TOTAL |
|
|
3.64 |
|
|
|
1.197 |
|
|
|
4.36 |
|
|
|
24.46 |
|
|
|
1.077 |
|
|
|
26.35 |
|
|
|
28.10 |
|
|
|
1.093 |
|
|
|
30.71 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COPPER |
|
|
|
|
|
|
|
|
Proven |
|
|
|
|
|
|
|
|
|
Probable |
|
|
|
|
|
|
|
|
|
Total |
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
Tons |
|
Grade |
|
Cu lbs |
|
Tons |
|
Grade |
|
Cu lbs |
|
Tons |
|
Grade |
|
Cu lbs |
PNG |
|
(millions) |
|
(%) |
|
(millions) |
|
(millions) |
|
(%) |
|
(millions) |
|
(millions) |
|
(%) |
|
(millions) |
Golpu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
54.63 |
|
|
|
1.025 |
|
|
|
1,234.0 |
|
|
|
54.63 |
|
|
|
1.025 |
|
|
|
1,234.0 |
|
GRAND TOTAL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
54.63 |
|
|
|
1.025 |
|
|
|
1,234.0 |
|
|
|
54.63 |
|
|
|
1.025 |
|
|
|
1,234.0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MOLYBDENUM |
|
|
|
|
|
|
|
|
Proven |
|
|
|
|
|
|
|
|
|
Probable |
|
|
|
|
|
|
|
|
|
Total |
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
|
|
|
|
|
Reserves |
|
|
|
|
Tons |
|
Grade |
|
Mo lbs |
|
Tons |
|
Grade |
|
Mo lbs |
|
Tons |
|
Grade |
|
Mo lbs |
PNG |
|
(millions) |
|
(lbs/ton) |
|
(millions) |
|
(millions) |
|
(lbs/ton) |
|
(millions) |
|
(millions) |
|
(lbs/ton) |
|
(millions) |
Golpu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
54.63 |
|
|
|
0.238 |
|
|
|
13.00 |
|
|
|
54.63 |
|
|
|
0.238 |
|
|
|
13.00 |
|
GRAND TOTAL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
54.63 |
|
|
|
0.238 |
|
|
|
13.00 |
|
|
|
54.63 |
|
|
|
0.238 |
|
|
|
13.00 |
|
Our methodology for determining our reserves is subject to change and is based upon
estimates and assumptions made by management regarding a number of factors as noted above in this
section.
Worldwide Operations
Description of Property
The following is a map of our worldwide operations:
Our operational mining areas in South Africa are set forth below:
|
|
|
|
|
|
|
|
|
|
|
Hectares |
|
Acres |
Doornkop |
|
|
2,941 |
|
|
|
7,267 |
|
Elandsrand |
|
|
5,113 |
|
|
|
12,634 |
|
Free State (includes Masimong and Virginia operations) |
|
|
22,583 |
|
|
|
55,802 |
|
Tshepong and Phakisa |
|
|
10,799 |
|
|
|
26,683 |
|
Bambanani |
|
|
2,356 |
|
|
|
5,821 |
|
Joel |
|
|
2,162 |
|
|
|
5,342 |
|
St Helena |
|
|
5,856 |
|
|
|
14,471 |
|
Kalgold |
|
|
615 |
|
|
|
1,520 |
|
|
|
|
|
|
|
|
|
|
Evander |
|
|
36,898 |
|
|
|
91,174 |
|
Target (includes Loraine) |
|
|
7,952 |
|
|
|
19,649 |
|
Total |
|
|
97,275 |
|
|
|
240,363 |
|
34
Our discontinued operational mining areas are set forth below:
|
|
|
|
|
|
|
|
|
|
|
Hectares |
|
Acres |
Mt. Magnet |
|
|
97,491 |
|
|
|
240,906 |
|
|
Cooke (Randfontein) |
|
|
7,875 |
|
|
|
19,460 |
|
|
|
|
|
|
|
|
|
|
Lindum (Randfontein) |
|
|
3,231 |
|
|
|
7,983 |
|
Total |
|
|
108,597 |
|
|
|
268,349 |
|
In PNG, we hold granted tenements as set forth below:
|
|
|
|
|
|
|
|
|
|
|
Hectares |
|
Acres |
PNG |
|
|
220,600 |
|
|
|
545,114 |
|
Total Worldwide Operations |
|
|
426,472 |
|
|
|
1,053,826 |
|
In line with the rest of the South African mining industry, and in an effort to reduce costs,
we have been rationalizing our mineral rights holdings in recent years. Accordingly, over the past
three years, we have disposed of our shares and participation rights in areas within and outside of
South Africa in which we have not actively pursued mining. However, in some cases we have retained
certain participation rights and option clauses in disposed of properties and mining rights. We may
continue to investigate further disposals.
Geology
The major portion of our South African gold production is derived from mines located in
the Witwatersrand Basin in South Africa. The Witwatersrand Basin is an elongated structure that
extends approximately 300 kilometers in a northeast-southwest direction and approximately 100
kilometers in a northwest-southeast direction. It is an Archean sedimentary basin containing a six
kilometer thick stratigraphic sequence consisting mainly of quartzites and shales with minor
volcanic units. The majority of production is derived from auriferous placer reefs situated at
different stratigraphic positions and at varying depths below the surface in three of the seven
defined goldfields of the Witwatersrand Basin.
Our Hidden Valley project comprises low sulphidation carbonate-base metal-gold epithermal
deposits within the Morobe Goldfield, in the Morobe Province of PNG. In the Hidden Valley project
area, a batholith of Morobe Granodiorite (locally a coarse grained monzogranite) is flanked by fine
metasediments of the Owen Stanley Metamorphics. Both are cut by dykes of Pliocene porphyry ranging
from hornblende-biotite to feldspar-quartz porphyries. A number of commonly argillic altered and
gold anomalous breccias are known, including both hydrothermal and over printing structural
breccias. The Hidden Valley deposit area is dominated by a series of post Miocene faults
controlling the gold mineralization, including an early north trending set and the main northwest
faulting.
Our Wafi project comprises the sedimentary/volcaniclastic rocks of the Owen Stanley
Formation that surround the Wafi Diatreme and host the gold mineralization. Gold mineralization
occurs as extensive high-sulphidation epithermal alteration overprinting porphyry mineralization
and epithermal style vein-hosted and replacement gold mineralization with associated wall-rock
alteration. The Golpu Copper-Gold project is located about one kilometer northeast of the Wafi gold
orebody. It is a porphyry (diorite) copper-gold deposit. The host lithology is a diorite that
exhibits a typical zoned porphyry copper alteration halo and the mineralized body can be described
as a porphyry copper-gold pipe.
Harmonys Mining Operations Overview
Previously, we discussed our South African operations per legal entity, which by design were
geographically grouped. These were Free State (owned by Harmony Company), Freegold, Elandsrand
(originally known as the Elandskraal operations), Randfontein, Evander, Avgold, ARMgold and
Kalgold. The shafts were then further divided into categories of Quality, Leveraged, Growth
and Surface.
As discussed under Item 4. South African Operations, we have changed the way in which we
manage our operations. In line with this change, we have amended the manner in which we discuss our
operations.
35
In South Africa, we conduct underground mining at 11 operations:
|
|
|
Tshepong (formerly part of Freegold) |
|
|
|
|
Phakisa (formerly part of Freegold) |
|
|
|
|
Bambanani (formerly part of Freegold) |
|
|
|
|
Doornkop (formerly part of Randfontein) |
|
|
|
|
Cooke operations (consists of Cooke 1, 2 and 3 shafts, formerly part of Randfontein) |
|
|
|
|
Elandsrand |
|
|
|
|
Masimong (formerly part of the Free State region) |
|
|
|
|
Virginia operations (consists of Harmony 2, Merriespruit 1 & 3, Unisel and Brand 3
& 5, all formerly part of the Free State region) |
|
|
|
|
Target (forms part of Avgolds operations) |
|
|
|
|
Evander (consists of Evander 5, 7 and 8) |
|
|
|
|
Joel (formerly part of Freegold, now included under Other Underground) |
We conduct surface mining at five sites (all included in Other Surface):
|
|
|
Free State (also known as Phoenix) |
|
|
|
|
Randfontein (Cooke plant has been classified as discontinued
operations along with the Cooke operations) |
|
|
|
|
Freegold |
|
|
|
|
Kalgold |
|
|
|
|
Target |
Surface mining conducted at the South African operations other than Kalgold involves
recovering gold from areas previously involved in mining and processing, such as metallurgical
plants, waste rock dumps and tailings dams (slimes and sand).
Internationally, our mining was previously conducted at the following two sites in Australia:
|
|
|
Mt. Magnet The site has put on care and maintenance as at the end of
December 2007. On August 1, 2008, the Monarch Golds administrator
indicated that Monarch Gold would not proceed with the proposed
purchase, and consequently the agreement was terminated. We have
since resumed management of the of the Mt. Magnet operations and
recommenced the sales process See International Operations above. |
|
|
|
|
South Kalgoorlie we finalized the sale of this operation with Dioro
on November 30, 2007 See Disposals above. |
Underground and surface mining was conducted at each of these operations, with underground
access through two declines at Mt. Magnet and one decline at South Kalgoorlie and surface access
principally through open-pits. Surface mining at South Kalgoorlie ceased in fiscal 2006 with
treatment consisting of Mt. Marion ore and low grade stockpiles. Open-pit mining recommenced at
South Kalgoorlie mines during fiscal 2007. The Mt. Marion underground operation at South Kalgoorlie
Mines ceased in June 2007, with only open-pit operations continuing on that site until the date of
sale to Dioro.
The following discussion is a two-part presentation of our operations:
|
|
|
an overview of our South African mining operations with a discussion
and production analysis of each of our operating segments; and |
|
|
|
|
an overview of our International (Australian and PNG) operations. |
Where we have translated the Rand amount budgeted for capital expenditures in 2009 into U.S.
dollars, we have used the closing rate at the balance sheet date.
South African Mining Operations
Unless indicated otherwise, the discussions below are for continuing operations.
36
Underground
Tshepong, Phakisa and Bambanani
Introduction: We acquired Tshepong, Phakisa and Bambanani when we, in January 2002, acquired the
Freegold operations from AngloGold through a 50 % joint venture with ARMgold. In September 2003, we
acquired 100% of these operations when ARMgold became a wholly owned subsidiary. These operations
are located in the Free State province. Production from the operations is processed through two
processing facilities (the Free State 1 (FS 1 Plant) and Central plant, the latter forms part of
our Virginia operations).
History: Exploration, development and production history in the area of the Freegold assets dates
from the early 1900s, leading to commercial production by 1932. Subsequent consolidation and
restructuring led to the formation of Free State Consolidated Gold Mine (Operations) Limited, which
became a wholly-owned subsidiary of AngloGold in June 1998.
Geology: The operations are located in the Free State Goldfield, which is on the southwestern edge
of the Witwatersrand basin. The Bambanani, Tshepong and Phakisa mines are located to the north and
west of Welkom. Mining is primarily conducted in the Basal reef, with limited exploitation of the B
Reef at Tshepong. The reefs generally dip towards the east or northeast while most of the major
faults strike north-south. B Reef is being mined at Tshepong with potential of being exploited
elsewhere.
Mining Operations: These operations are subject to the underground mining risks detailed in the
Risk Factors section. The management teams regularly revisit their mining strategy and management
procedures in order to minimize risks.
Mining is conducted at depths ranging from 1,911 and 3,129 meters at Bambanani and between
depths of 1,671 and 2,245 meters at Tshepong. The primary mining challenges at these operations
are seismic risks, ventilation and fire avoidance. Bambanani is classified as a seismically active
operation with seismic activity monitoring systems installed to do active seismic risk evaluation.
Seismic activity monitoring systems are upgraded on a continuous basis to ensure that it is kept
abreast of emerging technology. Current ventilation and refrigeration systems were evaluated and
improved with refrigeration plants installed at the Bambanani and Tshepong Mines. We believe this
will improve productivity and safety after operations at Tshepong were hampered by a number of
fires and seismic events that significantly affected production in the first half of fiscal 2008.
The Tshepong Decline project, which started in April 2003, has accessed an additional two
levels (69 and 71) of the Tshepong North Shaft. The Sub 66 project neared completion at the end of
June 2008 with a total capital expenditure of R289 million (U.S.$39.8 million). The balance of the
final estimated capital of R291million (U.S.$40 million) will be spent during the first quarter of
fiscal 2009. Production commenced at Sub 66 Decline during the year, with the build-up to continue
over the next two years. Emphasis is now being placed on significantly increasing mineable
reserves. Poor ground conditions caused some delays to the project, with the final mining component
being completed in June 2008, and all project work scheduled for completion by December 2008. Good
progress was made at the Sub 71Decline project during fiscal 2008, with a total of 1,089 metres
being developed by year-end. The escalation of input costs, combined with skills shortages (design
and engineering draughting personnel) had a negative impact on the project. First production is
expected in August 2012, with full production anticipated in July 2017. The total estimated value
of this project is R132 million (U.S.$18 million).
The development at Phakisa, a surface shaft, sunk to 75 level elevations and a planned decline
shaft to 85 levels will access the ore reserves to a depth of 2,662 meters below surface. It is
estimated that the area will yield 22.0 million tons, recovering 182.5 tons of gold over a project
life of 22 years. Project completion requires sinking of a decline shaft, equipping and
commissioning of the shaft with access development and stoping to maximum production build-up at a
capital cost of R1,348 million (U.S.$185.5 million). To date, R866 million (U.S.$119.2 million) has
already been spent. Good progress was achieved during fiscal 2008, with the reef ore passes, reef
hoisting facility and Rail-veyor reef and waste handling on 55 level completed. The second train on
the Rail-veyor is planned for October 2008. Installation of the permanent water handling systems
(i.e., Settlers, Main Pump Station on 77 Level, Mud press and underground dams) has progressed and
expected completion is October 2008. The cooling systems of Phakisa Shaft will include a first
phase 10MW Ice Plant on surface. This will be a first in the gold
37
mining industry. Phakisa started
the first production during September 2007 and will be opening up ore reserves for the next two years. The project is expected to be in full production
in June 2011 at 83,000 tons per month. The average production rate per annum over the peak period
of life of mine is 253,360 ounces.
Bambanani was restructured during the third quarter of fiscal 2008 due to the power shortages
in the country. This resulted in the tonnages being reduced by 50%. There was also a significant
reduction in the labor complement, with 2,086 people leaving through transfers and voluntary
retrenchments. Bambanani now operates as a low tonnage high grade mine (8.0g/t recovered grade).
Conops was introduced at the operations during the quarter ended December 31, 2003. Conops
were stopped at Bambanani during April 2005. Conops was officially stopped at Tshepong during
January 2008 after a due diligence study conducted during fiscal 2007 indicated that Conops was not
delivering at the planned levels. For a detailed discussion on Conops and the evaluation process
that was followed, see Item 5. Operating and Financial Review and Prospects Conops.
During fiscal 2008, Tshepong accounted for 14% (14% in 2006 and 2007) of our total gold sales,
with Phakisa accounting for 0.2% (nil in 2006 and 2007) and Bambanani 8% (8% in 2006 and 2007).
Safety: During fiscal 2008, the safety statistics for the operations compared to the Group average
for lost time frequency rate (LTFR) of 12.83 per million hours worked and fatality frequency rate
(FFR) of 0.18 are as follows:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LTFR |
|
|
FFR |
|
|
Tshepong
|
|
|
18.52 |
|
|
|
0.17 |
|
|
|
Phakisa
|
|
|
4.83 |
|
|
|
0.37 |
|
|
|
Bambanani
|
|
|
11.18 |
|
|
|
0.40 |
|
|
|
Safety standards receive constant and high-level attention at all the operations.
Plants: The ore from theses operations are sent to FS 1 Plant for processing. This plant, which
processes underground ore, waste rock and various surface accumulations, was commissioned in 1986
and is a conventional CIP plant processing ore that has been milled by semi-autogenous grinding.
Gold is recovered from the eluate solution using zinc precipitation and a precoat vacuum filter.
The precipitate recovered from the filter is calcined and smelted to bullion.
The following table sets forth processing capacity and average tons milled during the fiscal
2008 for the FS 1 Plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for |
|
|
Processing |
|
the Fiscal Year |
Plant |
|
Capacity |
|
Ended June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
FS 1 |
|
|
420,000 |
|
|
|
416,447 |
|
In fiscal 2008, FS 1 Plant recovered approximately 97% of the gold contained in the ore
delivered for processing.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Tshepong |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
1,649 |
|
|
|
1,824 |
|
|
|
1,786 |
|
Recovered grade (ounces/ton) |
|
|
0.166 |
|
|
|
0.175 |
|
|
|
0.188 |
|
Gold sold (ounces) |
|
|
273,119 |
|
|
|
318,887 |
|
|
|
335,289 |
|
38
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Tshepong |
|
2008 |
|
2007 |
|
2006 |
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
223 |
|
|
|
203 |
|
|
|
180 |
|
Cash cost |
|
|
125 |
|
|
|
112 |
|
|
|
111 |
|
Cash profit |
|
|
98 |
|
|
|
91 |
|
|
|
69 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
457 |
|
|
|
351 |
|
|
|
332 |
|
Capex (millions) ($) |
|
|
27 |
|
|
|
26 |
|
|
|
21 |
|
Tons milled from the Tshepong shaft increased to 1,824,000 in fiscal 2007, compared with
1,786,000 in fiscal 2006. Ounces sold were 318,887 in fiscal 2007, compared with 335,289 in fiscal
2006. This decrease was attributable to the decrease in recovery grade to 0.175 in fiscal 2007,
compared with 0.188 in fiscal 2006. The decrease in recovery grade was primarily due to decreases
in the shaft call factor, plant call factor and the average mining grade which was 1365 cmg/t in
fiscal 2007, compared to 1440 cmg/t in fiscal 2006, in line with the Life of Mine (LOM) profile.
Industry standard practice in South Africa is to report drill results and cut-off grades for
resource estimates in gold as thickness-grade values (cmg/t).
Cash costs for the Tshepong shaft were U.S.$112 million in fiscal 2007, compared with
U.S.$111 million in fiscal 2006. Cash costs per ounce were U.S.$351 in fiscal 2007, compared with
U.S.$332 in fiscal 2006. This increase in unit cost was attributable primarily due to decrease in
the number of ounces of gold produced.
Tons milled declined by 10% from 1,824, 000 tons in fiscal 2007 to 1,649,000 in fiscal 2008,
with gold production decreasing by 14% from 318,887 ounces in fiscal 2007 to 273,119 ounces in
fiscal 2008. The decrease was attributable to the decrease in the recovery grade to 0.166 in
fiscal 2008, compared with 0.175 in fiscal 2007. The decrease in recovery grade was primarily due
to the decrease in the shaft call factor and the average mining grade which was 1275 cmg/t in
fiscal 2008, compared to 1365 cmg/t in fiscal 2007. The drop in the average mining grade is in line
with the Life of Mine profile. During fiscal 2007 the mining in the east south block was in the
main high grade pay shoot and as we continued mining south during fiscal 2008 we where mining
closer to the edge of this high grade channel. The continuation of this channel will be mined once
the sub66 and sub 71 decline is completed. Tshepong was hampered by a number of fires and seismic
events that significantly affected production in the first half of fiscal 2008. The cessation of
Conops also resulted in lower production.
Cash costs for the Tshepong shaft were U.S.$125 million in fiscal 2008, compared with U.S.$112
million in fiscal 2007. Cash costs per ounce were U.S.$457 in fiscal 2008, compared with U.S.$351
in fiscal 2007. This increase in unit cost is attributable primarily to decrease in the number of
ounces of gold produced. Cash costs have increased by 11% in fiscal 2008, primarily due to
increases in the costs of labor and supplies and the effect of inflation on supply contracts.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 26.0 million tons (4.6
million ounces) will be sufficient for Tshepong to maintain underground production until
approximately 2024. Any future changes to the assumptions upon which the ore reserves are based, as
well as any unforeseen events affecting production levels, could have a material effect on the
expected period of future operations.
Capital Expenditure: We incurred approximately R195 million (U.S.$26.8 million) in capital
expenditures at the Tshepong shaft in the fiscal 2008, primarily for the decline project and
ongoing development. We have budgeted R74.7 million (U.S.$10.3 million) for project capital
expenditures in fiscal 2009. This capital includes R60.6 million (U.S.$8 million) for the
additional two levels 73 and 75 and B Reef exploration project of R10.8 million (U.S.$1.5
million).
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Phakisa |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
34 |
|
|
|
|
|
|
|
|
|
Recovered grade (ounces/ton) |
|
|
0.123 |
|
|
|
|
|
|
|
|
|
Gold sold (ounces) |
|
|
4,212 |
|
|
|
|
|
|
|
|
|
39
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Phakisa |
|
2008 |
|
2007 |
|
2006 |
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
4 |
|
|
|
|
|
|
|
|
|
Cash cost |
|
|
2 |
|
|
|
|
|
|
|
|
|
Cash profit |
|
|
2 |
|
|
|
|
|
|
|
|
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
556 |
|
|
|
|
|
|
|
|
|
Capex (millions) ($) |
|
|
40 |
|
|
|
32 |
|
|
|
23 |
|
The expected capacity of the Phakisa shaft will be 131,175 tons per month. Phakisa has no rock
hoisting facilities and all rock will be transported via a Rail system on 55 level to the Nyala
shaft for hoisting to surface. First production took place during October 2007, with a build up to
full production expected in the next two to three years.
On a simplistic basis reported proven and probable underground ore reserves of 21.9 million
tons (5.3 million ounces) will be sufficient for the Phakisa shaft to, once production commence,
maintain production until approximately fiscal 2030. Any future changes to the assumptions upon
which the reserves are based, as well as any unforeseen events affecting production levels, could
have a material effect on the expected period of future operations.
Capital Expenditure: We incurred approximately R293 million (U.S.$40 million) in capital
expenditures at the Phakisa operations in the fiscal year ended June 30, 2008. We have budgeted
Rand 330 million (U.S.$45 million) for capital expenditures in fiscal 2009, primarily for the
establishing and development of the shaft.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Bambanani |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
912 |
|
|
|
1,283 |
|
|
|
1,402 |
|
Recovered grade (ounces/ton) |
|
|
0.174 |
|
|
|
0.154 |
|
|
|
0.143 |
|
Gold sold (ounces) |
|
|
158,985 |
|
|
|
197,060 |
|
|
|
200,739 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
128 |
|
|
|
126 |
|
|
|
106 |
|
Cash cost |
|
|
102 |
|
|
|
115 |
|
|
|
101 |
|
Cash profit |
|
|
26 |
|
|
|
11 |
|
|
|
5 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
641 |
|
|
|
586 |
|
|
|
502 |
|
Capex (millions) ($) |
|
|
15 |
|
|
|
17 |
|
|
|
14 |
|
Tons milled from the Bambanani shaft decreased to 1,283,000 in 2007 compared with 1,402,000 in
fiscal 2006. An underground fire in March 2007 resulted in production loss of 4,180 ounces in
fiscal 2007. Ounces sold were 197,060 in fiscal 2007, compared with 200,739 in fiscal 2006. The
decrease in volumes was offset by an increase in the recovered grade, which increased from 0.143 in
fiscal 2006 to 0.154 in fiscal 2007.
Cash costs for Bambanani were U.S.$586 in fiscal 2007, compared with U.S.$502 in fiscal 2006.
The costs per ounce increased by 17% in fiscal 2007, due primarily to increases in the costs of
labor and supplies and the effect of inflation on supply contracts.
Tons milled from the Bambanani shaft decreased to 912,000 in 2008 compared with 1,283,000 in
fiscal 2007. Ounces sold were 158,985 in fiscal 2008, compared with 197,060 in fiscal 2007. This
decrease was due to the restructuring of the shaft due to power constraints but was offset by a
better recovered grade, which increased from 0.154 in fiscal 2007 to 0.174 in fiscal 2008.
Cash costs for Bambanani were U.S.$641 in fiscal 2008, compared with U.S.$586 in fiscal 2007.
The costs per ounce increased by 9% in fiscal 2008, due to the slow start up after the collapsing
of the old ore pass system and increases in the costs of labor and supplies and the effect of
inflation on supply contracts
The rock hoisting capacity at Bambanani is 116,000 tons per month. The average tons milled in
fiscal 2008 was 76,000 tons per month due to the restructuring during the latter half of the fiscal
year. 46,000 tons per month are planned for fiscal 2009, offset by an increased recovered grade.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven
40
and probable ore reserves of 4.2 million tons (1.2
million ounces) will be sufficient for Bambanani to maintain underground production until approximately 2020. Any future
changes to the assumptions upon which the ore reserves are based, as well as any unforeseen events
affecting production levels, could have a material effect on the expected period of future
operations.
Capital Expenditure: We incurred approximately R107 million (U.S.$14.7 million) in capital
expenditures at Bambanani in the fiscal 2008, primarily for ongoing development. We have budgeted
R25.3 million (U.S.$3.5 million) for capital expenditures in fiscal 2009 for access development for
the shaft pillar extraction and R26.3 million (U.S.$3.6 million) for ongoing development.
Doornkop
Introduction: Doornkop is located in the Gauteng Province of South Africa, approximately thirty
kilometers west of Johannesburg. The operation is owned by Randfontein Estates Limited
(Randfontein). Doornkop currently operates under its own mining authorization of 2,941 hectares.
Production is treated at the Doornkop plant.
History: We acquired this operation when Randfontein became a wholly-owned subsidiary during
calendar year 2008.
Geology: These operations are situated in the West Rand Goldfield of the Witwatersrand Basin, the
structure of which is dominated by the Witpoortjie and Panvlakte Horst blocks, which are
superimposed over broad folding associated with the southeast plunging West Rand Syncline.
During the 2008 year the gathering of additional geological information from on-reef
development and exploration drilling on the South Reef has increased our knowledge about the
sedimentology and grade characteristics of this ore body. This new knowledge has been incorporated
into a process whereby the geological depositional model has been extensively reviewed. This led to
a change in the model from an original more channelized deposit to what we now see as being a more
sheet-like deposit that was formed in a lower energy environment where the grade is distributed
more evenly across the ore body. This change resulted in an overall drop in the grade estimate of
the South Reef. In practice, less selective mining would be taking place as a result and that would
enable higher percentage extractions of the total ore body.
There are six identified main reef groupings in the area: the Black Reef; the Ventersdorp
Contact Reef; the Elsburg Formations; the Kimberleys; the Livingstone Reefs; and the South Reef.
Within these, several economic reef horizons have been mined at depths below surface between 600
and 1,260 meters.
The reefs comprise fine to coarse grained pyritic mineralization within well developed thick
quartz pebble conglomerates or narrow single pebble lags, which in certain instances are replaced
by narrow carbon seams.
Mining Operations: These operations are subject to the underground mining risks detailed in the
Risk Factors section. Due to the shallow to moderate depths of the operations, seismicity and
pressure related problems are infrequent. There is a risk of subterranean water and/or gas
intersections in some areas of the mines. However, this risk is mitigated by active and continuous
management and monitoring, which includes the drilling of boreholes in advance of faces. Where
water and/or gas are indicated in the drilling, appropriate preventative action is taken.
Currently, the Kimberley Reef is mined on the upper levels of the Doornkop Shaft between 900
and 1,100 meters below surface. Most of this mining is taking place on channel edges, which results
in sporadic high, but mostly low recovered grades. Mining from conventional sections of this reef
ceased during fiscal 2008 while the trackless section will continue for two years during the
build-up phase of production from the South Reef. During fiscal 2008, production was suspended for
18 days due to equipping relating to the Doornkop South Reef project. These overlapped with the
Eskom power shortages to some degree, and both had an impact on the production.
The Doornkop South Reef Project was announced on January 22, 2003. The project involved the
deepening of the Doornkop main shaft to 1,973 meters to the South Reef, which lies between 1,650
and 2,000 meters below surface, and includes development towards these mining areas. The estimated
final capital cost is R1.634 million (U.S.$224.8 million), with R956 million (U.S.$131.6 million)
spent as of June 30, 2008.
The most significant achievement for fiscal 2008 was the completion of the sinking operations
and equipping of winding plant compartments. The rock winder on surface was commissioned during
March 2008. The Rock winder compartments in the shaft will be equipped by January 2009. Milestones
for fiscal 2008 included the completion of station development and water and rock storage
facilities
41
which will
facilitate the first years of production build-up to full production. Remaining work includes development of two
additional silos, development to reef on 192, 197 and 202 levels and pump station commissioning in
October 2008. Full production is expected in July 2012.
During fiscal 2008, Doornkop accounted for 2% (2% in 2006 and 2007) of our total gold sales.
Safety: The safety record at these operations during fiscal 2008 was as follows: in terms of LTFR
of 8.55 per million hours worked achieved at Doornkop compared favourably with the group average of
12.83. The FFR (0.19) compared unfavorably with the group average of 0.18.
Safety at the operations receives constant and high-level attention and where problems are
identified, steps are taken to address the situation.
Plants: The processing facilities presently comprises of one operating plant, the Doornkop
metallurgical plant, which is serviced by a surface rail network. The Doornkop metallurgical plant,
commissioned in 1985, is a conventional CIP plant, which was used to treat waste rock and other
surface accumulations. It is now treating all ore from underground mining at the Doornkop and Cooke
operations.
The following table sets forth processing capacity and average tons milled during fiscal 2008 for
the Doornkop plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for the |
|
|
Processing |
|
Fiscal Year Ended |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Doornkop |
|
|
220,000 |
|
|
|
144,537 |
|
In fiscal 2008, the Doornkop plant recovered approximately 95% of the gold contained in the
ore delivered for processing. During fiscal 2006, the Doornkop plant was upgraded and all
underground tons were moved from Cooke to Doornkop plant.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Doornkop |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
494 |
|
|
|
597 |
|
|
|
515 |
|
Recovered grade (ounces/ton) |
|
|
0.089 |
|
|
|
0.096 |
|
|
|
0.085 |
|
Gold sold (ounces) |
|
|
44,413 |
|
|
|
57,364 |
|
|
|
43,593 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
35 |
|
|
|
37 |
|
|
|
23 |
|
Cash cost |
|
|
31 |
|
|
|
25 |
|
|
|
24 |
|
Cash profit |
|
|
4 |
|
|
|
12 |
|
|
|
(1 |
) |
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
703 |
|
|
|
439 |
|
|
|
558 |
|
Capex (millions) ($) |
|
|
48 |
|
|
|
38 |
|
|
|
26 |
|
Tons milled from Doornkop shaft were 597,000 in fiscal 2007, compared with 515,000 in fiscal
2006. Mining continues in the old, upper areas of the mine on the Kimberley reef, while the South
Reef project is developed. Volumes increased, mainly as a result of flexibility created during the
year by increasing development of the orebody. Ounces sold were 57,364 in fiscal 2007, compared
with 43,593 in fiscal 2006. This increase in ounces sold was primarily due to the increase in
recovered grade and additional tons milled. The recovered grade improved to 0.096 in fiscal 2007,
compared with 0.085 in fiscal 2006.
Cash costs per ounce of gold were U.S.$439 in fiscal 2007, compared with U.S.$558 in fiscal
2006. This decrease was attributable primarily to the higher production volumes and the higher
recovered grade.
Tons milled from Doornkop shaft were 494,000 in fiscal 2008, compared with 597,000 in fiscal
2007. Volumes were negatively affected mainly as a result of an 18 day planned production stoppage
to facilitate required shaft work and a reduction in volume at the conventional Kimberley mining
section due to low grades. The shaft work was related to the South Reef project sinking program. In
addition three days were lost to the industry through the Eskom power management process. Ounces
sold were 44,143 in fiscal 2008, compared 57,364 in fiscal 2007.
42
The decrease in ounces sold was
primarily due to the lower recovery grade and decrease in tons milled. The recovered grade deteriorated to 0.089 in fiscal 2008, compared with 0.096 in
fiscal 2007, due to the depletion of higher grade reserves in the Kimberley reef section of the
mine. The conventional mining sections of this reef mined in the channel edge areas and production
was stopped during June 2008. Production from trackless areas will continue during the build-up
phase of mining from the project South Reef areas
Cash costs per ounce of gold were U.S.$703 in fiscal 2008, compared with U.S.$439 in fiscal
2007. This increase was attributable primarily to the lower production volumes and industry wide
cost increases. It was also adversely influenced by the movement out of Capital areas into
production areas which resulted in costs previously incurred as capital expenditure, now being
spent as operational costs.
The hoisting capacity of the Doornkop shaft is 185,000 tons per month. The average tons milled
in fiscal 2008 were 41,166 tons per month.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 1.5 million tons (0.2
million ounces) will be sufficient for the Doornkop shaft to maintain production until
approximately fiscal 2019. Any future changes to the assumptions upon which the reserves are based,
as well as any unforeseen events affecting production levels, could have a material effect on the
expected period of future operations.
Capital Expenditure: We incurred approximately R349 million (U.S.$48.0 million) in capital
expenditures in fiscal 2008 at Doornkop, primarily for the shaft completion & equipping, supporting
infrastructure and development. We have budgeted R271.2 million (U.S.$37.3 million) for capital
expenditures at the Doornkop South Reef project in fiscal 2009.
Elandsrand
Introduction: Elandsrand is located near Carletonville in the North West province of South Africa.
The assets and associated liabilities were purchased during fiscal 2001 for approximately
R1 billion (U.S.$128.4 million) from Anglogold. Production from the operation is treated at the
Elandskraal plant.
History: Gold mining began at Elandsrand in 1978 following approval of the project in 1974 by
Elandsrand Gold Mining Company. Two surface shafts and two adjoining sub-vertical shafts were sunk
at Elandsrand. The sub-vertical shafts at Elandsrand, which accessed the deeper part of the VCR
reef in the lease area, were completed in 1984. The deepening of the sub-vertical shafts to
approximately 3,600 meters below surface, has been completed. Activities are currently focused on
accessing and opening up areas of the new mine and on the development and construction of support
infrastructure.
Geology: Elandsrand contains three identified main reef groupings, the Ventersdorp Contact Reef, or
VCR, the Carbon Leader Reef, or CLR and the Mondeor Reef. Only the VCR is economic to mine and has
been mined at depths below surface between 1,600 and 2,800 meters with future production to take
place up to 3,600 meters below surface at the Elandsrand operations. The VCR and CLR consist of
narrow (20 centimeters to 2 meters) tabular orebodies of quartz pebble conglomerates hosting gold,
with extreme lateral continuity.
At the Elandsrand operation, the vertical separation between the VCR and CLR increases east to
west from 900 meters to 1,300 meters as a result of the relative angle of the VCR unconformity
surface to the regional stratigraphic strike and dip. The CLR strikes west-southwest and dips to
the south at 25 degrees. The VCR strikes east-northeast and has a regional dip of 21 degrees to the
south-southeast. Local variations in dip are largely due to the terrace-and-slope palaeotopography
surface developed during VCR deposition.
Mining Operations: The Elandsrand mine is subject to the underground mining risks detailed in
the Risk Factors section.
The Elandsrand mine, a mature mine with a declining production profile, has the challenge of a
new mine being developed underneath the old mine. The implementation of Conops between August 2004
and February 2005 improved production. However, after an assessment done during fiscal 2008, Conops
was stopped during February 2008. The operation is still hampered by the lack of flexibility, an
issue that will be addressed by the full commissioning of the new mine. Due to the operating depths
of the Elandsrand underground operations, seismicity and high rock stress are significant risks at
the mine. We regularly review our mining strategy and management procedures at all of mining
operations in our efforts to mitigate these risks. The primary challenges facing the Elandsrand
operations are the lowering of working costs, increasing mining flexibility, controlling capital
expenditure and the timely completion of the Elandsrand New Mine by fiscal 2010.
Capital development on three levels of the New Mine has been completed and these levels are
producing 54% of the total ounces from the Mine. Ongoing development is taking place in both
easterly and westerly directions on these levels. Access development delays on two other levels
resulted from slow progress of the access haulages through the Cobra Dyke.
43
During 2008, further progress was made with the project, notably:
|
|
|
22 kv system to 100 level was completed and commissioned. |
|
|
|
|
The turbine dam between 92 and 95 level was completed during the year. |
|
|
|
|
The development of the refrigeration chambers on 98 and 100 level was completed. |
|
|
|
|
The centre hole of the No.3 Backfill shaft was drilled during the year and the preparation for
the sinking of the sub-bank was started in June 2008. |
|
|
|
|
The end of capital position was reached on 113 level RAW East. |
|
|
|
|
The centralized blasting system was installed and commissioned on 102, 105, 109 and 113 levels. |
|
|
|
|
All piping associated with the pumping on 115 level was installed during the year including
all electrical panels associated with the pumping. |
|
|
|
|
The chilled water feed and return shaft columns were installed in No.2 Backfill shaft from 95
to 105 level. |
The project is expected to be completed by fiscal 2010 and is expected to have a life of mine
of 20 years. From the inception of the project through the end of fiscal 2008, R776 million
(U.S.$106.8 million) has been expended. A further R228 million (U.S.$31.4 million) has been
budgeted to complete the project.
In October 2, 2007, an incident occurred at the Elandsrand operation involving a compressed
pipe column which broke off below the shaft surface bank and fell to the bottom of the men and -
material shaft, causing extensive damage to the shaft steel work and electrical cables. The
incident resulted in 3,000 workers being stranded underground for more than 30 hours. Mining
operations were temporarily suspended for 42 days to allow for repairs to be conducted in the
shaft. On November 16, 2007, we announced that a tripartite team, consisting of management, unions
and the Department of Minerals and Energy had found the shaft to be in good working condition.
Elandsrand mine was brought back into operation on November 19, 2007 after it followed
precautionary safety procedures during the start up of underground workings. Management presented
its findings of the investigation to the DME relating to the pipe failure, emergency power, water
and evacuation services and procedures, as well as the impact of Conops on maintenance. While the
emergency services were found to be acceptable, we have revised our emergency procedures and are in
the process of completing a new Code of Practice relating to emergency preparedness. Conditions in
the working places, following a 42 day period during which no production took place, were found to
be better than expected. Production at Elandsrand has resumed, and the shaft was back in full
production in December 2007.
In fiscal 2008, our Elandsrand operations accounted for approximately 8% (8% in fiscal years
2007 and 2006) of our total gold sales.
Safety: During fiscal 2008, the safety record at the Elandsrand mine in terms of lost time
frequency rate 18.49 per million hours worked compared unfavourably with the group average of
12.83. Significant work was done to address the seismic risk described above and the fatality
frequency rate (0.08) returned to a more consistent ratio with the group average of 0.18 for
underground operations. Safety standards from our other operations are being applied at Elandsrand
and receive constant and high-level attention.
Plants: Commissioned in 1978, the Elandsrand Plant has milling in closed circuit with primary and
secondary hydrocyclones, secondary ball milling in closed circuit with hydrocyclones, thickening
and cyanide leaching in a CIP pump cell carousel circuit. The CIP was commissioned after an upgrade
of the facility in 1999. Loaded carbon from the Elandsrand Plant is transported by road to the
Central Plant at Virginia for elution, electro-winning and smelting to produce gold. Residues from
the CIP are pumped either to a backfill plant or directly to the tailings facility. Ore from
Elandsrand underground operations are delivered to the plant for treatment via conveyor belt after
being hoisted from underground. Due to a high percentage of freegold, a gravity concentration
circuit is used to extract a large percentage of the gold. The sludge from this concentrator is
then transported by air to the Target Plant for extraction and smelting.
The following table sets forth processing capacity and average tons milled during fiscal 2008
for the plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for the |
|
|
Processing |
|
Fiscal Year |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Elandsrand Plant |
|
|
185,000 |
(1) |
|
|
81,713 |
|
44
|
|
|
(1) |
|
Processing capacity will reach its optimal capacity upon completion of the Elandsrand New Mine Project. |
In fiscal 2008, the Elandsrand Plant recovered approximately 96.31% of the gold contained in
the ore delivered for processing.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Elandsrand |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
981 |
|
|
|
1,117 |
|
|
|
987 |
|
Recovered grade (ounces/ton) |
|
|
0.162 |
|
|
|
0.174 |
|
|
|
0.173 |
|
Gold sold (ounces) |
|
|
158,631 |
|
|
|
194,710 |
|
|
|
170,867 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
133 |
|
|
|
124 |
|
|
|
90 |
|
Cash cost |
|
|
103 |
|
|
|
103 |
|
|
|
89 |
|
Cash profit |
|
|
30 |
|
|
|
21 |
|
|
|
1 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
652 |
|
|
|
527 |
|
|
|
523 |
|
Capex (millions) ($) |
|
|
44 |
|
|
|
33 |
|
|
|
31 |
|
Tons milled from the Elandsrand shaft were 1,117,000 in fiscal 2007, compared with 987,000 in
fiscal 2006. Ounces sold increased to 194,710 in fiscal 2007, compared with 170,867 in fiscal 2006
as a result of the increased volumes in production. Mining continues in the old, upper areas of the
mine, while the new mine project is completed. Recovered grades increased during fiscal 2007,
resulting in an average of 0.174 in fiscal 2007, compared to the average of 0.173 in fiscal 2006.
The increase in labor rates and inflation were the main contributors to the increase in cash
cost from U.S.$523 per ounce in fiscal 2006 to U.S.$527 per ounce in fiscal 2007.
Tons milled from the Elandsrand shaft were 981,000 in fiscal 2008, compared with 1,117,000 in
fiscal 2007, and ounces sold were 158,631 in fiscal 2008, compared with 194,710 in fiscal 2007.
Volumes were negatively affected, mainly as a result of days lost to the shaft accident, namely 42,
and the continued lack of flexibility in face length to deal with erratic face grades and
seismicity. The recovered grade declined during fiscal 2008 as a result of higher channel widths on
the Western section of the mine, as well as a delay in starting up some of the higher grade areas,
due to it taking longer than expected to bring the environmental conditions within standard in
deeper mining areas, after the shaft incident in October 2007.
The increase in labor rates and inflation were the main contributors to the increase in cash
cost from U.S.$527 per ounce in fiscal 2007 to U.S.$652 per ounce in fiscal 2008. Costs per ounce
have increased in fiscal 2008 by 24%, due primarily to the reduced ounces as a result of the shaft
incident causing the mine to stand for 42 days. Increases in the costs of labor and supplies,
especially steel and the effect of inflation on supply contracts further contributed to the
increase in cash cost. Electricity increases in excess of current inflation also negatively
impacted on costs.
Elandsrand currently operates one production shaft, with a current hoisting capacity of
190,000 tons per month which will be utilized to its full capacity, once the Elandsrand New Mine
Project is complete and production build reaches its maximum. The average tons milled in fiscal
2008 was 81,750 tons per month.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 44.4 million tons (8.6
million ounces) will be sufficient for the Elandsrand shaft to maintain underground production
until approximately calendar year 2026. Any future changes to the assumptions upon which the ore
reserves are based, as well as any unforeseen events affecting production levels, could have a
material effect on the expected period of future operations
Capital Expenditure: We incurred approximately R318.4 million (U.S.$43.8 million) in capital
expenditures at the Elandsrand operations in fiscal 2008 mainly for the sub shaft deepening project
and ongoing development.
45
We have budgeted R433.6 million (U.S.$59.7 million), for capital expenditures at the Elandsrand
operations in fiscal 2009, primarily for the sub-shaft deepening project and ongoing development
expenditure.
Masimong
Introduction: Masimong is located in the Free State province, near Riebeeckstad. The Masimong
complex comprises of Masimong 4 and 5 shaft. Mining is conducted at depths ranging from 1,518
meters to 1,994 meters. Ore is treated at the Central Plant and FS 1 Plant.
History: Masimong is located in the Free State Goldfield on the south-western edge of the
Witwatersrand Basin. We purchased the Masimong complex (formerly know as Saaiplaas Shafts 4 and 5)
on September 1998.
Geology: Masimong is located in the Free State Goldfield on the south-western edge of the
Witwatersrand Basin. The operation, which originally exploited the Basal Reef, is also mining
secondary reefs, most notably the Leader Reef (15-20m above Basal), the B Reef (100m above Basal)
and the A Reef (40m above the B Reef). Harmony 2 is continuing to mine high grade Basal Reef
pillars, as well as Leader Reef, but the majority of its production comes from the A Reef. The A
Reef is highly channelized and mining is confined to these distinct channels. Dips are shallow
towards the east, becoming steeper approaching the De Bron Fault in the west.
Mining Operations: The operations are subject to the underground mining risks detailed in the Risk
Factors section. Due to the shallow to moderate depths of the underground operations, seismicity
related problems are relatively infrequent. We regularly revisit our mining strategy and management
procedures in connection with our efforts to mitigate risks of these problems. There is a risk of
subterranean water and/or gas intersections in some areas of the mine. However, this risk is
mitigated by active and continuous management and monitoring, which includes the drilling of
boreholes in advance of faces. Where water and/or gas is indicated in the drilling, appropriate
preventative action is taken. The principal challenges at the operations of achieving optimal
volumes and grades of ore production are addressed by stringent ore reserve management.
In fiscal 2002, we began implementing the Masimong Expansion Project, which includes
developing the Basal and B Reef orebodies in the Masimong shaft area and equipping the shaft. The
envisaged growth from the project was not realized in 2005 and 2006, and as a result the project
was halted in June 2006. Conops was implemented in the third quarter of fiscal 2006 but, after a
reassessment, was stopped at Masimong 5 Shaft during the second quarter of fiscal 2008.
In fiscal 2008, Masimong accounted for approximately 6% (7% in fiscal 2007 and 6% in fiscal
2006) of our total gold sales.
Safety: The safety record at Masimong during fiscal 2008 in terms of LTFR of 9.57 per million hours
worked compared favorably with the group average of 12.83. The FFR of 0.12 at Masimong compared
favorably with the group average of 0.18 for underground operations.
Plants: Ore from Masimong is treated at the Central and Saaiplaas plants. See Item 4. South
African Mining Operations Virginia Operations Plants.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Masimong Shaft Complex |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
892 |
|
|
|
1,074 |
|
|
|
1,020 |
|
Recovered grade (ounces/ton) |
|
|
0.132 |
|
|
|
0.138 |
|
|
|
0.133 |
|
Gold sold (ounces) |
|
|
117,575 |
|
|
|
147,958 |
|
|
|
136,153 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
96 |
|
|
|
95 |
|
|
|
73 |
|
Cash cost |
|
|
88 |
|
|
|
82 |
|
|
|
67 |
|
Cash profit |
|
|
8 |
|
|
|
13 |
|
|
|
6 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
745 |
|
|
|
559 |
|
|
|
489 |
|
Capex (millions) ($) |
|
|
16 |
|
|
|
15 |
|
|
|
14 |
|
Tons milled from the Masimong shaft complex were 1,074,000 in fiscal 2007, compared with
1,020,000 in fiscal 2006, and ounces sold were 147,958 in fiscal 2007, compared with 136,153 in
fiscal 2006. Year on year production was slightly higher with a slightly higher recovery grade.
46
Cash costs were U.S.$82 million in fiscal 2007 compared with U.S.$67 million in fiscal 2006
with cash costs per ounce at U.S.$559 in fiscal 2007 compared with U.S.$489 in fiscal 2006. This
increase in cash cost is mainly attributable to increase in labor costs as a result of the annual
wage increases as well as a 21% increase in number of employees. This increase in people was to
fully staff the operation for Conops. This was the first year that Masimong was fully on a Conops
cycle. The effect of Conops is increased costs in the short-term as additional people are utilized
without being fully operational, but increased profitability in the longer-term as higher volumes
have a positive impact on the bottom-line.
Tons milled from the Masimong shaft complex were 892,000 in fiscal 2008, compared with
1,074,000 in fiscal 2007. Ounces fold were 117,575 in fiscal 2008, compared with 147,958 in fiscal
2007. This is mainly attributable to the reduction in tons milled.
The drop in recovered grade by 0.006 ounces per ton from fiscal 2008 to fiscal 2007 can be
attributed to a 2.63% drop in grade mined and a 0.715% drop in the mine call factor. Both these
parameters were negatively influenced by the B Reef, as mining of B Reef in fiscal 2008 was
significantly focussed in the South Eastern portion of the 5 shaft lease area. This area is
typically a highly channelized deposit with economic channels occuring at oblique to perpendicular
angles to the normal depositional axis of the B Reef. These channels are generally small measured
on the latitudinal axis and highly unpredictable, thus making mining and valuation extremely
difficult.
Cash costs were U.S.$88 million in fiscal 2008 compared with U.S.$82 million in fiscal 2007
with cash costs per ounce at U.S.$745 in fiscal 2008 compared with U.S.$559 in fiscal 2007. This
increase in cash cost is mainly attributable to increase in labor costs as a result of the annual
wage increases.
The total shaft hoisting capacity is 134,000 tons per month. The average tons milled in fiscal
2008 were 74,354 tons per month.
The Conops production cycle was stopped on Masimong in December 2007. Through restructuring
and reengineering, the excess labor was identified and relocated to other shafts. This process was
completed in March 2008. Additional Conops costs were incurred during the phasing out period
(lower production with the full complement of Conops labor).
The year on year decrease in tonnage from fiscal 2007 to fiscal 2008 is a result of the
abovementioned stoppage of Conops The mine plan was revised during January 2008 to adjust to the
non-Conops production cycle.
During the initial stages of restructuring significant production upsets were encountered due
to the redeployment of mine employees and termination of contractors and labor hire employees.
This upset was especially evident in the March 2008 quarter, when production dropped to
160,832 tons which equates to a 20.7% drop from the previous (December 2007) quarter. the June
2008 quarter was the first full normalized production quarter after the stoppage of Conops
production cycle.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 5.1 million tons (0.8
million ounces) will be sufficient for the Masimong shaft complex to maintain underground
production until approximately fiscal 2018. Any future changes to the assumptions upon which the
reserves are based, as well as any unforeseen events affecting production levels, could have a
material effect on the expected period of future operations.
Capital Expenditure: We incurred approximately R114.0 million (U.S.$15.7 million) in capital
expenditures at Masimong in fiscal 2008. We have budgeted a total of R109.4 million ($15.0 million)
for capital expenditures at Masimong in fiscal 2009. Of this, R17.0 million (U.S.$2.3 million) is
for upgrading of the rail bound equipment, with the remainder budgeted for ongoing development.
Virginia operations
Introduction: The Virginia operations are located in the Free State province, near Virginia. The
Virginia operations consist of the original Harmony mines, the Unisel mine, Brand shafts 2, 3 and
5. Mining is conducted at these operations at depths ranging from 682 meters to 2,042 meters. Ore
is treated at the Central Plant and FS 1 Plant.
History: Our operations in the Free State began with the Harmony mine, which is an amalgamation of
the Harmony, Virginia and Merriespruit mines. Beginning in 1996, we began purchasing neighboring
mine shafts. The Unisel mine was purchased in September 1996, the Saaiplaas mine Shafts 2 and 3
were purchased in April 1997, the Brand mine Shafts 2, 3 and 5 were purchased in May 1998.
47
Geology: These operations are located in the Free State Goldfield on the south-western edge of the
Witwatersrand Basin. The operations, which originally exploited the Basal Reef, are also mining
secondary reefs, most notably the Leader Reef (15-20m above Basal), the B Reef (100m above Basal)
and the A Reef (40m above the B Reef). Harmony 2 is continuing to mine high grade Basal Reef
pillars, as well as Leader Reef, but the majority of its production comes from the A Reef. The A
Reef is highly channelized and mining is confined to these distinct channels.
Merriespruit 1 is exploiting the Basal and Leader reefs, as well as locally developed high
grade Middle Reef pockets. The mining operations of the Middle Reef was discontinued during 2008
at Merriespruit 1 shaft. Dips at Merriespruit 1 shaft tend to be at 8° to the north west with
numerous east west trending Faults/Dykes which cut through the shaft pillar , the Dolfin Sill
which disrupt the reef horizoning the north east and the De Bron Fault in the west. Merriespruit 3
shaft is mining Leader and Basal reef, with the majority being concentrated on the Leader reef due
to the fact that a large area of the shaft is beyond the zone of convergence with the Basal reef.
Dips tend to be between 10° and 20° to the Northwest. The structure is fairly complicated with the
De Bron fault in the west, the Virginia fault in the east and the Merriespruit thrust fault in the
south, resulting in significant strike and dip changes and large overlapping reef blocks.
At Unisel, the Basal, Middle and Leader Reefs are mined, with reefs dipping 30° to the east.
The structure is complex due to a number of north-south trending faults as well as sills close to
the Basal Reef. Brand 1/3 is mining Basal pillars together with the A Reef. The structure is
dominated by north-south trending faults, often with lateral shift. Brand 2 and 5, currently on
care and maintenance, have mined mostly Basal and Leader Reefs.
Mining Operations: The operations are subject to the underground mining risks detailed in the Risk
Factors section. Due to the shallow to moderate depths of the underground operations, seismicity
related problems are relatively infrequent with the exception of Unisel and Harmony shafts and
Merriespruit 1 shaft pillar, where these problems receive constant attention. We regularly revisit
our mining strategy and management procedures in connection with our efforts to mitigate risks of
these problems. There is a risk of subterranean water locally at Merriespruit 1, referred to as
water pillar area, and/or gas intersections in some areas of the mine. However, this risk is
mitigated by active and continuous management and monitoring, which includes the drilling of
boreholes in advance of faces. Where water and/or gas is indicated in the drilling, appropriate
preventative action is taken. The principal challenges at the operations of achieving optimal
volumes and grades of ore production are addressed by stringent ore reserve management.
Development was restarted at the Virginia operations in 2006, a positive life of mine has been
re-established on all the shafts and the shafts have returned to profitability.
Merriespruit 1 installed a floating shaft tower in the shaft barrel in 2005, to allow mining
of the shaft pillar. Mining of the inner shaft pillar commenced in October 2006 and is being
successfully mined. Approximately 70% of the pillar is mined out.
Merriespruit 3 shaft improved its haulage and tramming conditions during fiscal 2007 and 2008,
allowing the shaft to improve its safety and tonnage profile. Equipping of basal reef on 12 level
took place during 2008 and limited mining of the basal reef will resume for the first time since
2002.
Harmony 2 shaft re-started the H2 shaft pillar Leader reef exploration program in 2005,
following the improvement in the gold price. This ground has been successfully mined and the
extension of the pay shoot towards H3 shaft is currently being explored. The evaluation and
quantification of the A reef vent project block were completed in 2007 (drilling etc.) and
development started in 2008. Basal reef pillars belonging to Merriespruit 1 are being accessed
through the shaft. The 1st pillar is currently being mined and equipping towards further
pillars is ongoing.
Brand 1 shaft is being utilized to mine the Brand 1 and 3 ore bodies. Major effort has been
done to improve the infrastructure of the shaft, which has allowed the shaft to improve its tonnage
handling to the current levels of some 44 000t per month. A loop is currently being developed in
the 40 level haulage to allow access to the A reef in the Brand 3 area. This will allow improved
servicing of the area and a 2,5 Km reduction in tramming distances.
At Brand mine the grade remained constant year on year at 0.103g/t, while the tonnage increased
from 445,000 tons to 459,000 tons. This resulted in an increased gold production, up from 45611
ozs in 2007 to 47101 oz,s in 2008. The tonnage increased as a result of improved efficiencies in
2008 in spite of Eskom power supply problems in the second half of the production year.
48
Unisel experienced a decrease in tonnage from 614,000 tons in 2007 to 547,000 tons in 2008. This
was primarily a consequence of the Eskom power cuts in February and lower subsequent production as
a result of power restrictions. At the same time the mine experienced a decline in grade from 0.130
in 2007 to 0.124 in 2008 due to the depletion of higher grade Middle Reef panels. The combined
factors of tonnage and grade led to the decrease in ounces from 79,992 in 2007 to 67,613 in 2008
The Brand 2 and Brand 5 Shafts are currently on care and maintenance whilst Brand 5 serves as a
major pumping shaft for the President Steyn, Brand, Bambanani and Unisel mining areas. Harmony 3
shaft is currently used only as a service shaft for pumping although some of its reserves are mined
through the adjacent Harmony 2 shaft.
In fiscal 2008, Virginia operations accounted for approximately 13% (12% in fiscal 2006 and
2007) of Harmonys total gold sales.
Safety: The safety record during fiscal 2008 in terms of LTFR of 19.79 per million hours worked
compared unfavorably to the group average of 12.83. The FFR of 0.20 compared unfavorably to the
group average of 0.18 for underground operations.
Plants: There are two metallurgical plants at the Free State operations, namely Central and
Saaiplaas plants. A third plant, Virginia plant, was closed in fiscal 2005 and clean-up operations
implemented and, during fiscal 2008, a project was initiated on the demolition of the plant which
will continue through into fiscal 2010. The Central plant was commissioned in 1986 and employs
CIP/CIL hybrid technology. It is currently dedicated to the treatment of both underground ore and
waste rock. The Saaiplaas plant, commissioned in the late 1950s, has been converted from the zinc
precipitation filter process to the CIL. It currently processes reclaimed slime at 6 million tons
per annum.
The following table sets forth processing capacity and average tons milled during fiscal 2008
for each of the plants:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled |
|
|
|
|
|
|
for the Fiscal Year |
|
|
Processing |
|
Ended |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Central |
|
|
168,000 |
|
|
|
141,500 |
|
Saaiplaas |
|
|
500,000 |
|
|
|
583,650 |
|
In fiscal 2008, our Central plant recovered approximately 95% of the gold contained in the ore
delivered for processing and approximately 48.7% at the Saaiplaas plant.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Virginia operations |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
2,349 |
|
|
|
2,507 |
|
|
|
2,368 |
|
Recovered grade (ounces/ton) |
|
|
0.107 |
|
|
|
0.106 |
|
|
|
0.117 |
|
Gold sold (ounces) |
|
|
250,324 |
|
|
|
266,948 |
|
|
|
276,285 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
204 |
|
|
|
172 |
|
|
|
146 |
|
Cash cost |
|
|
180 |
|
|
|
147 |
|
|
|
135 |
|
Cash profit |
|
|
24 |
|
|
|
25 |
|
|
|
11 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
719 |
|
|
|
546 |
|
|
|
487 |
|
Capex (millions) ($) |
|
|
20 |
|
|
|
19 |
|
|
|
14 |
|
Tons milled from the Virginia operations increased to 2,507,000 in fiscal 2007, compared with
2,368,000 in fiscal 2006. This is partially attributable to the increase in volumes at Merriespruit
1, mainly as a result of being able to commence mining in the shaft pillar area, after completion
of the shaft tower installation project.
49
Equipping and development was enhanced enabling entry to panels at an increased rate. Also
contributing to this increase in tons milled was the improved blasting frequency at Unisel. This
increase was offset by a decrease in tons milled of 81,000 at Harmony 2, primarily due to an
underground fire experienced in the Basal pillar.
Ounces sold were 266,948 in fiscal 2007, compared with 276,285 in fiscal 2006. The decrease in
ounces sold was negatively influenced by the lower grade. Contributing to the decrease in average
grade was the fire in the high grade basal pillar area at Harmony 2, where the grade decreased from
0.116 in fiscal 2006 to 0.089 in fiscal 2007. The erratic grade of the Middle reef at Merriespruit
1 also attributed to the decrease in grade. The negative impact of the grade on the ounces sold was
partially offset by the increase in ounces sold from the other operations, mainly due to an
increase in volumes.
Cash costs were U.S.$147 million in fiscal 2007, compared with U.S.$135 million in fiscal
2006. This increase was primarily attributed to higher production levels and an increase in labor
cost. Included is approximately R3.1million (U.S.$0.4 million) for costs to fight the fire at
Harmony 2 and replace critical items lost in the fire. Merriespruit 1 experienced an increase in
costs as a result of the additional support required in the shaft pillar area. At Unisel,
additional costs were incurred for upgrade of the refrigeration plant and infrastructure. Cash
costs per ounce were U.S.$546 in fiscal 2007, compared with U.S.$487 in fiscal 2006. This increase
was attributable primarily to a lower recovery grade resulting in lower ounces as well as an
increase in cash costs.
Tons milled from the Virginia operations decreased from 2,507,000 in fiscal 2007 to 2,349,000
in fiscal 2008. A fire at Merriespruit 1 affected production in the first quarter of fiscal 2008 and
also adversely affected the flexibility at this operation. Labor shortages and power outages also
affected production negatively in the latter part of the year. Industrial action by labor unions
led to loss of production shifts. Stoping restrictions as recommended by rock engineers affected
production in the pillar areas.
Lack of availability of replacement ground at Merriespruit 3 also impacted negatively on the
volumes for fiscal 2008. Stoping width restrictions to 2.5m by Rock engineering recommendations,
adversely affected both tons and gold content (less channel exposure resulting in lower gold
content, and lower stope width in lower tons.) The marginality of the ore body and the subsequent
stop-start history of the development on the shaft during periods of lower gold price have created
an availability and flexibility problem on the shaft. Labor availability was problematic, with less
than planned crews available for a significant period of the year. (17 out of 18 crews) The
location and opening of the downdip extension of a wide leader pay shoot and a change of mining
direction to parallel the pay trend to reduce the crew moves proved successful.
Harmony 2 shaft was affected by power shortages during the third quarter resulting in a number
of lost production shifts. Coupled with this was an incident at the substation at Harmony 2 Shaft
which led to a loss of 2 shifts in March 2008. Seismicity in high grade basal pillars leading to a
drop in the face grade and production stoppages during fiscal 2008. A low strike rate from
development led to a slow opening up of payable reserves resulting in a lack of flexibility. Labor
shortages were also experienced especially after the Voluntary Retrenchment Scheme during which no
outside labor could be hired as replacement prior to the relocation of labor from other Harmony
shafts.
Ounces sold were 250,524 in fiscal 2008, compared with 266,948 in fiscal 2007. The decrease in
ounces was primarily due to a decrease in tons milled. The grade for fiscal 2008 of 0.107 was
similar to the recovered grade of 0.106 for fiscal 2007.
Cash costs were U.S.$180 million in fiscal 2008, compared with U.S.$147 million in fiscal
2007. This can be partly attributed to an increase in labor cost as well as costs at Merriespruit 1
for additional support required in the shaft pillar area and the cost related to the fire in the
first quarter. Cash costs per ounce were U.S.$719 in fiscal 2008, compared with U.S.$546 in fiscal
2007. This increase was attributable primarily to increased labor rates and inflationary
escalations as well as the decrease in ounces produced.
The upgrading of the old infrastructure at Brand 3 and Unisel during fiscal 2008 led to the
increase in their cash cost. Labor in fiscal 2008 on Brand 3 increased due to the inclusion of
equipping crews to assist with the opening up of old areas, which were previously stopped. This led
to the increase in the tons and an increase in plant costs. The inclusion of the Bobebe employees,
previously carried by Central Services contributed to the increase in our cash costs. The upgrading
of rails and the loco conversions on Unisel and Brand 3, to comply to new railbound
specifications, also contributed to the higher cash costs in fiscal 2008.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 8.5 million tons (1.1
million ounces) will be sufficient for the Virginia operations to maintain production until
approximately 2015. However, any future
50
changes to the assumptions upon which the reserves are based, as well as any unforeseen events
affecting production levels, could have a material effect on the expected period of the future
operations.
Capital Expenditure: We incurred approximately R152 million (U.S.$20 million) in capital
expenditures at the Virginia operations in fiscal 2008, principally for ongoing capital
development. We have budgeted R138 million (U.S.$18 million) for ongoing capital development in
fiscal 2009, as well as R7 million (U.S.$0.9 million) for upgrading rail bound equipment. An
additional R10 million (U.S.$1 million) has been earmarked for various drilling exploration
projects.
Target
Introduction: We acquire the Target mine when Avgold became a wholly owned subsisdiary in fiscal
2004. Target is situated near the town of Allanridge in the Free State Province, some 270
kilometers southwest of Johannesburg. Located at approximately latitude 28 (LOGO) 00S and
longitude 26 (LOGO) 30E on the northern limit of the Welkom Goldfields, the site is accessed via
the R30 motorway situated between the towns of Bothaville and Welkom.
History: The Target Operations area was initially explored through surface drilling in the late
1980s with further exploration being undertaken from a 5.6 kilometers long decline, commenced in
1995, driven from 203L at Lorraine No. 1 Shaft. A positive feasibility study into the development
of a 105 ktpm operation was produced in May 1998 resulting in the decision to develop the Target
mine. A detailed mine design was produced in 2000 and the mine officially opened in May 2002. Upon
closure of the Lorraine mine in August 1998, the Lorraine No. 1 and No. 2 Shafts were transferred
to the Target mine, becoming Target No. 1 and No. 2 Shafts, respectively.
Geology: The gold mineralization currently exploited by Target mine is contained within a
succession of Elsburg and Dreyerskuil quartz pebble conglomerate reefs hosted by the Van Heeverrust
and Dreyerskuil Members of the Eldorado Formation, respectively. Additional mineral resources have
been delineated in the Big Pebble Reefs of the Kimberley Formation but these are not planned to be
exploited in the current life of mine plan.
The majority of the mineral reserves at Target mine are contained within the Eldorado fan, a
structure with dimensions of some 135 meters vertically, 450 meters down-dip and 500 meters along
strike. The Eldorado fan is connected to the subsidiary Zuurbron fan, located between the Target
mine and Lorraine, by a thinner and lower grade sequence of Elsburg reefs termed the Interfan area.
To the north of the Eldorado fan, a number of fans have been intersected by surface drilling of
which the Siberia and Mariasdal fans are the most significant. These fans are subject to ongoing
technical studies and do not form part of the current Target mine life of mine mineral reserve.
A number of faults that displace the reefs of the Target mine have been identified of which the
most prominent are the north-south trending Eldorado fault and the east-west trending Dam and Blast
faults. The Eldorado uplifts the more distal portions of the Elsburg and Dreyerskuil Reefs while
the Blast fault forms the northern border of the Target mine.
Target North is sub-divided into the Paradise, Siberia and Mariasdal areas by the east-west
trending Siberia and Mariasdal faults. To the north of the Siberia fault, the Eldorado fault
continues trending more to the northwest and an additional north-south trending fault, the Twin
fault has uplifted the distal portions of the reefs. North of the Maraisdal fault, the reef
horizons are at a depth greater than 2,500 meters below surface. Resources have been delineated on
strike up to 15 kilometers north of the Target mine
Approximately 40 kilometers north of Target mine, surface boreholes have intersected gold
bearing reefs in the Oribi area close to the town of Bothaville. Resources have been delineated at
Oribi on the VCR and Elsburg at depths of approximately 2,750 meters below surface.
Mining operations: Target is subject to the risks associated with underground mining detailed in
the Risk Factors section.
Mining operations comprise one primary underground mine commissioned in May 2002, making use
of information systems and mechanization, combined with process-driven organizational design that
relies on a multi-skilled workforce. The majority of the production is derived from mechanized
mining; however, conventional stoping is still employed primarily to de-stress areas ahead of the
mechanized mining.
In fiscal 2008, Target experienced a number of issues, including falls of ground, flooding,
the low availability of mechanized equipment and belt systems and poor fragmentation in the massive
stopes. These all contributed to significantly reduce volumes and flexibility. The mine also
51
continued
to contend with issues such as grade and grade estimation, an area which received a great deal of attention in the last
quarter, and which showed signs of improvement.
Some of the new trackless fleet arrived in the second half of fiscal 2008 and the water
handling problems (that caused flooding of the ends) had largely been addressed by June 2008.
In fiscal 2008, Targets operations accounted for 4% of our total gold sales (6% in fiscal years
2007 and 2006).
Safety: The safety record at Target during fiscal 2008 in terms of lost time frequency rate of
10.76 per million hours worked compared favorably with the group average of 12.83 while the
fatality frequency rate of 0.0 compared favorably with the group average of 0.18 for underground
operations.
Safety at the operations receives constant and high-level attention and where problems are
identified steps are taken to address the situation.
Plants: Target Plant was commissioned towards the end of 2001, and currently treats both
underground ore and surface waste rock dump. The process route comprise primary crushing, open
circuit primary SAG milling, secondary ball milling closed with hydrocyclones, thickening, cyanide
leaching, CIP adsorption, elution, electrowinning, smelting and tailings disposal. The milling
circuit incorporates gravity concentration, the concentrates from which are processed via intensive
cyanidation and electrowinning.
The installation of a ROM mill to enable the mills to run autogenously is complete and the ROM
mill was commissioned in November 2007. The total project capital expenditure was R22 million
(U.S.$3 million). The objective is to save R 1.2 million on grinding media monthly. All capital on
this project has been spent and the project was closed during May 2008.
The following table sets forth processing capacity and average tons milled during fiscal 2008:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled For the |
|
|
Processing |
|
Fiscal Year Ended |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Target Plant |
|
|
105,000 |
|
|
|
97,973 |
|
In fiscal 2008, the Target Plant recovered approximately 96% of the gold contained in the ore
delivered for processing.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Target |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
686 |
|
|
|
904 |
|
|
|
813 |
|
Recovered grade (ounces/ton) |
|
|
0.124 |
|
|
|
0.158 |
|
|
|
0.185 |
|
Gold sold (ounces) |
|
|
85,006 |
|
|
|
142,433 |
|
|
|
150,196 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
69 |
|
|
|
91 |
|
|
|
81 |
|
Cash cost |
|
|
51 |
|
|
|
53 |
|
|
|
52 |
|
Cash profit |
|
|
18 |
|
|
|
38 |
|
|
|
29 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
605 |
|
|
|
370 |
|
|
|
346 |
|
Capex (millions)($) |
|
|
35 |
|
|
|
16 |
|
|
|
10 |
|
Tons milled from the Target shaft increased to 904,000 in fiscal 2007, compared with 813,000
in fiscal 2006. The age of the current fleet (vehicles) is of a big concern.
Ounces sold were 142,433 in fiscal 2007, compared with 150,196 in fiscal 2006. The decrease in
ounces sold, was negatively influenced by the lower grade. The recovery grade decreased from 0.185
in fiscal 2006 to 0.158 in fiscal 2007.
52
Cash costs for Target were U.S.$53 million in fiscal 2007, compared with U.S.$52 million in
fiscal 2006. This increase was primarily attributed to higher production levels, and an increase in
labor cost. Cash costs per ounce were U.S.$370 in fiscal 2007, compared with U.S.$346 in fiscal
2006. This increase was attributable primarily to a lower recovery grade as well as an increase in
cash costs.
Tons milled from the Target shaft decreased from 904,000 in fiscal 2007 to 686,000 in fiscal
2008. The main issues contributing to the drop in production include trackless fleet availability,
flooding of mining block, fragmentation problems in massive stopes and lack of face length
especially for massive stopes. Problems encountered in the massive stopes were the main
contributor to grade and volume decreases.
Ounces sold were 85,006 in fiscal 2008, compared with 142,433 in fiscal 2007. The decrease in
ounces sold was negatively influenced by the lower grade. The recovery grade decreased from 0.158
in fiscal 2007 to 0.124 in fiscal 2008.
Cash costs for Target were U.S.$51 million in fiscal 2008, compared with U.S.$53 million in
fiscal 2007. This decrease was primarily attributed to lower production levels. Cash costs per
ounce were U.S.$605 in fiscal 2008, compared with U.S.$370 in fiscal 2007. This increase was
attributable primarily to a lower recovery grade.
The fleet replacement project is progressing well and it is expected to have a newer fleet
with better availability by December 2008. The flooding problems are largely due to inferior dam
capacity and pumping infrastructure at the main dam. A new dam is being constructed and is
expected to be completed by March 2009. In the interim period, the current dam and pumping
arrangements have been upgraded and the risk of flooding will be reduced significantly by September
2008. Fragmentation in the massive stopes was as a result of excessive hydraulic radius used in the
planning phase. This has been addressed and all new massive stopes that have come into operation
from July 2008 are at smaller dimensions to address the fragmentation issue.
The focus for fiscal 2009 will be the development of the new decline to access the Block 3
area which contains 40% of the mines gold reserves. Production is expected to be a steady state of
65 000 tonnes per month for the next two years after which we expect to ramp up to the 80 000
tonnes per month at a grade of 5.5g/t to 6g/t.
The Target shafts hoisting capacity is 110,000 tons per month. The average tons milled in
fiscal 2008 was 57,259 tons per month.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 21.9 million tons
(4.25 million ounces) will be sufficient for the Target shaft to maintain production until
approximately 2028. However, any future changes to the assumptions upon which the reserves are
based, as well as any unforeseen events affecting production levels, could have a material effect
on the expected period of the future operations.
Capital Expenditure: We incurred approximately R257 million (U.S.$35 million) in capital
expenditures at the Target shaft in fiscal 2008, principally for underground development and the
replacement of the underground fleet. We have budgeted R370 million (U.S.$51 million) for capital
expenditures at Target in fiscal 2009, primarily for underground development, as well as the
replacement of the underground vehicles.
Evander Operations
Introduction: The Evander operations are located in the province of Mpumalanga in South Africa and
are comprised of an amalgamation of the former Kinross, Bracken, Leslie and Winkelhaak mines and
36,898 hectares of mineral rights adjacent to these mines. Mining at our Evander operations is
conducted at depths ranging from 300 meters to 2,100 meters.
History: Gold mining in the Evander Basin began in 1955. Eventually, four mining operations were
established at Evander. In 1996, as a result of depletion of ore reserves, all four mining areas
were merged to form Evander. In August 1998, we acquired Evander as a wholly-owned subsidiary.
Geology: The area covered by Evanders mining authorization and mineral rights is situated within
the Evander basin, a geologically discrete easterly extension of the main Witwatersrand Basin. Only
one economic placer unit, the Kimberley Reef, is mined at Evander. In addition to the faulting of
the reef horizon, there are numerous dykes and sills that complicate the mining layouts, the most
significant of which is an extensively developed dolerite footwall sill that occasionally
intersects the Kimberley Reef, causing displacements within it.
Mining Operations: The Evander operations are primarily engaged in underground mining. The Evander
operations also process a limited amount of waste rock as and when necessary to allow the plants to
operate efficiently. These operations are subject to the underground mining risks detailed in the
Risk Factors section.
53
Due to the shallow to moderate depths of the Evander underground operations, seismicity and
pressure high rock stress-related problems are relatively infrequent. There is a risk of
subterranean water and/or gas intersections in some areas of the mine. However, this risk is
mitigated by active and continuous management and monitoring, which includes the drilling of
boreholes in advance of faces. Where water and/or gas is indicated in the drilling, appropriate
preventative action is taken. In fiscal 2004, an agreement was reached with the unions for the
implementation of Conops at Evander. Downsizing and restructuring of the 7 Shaft area resulted in
labor surpluses and it was also decided to stop Conops in fiscal 2008 at Evander 5 shaft. Parts of
Evander 8 shaft continue to work on Conops.
During fiscal 2005, the Evander 2 and 5 Shafts were combined and downscaled, while the Evander
9 Shaft was closed successfully and placed on care and maintenance. The Evander 9 Shaft employees
were transferred to other Evander operations. The Evander 7 Shaft (Decline No. 3, phase 3) project
was terminated in fiscal 2008.
Potential exists at several areas in Evander:
Evander South
|
|
|
Project currently at an exploration stage following the prefeasibility study; |
|
|
|
|
Surface exploration drilling to be carried out in order to improve quality
of and confidence in the current estimate; and |
|
|
|
|
Drilling to commence in October 2008. |
Shaft 7 portion of the 2010 Payshoot.
|
|
|
Project at an initial exploration stage following the geological study; |
|
|
|
|
Underground development and drilling, underground and from surface, is planned in
order to investigate the 7 Shaft flank of the postulated payshoot; and |
|
|
|
|
Feasibility study to follow, pending confirmation of the ore resource in this area. |
Twistdraai and Shaft 6
|
|
|
Joint Venture with the African Precious Minerals (APM) is being formed to
explore these two target areas; |
|
|
|
|
APM is going to earn in the 52% equity stake upon completion of the full
bankable feasibility study for each area; and |
|
|
|
|
The geological studies are under way and drilling will commence in fiscal 2009. |
Rolspruit
|
|
|
It is a future mining area of the current Shaft 8; |
|
|
|
|
Pre-feasibility study is being updated with more recent cost and gold price factors; and |
|
|
|
|
Synergies with the current Shaft 8 deepening could be considered. |
Poplar
|
|
|
Surface exploration drilling is required to bring this project into the full bankable feasibility study; |
|
|
|
|
Pre feasibility study is due to be updated (after the Rolspruit study) with costs and gold price
factors; and |
|
|
|
|
The surface exploration drilling at Evander South is likely to produce information that will enhance
the Poplar geological interpretation. |
In fiscal 2008, the Evander operations accounted for approximately 12% (10% in fiscal 2007 and
12% in fiscal 2006) of our total gold sales.
Safety: The safety record at the Evander operations in terms of LTFR of 16.64 per million hours
worked during fiscal 2008 is unfavorable when compared to the group average of 12.83. The FFR of
0.07 during fiscal 2008 is favorable when compared to the group average of 0.18 for underground
operations.
54
Plants: Evander has one active processing plant, the Kinross-Winkelhaak plant, which is operated as
two geographically distinct sections. Ore from Evander 7 and 8 is hoisted directly to and treated
at the Kinross plant, which is a CIL plant. All of the ore from Shafts 2 and 5 is milled and
thickened at the Winkelhaak plant, and the slurry is pumped to the Kinross plant for further
processing.
The following table sets forth processing capacity and average tons milled during fiscal 2008
for the operating plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for the |
|
|
Processing |
|
Fiscal Year Ended |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Kinross-Winkelhaak |
|
|
200,000 |
|
|
|
120,564 |
|
In fiscal 2008, the plant at Evander operations recovered approximately 96.4% f the gold
contained in the ore delivered for processing.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Evander operations |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
1,447 |
|
|
|
1,667 |
|
|
|
1,700 |
|
Recovered grade (ounces/ton) |
|
|
0.166 |
|
|
|
0.141 |
|
|
|
0.161 |
|
Gold sold (ounces) |
|
|
240,037 |
|
|
|
235,443 |
|
|
|
274,439 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
193 |
|
|
|
151 |
|
|
|
142 |
|
Cash cost |
|
|
127 |
|
|
|
113 |
|
|
|
111 |
|
Cash profit |
|
|
66 |
|
|
|
38 |
|
|
|
31 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
525 |
|
|
|
481 |
|
|
|
404 |
|
Capex (millions) ($) |
|
|
33 |
|
|
|
28 |
|
|
|
26 |
|
Tons milled at the Evander operations were 1,667,000 in fiscal 2007, compared with 1,700,000
in fiscal 2006, and ounces sold were 235,443 in fiscal 2007, compared with 274,439 in fiscal 2006.
The decrease in tons milled was due to the depletion of the open raise lines on 24 level at Evander
5. The decrease in tons milled partially offset by an increase in tons from the mining of pillar
areas at Evander 7 and 8. The decrease in ounces was due to the significantly lower production in
reef tons as the shafts started to hoist waste with reef that dilutes the quality of the ore. At
Evander 7, the grade decreased, primarily due to the depletion of a very high grade pay shoot in
the No 3 decline areas and the increase in mining in the lower grade pillar area of the shaft. The
recovered grade at Evander 8 decreased as well as a result of payshoot variability due to
sequential mining. The decrease in recovered grade was partially offset by an improvement of the
MCF from 62% in 2006 to 70.5% in 2007 at Evander 5.
The increase in cash costs from U.S.$404 per ounce in fiscal 2006 to U.S.$481 per ounce in
fiscal 2007 was attributable primarily to the decrease in ounces produced as a result of the
decrease in recovery grade.
Tons milled at the Evander operations were 1,447,000 in fiscal 2008, compared with 1,667,000
in fiscal 2007, and ounces sold were 240,037 in fiscal 2008, compared with 235,443 in fiscal 2007.
The decrease in tons milled is partially attributable to the reduction of the development at
Evander 7 in November 2007 and the closure of the pillars in the old mine in February 2008. At
Evander 8, tons milled decreased by 113,000 tons due to poorer environmental conditions in the
decline area which affected mining from this area. The shaft is currently busy with a
raise-borehole from 17 Level to 24 Level which will alleviate the medium term ventilation
constraints. Recovered grade was 0.166 in fiscal 2008, compared with 0.141 in fiscal 2007. The
higher recovered grade is partially due to an improvement of the MCF at Evander 5 from 70,5% in
2007 to 71,7% in 2008, as well as mining in higher grade areas at the shaft. At Evander 7 and 8,
the closure of the more marginal pillar sections and focusing on the higher grade decline sections
also contributed to the higher recovered grade.
55
The increase in cash costs from U.S.$481 per ounce in fiscal 2007 to U.S.$525 per ounce in
fiscal 2008 was attributable primarily due to the increase in cash costs from U.S.$113 million in
fiscal 2007 to U.S.$127 million in fiscal 2008 as result of labor increases and inflation on
consumables and electricity increases in excess of current inflation. Excess employees from Evander
7 in lieu of the restructuring as impacted negatively on the cash costs.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 11.2 million tons (1.9
million ounces) will be sufficient for the Evander operations to maintain production until
approximately fiscal 2027. Any future changes to the assumptions upon which the reserves are based,
as well as any unforeseen events affecting production levels, could have a material effect on the
expected period of future operations.
Capital Expenditure: We incurred approximately R242 million ($33 million) in capital expenditures
at the Evander operations in fiscal 2008. The expenditure was primarily for ongoing development as
well as deepening of the decline shaft systems at Evander 7 and 8. We have budgeted R174 million
($22 million) for capital expenditures in fiscal 2009 primarily for ongoing development and the
upgrading of major equipment. Included is also an amount for phases 6 and 7 of the No 2 decline at
Evander 8 and two ventilation bore holes. The No 3 decline project at Evander 7 was stopped in
November 2007.
Other Underground
Introduction: Other Underground consists of several shafts, including Joel and St Helena. As the
most significant portion of the results from this segment is attributable to Joel, we have only
disclosed the relevant information for Joel.
History: Joel was purchased from a subsidiary of AngloGold at the same time as the rest of the
Freegold assets in January 2002.
Geology: The mine is located in the Free State Goldfield, which is on the southwestern edge of the
Witwatersrand basin. Joel is located 30 kilometers south of Welkom and is mining the shallow
flat-dipping Beatrix/VS5 Reef.
Mining operations: These operations are subject to the underground mining risks detailed in the
Risk Factors section.
Mining takes place at an average depth of approximately 1,200 meters at Joel.
During fiscal 2008, Joel accounted for 3% of our total gold sales (3% in fiscal 2007 and 2% in
fiscal 2006
Safety: During fiscal 2008, the LTFR at Joel of 4.91 per million hours worked compared favorably
with the group average of 12.83. The FFR at Joel of 0.00 compared favorably with the group average
of 0.18.
Plants: The Joel plant is a hybrid CIP/CIL plant and was commissioned in 1987. During fiscal 2005,
it was decided to close the Joel Plant and place the plant under care and maintenance. A
feasibility study is underway to investigate the possibility of reopening the Joel plant around
January 2009.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
|
Joel |
|
2008 |
|
|
2007 |
|
|
2006 |
|
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
449 |
|
|
|
504 |
|
|
|
436 |
|
Recovered grade (ounces/ton) |
|
|
0.136 |
|
|
|
0.158 |
|
|
|
0.134 |
|
Gold sold (ounces) |
|
|
61,215 |
|
|
|
79,923 |
|
|
|
58,595 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
52 |
|
|
|
51 |
|
|
|
31 |
|
Cash cost |
|
|
39 |
|
|
|
33 |
|
|
|
29 |
|
Cash profit |
|
|
13 |
|
|
|
18 |
|
|
|
2 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
639 |
|
|
|
418 |
|
|
|
498 |
|
Capex (millions) ($) |
|
|
5 |
|
|
|
4 |
|
|
|
4 |
|
56
Tons milled from Joel shaft increased to 504,000 in fiscal 2007, compared with 436,000 in
fiscal 2006, attributable primarily to the commissioning of the mineshaft loading arrangement on
137 level. Tons milled were negatively influenced in fiscal 2007 due to ceasing hoisting operations
at North Shaft on March 15, 2007 for the sinking stage removal, guide rope installation and the
installation of a proper spillage arrangement at shaft bottom. Ounces sold were 79,923 in fiscal
2007, compared with 58,595 in fiscal 2006. The improved recovered grade and the increased tons
positively influenced ounces sold. Recovered grade improved to 0.158 in fiscal 2007 compared with
0.134 in fiscal 2006.
Cash costs for Joel increased to U.S.$33 million in fiscal 2007, compared with U.S.$29 million
in fiscal 2006. This increase was primarily attributed to higher production volumes and increased
labor costs to support the build-up in production. Cash costs per ounce were U.S.$418 in fiscal
2007, compared with U.S.$498 in fiscal 2006. This decrease was primarily attributable to the higher
production levels and an increased grade.
The decrease in tons milled from 504 000 in fiscal 2007 to 449 000 in fiscal 2008 is due to
the fact that the rehabilitation work on North Shaft was only completed at the end of October 2007.
Consequent teething problems at North Shaft also impacted here, for instance shaft bottom cleaning,
installation of ventilation pipes on platform, Winder motor burnout which resulted in a delay as
another motor had to be sourced from Anglogold Ashanti.
Grade was affected by long distance up dip scraping which was caused by change in hoisting
from North to South Shaft due to South Shaft rehabilitation. Higher than expected stoping widths
was encountered which affected the face grams per ton. Joel has a centralised high grade area with
the outskirts being of lower grade. Due to no flexibility and availability Joel was forced to move
to the outskirts therefore causing a lower recovery grade.
Ounces sold were 61,215 in fiscal 2008, compared to 79,923 in fiscal 2007. This was mainly due
to a combination of lower tons milled as well as a lower recovery grade.
The increase in cash costs from U.S.$33 million in fiscal 2007 to U.S.$39 million in fiscal
2008 is due to wage and salary increases granted to labor as well as an increase in the skilled
labor complement to address skills shortage on Joel. As Joel does not have its own plant, ore is
transported to a plant in Virginia which is 33 kilometers away. This is done by means of trucks.
Due to the increase in diesel, a fuel levy is charged to compensate the cartage contractor for the
fuel increases. This also resulted in increased costs.
Cash costs for Joel increased to U.S.$39 million in fiscal 2008, compared with U.S.$33 million
in fiscal 2007. This increase was primarily attributed to increased labor costs. Cash costs per
ounce were U.S.$639 in fiscal 2008, compared with U.S.$418 in fiscal 2007. The increase was
primarily attributable to the decrease in tonnage due to the re-equipping where after the shaft was
not fully operational for the first two quarters of fiscal 2008.
The rock hoisting capacity at Joel is 180,000 tons per month. The average tons milled in
fiscal 2008 was 37,420 tons per month.
On a simplistic basis, assuming no additional reserves are identified, at expected production
levels, it is foreseen that the reported proven and probable ore reserves of 4.1 million tons (0.6
million ounces) will be sufficient for Joel to maintain underground production until approximately
2017. Any future changes to the assumptions upon which the ore reserves are based, as well as any
unforeseen events affecting production levels, could have a material effect on the expected period
of future operations.
Capital Expenditure: We incurred approximately R39 million (U.S.$5.4 million) in capital
expenditures at Joel in fiscal 2008, on development on 129 level, general replacement, maintenance
and ongoing development and have budgeted R24.0 million (U.S.$3.3 million) for 129 Level
Development capital expenditures in fiscal 2009, and R15.4 million (U.S.$2.1 million) for ongoing
development.
Other Surface
Introduction: Other Surface consists of Kalgold, Phoenix and the surface operations owned by the
Freegold and Avgold companies. As the results of operations for Other Surface consists primarily
of the results from Kalgold and Phoenix, these two operations have been discussed separately.
Kalgold
Introduction: We conduct a surface mining operation at the Kalgold gold mine, 60 kilometers south
of Mafikeng in the North West Province of South Africa. Through Kalgold, we also control extensive
mineral rights on the Kraaipan Greenstone Belt in the North West Province of South Africa.
57
History: We acquired Kalgold on July 1, 1999 and fully incorporated Kalgold into our operations in
October 1999. Prior to our acquisition, the Kalgold mine had operated for more than three years.
Geology: The Kalgold operations are situated on the Kraaipan granite-greenstone belt, which is a
typical gold-bearing greenstone formation. It has undergone intense structural deformation that has
led to its dislocation into separate units.
Within the mining lease area, mineralization occurs in shallow dipping quartz veins, which
occur in clusters or swarms, within the steeply dipping magnetite-chert banded iron formation.
Disseminated sulphide mineralization, dominated mostly by pyrite, occurs around and between the
shallow dipping quartz vein swarms.
The first zone to be exploited by open cast mining has been an area known as the D-Zone. The
D-Zone orebody has a strike length of 1,300 meters. Mineralization has also been found in the
Mielie Field Zone (adjacent to the D-Zone), the A-Zone and A-Zone West (along the strike to the
north of the D-Zone), and the Watertank and Watermill areas to the north of the A-Zone.
Mining Operations: The Kalgold operations are engaged in open-pit mining. This operation is subject
to the open cast mining risks detailed in the Risk Factors section. Small subterranean water
intersections in the pit are common and are actively managed and appropriate action is taken when
necessary. The primary mining challenges at the Kalgold operations of achieving optimal volumes and
grades of ore production are addressed by stringent ore reserve management. Water shortages, due
to drought in the area, were experienced for most of fiscal 2007 and the first quarter of fiscal
2008, which had a significant impact on production. These water shortages were followed by
abnormally high rainfall and electricity disruptions, resulting in a number of days of production
lost during the 2008 fiscal year, which was further compounded by a number of plant breakdowns.
Kalgold is on the domestic electricity grid and was subject to extensive load shedding.
In fiscal 2008, the Kalgold operations accounted for approximately 5% (2% in fiscal 2007 and
3% in fiscal 2006) of our total gold sales.
Safety: The Kalgold operations had a lost time injury frequency rate of 4.97 per million hours
worked in fiscal 2008, and recorded no fatal accidents in fiscal 2008.
Plants: Ore is trucked from the pit and is directly tipped into the feed bin to the pre-primary
crusher or stockpiled. The ore then undergoes a four phase crushing process before it reaches the
Dome stockpile. Three ball mills are used to grind the ore down to between 70-80% less than 75
micron for the leaching process.
The following table sets forth processing capacity and average tons milled during fiscal 2008 for
the plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for the |
|
|
Processing |
|
Fiscal Year Ended |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
CIL |
|
|
135,000 |
|
|
|
127,552 |
|
Heap Leach(1) |
|
|
|
|
|
|
|
|
|
|
|
(1) |
|
Active use of heap leaching was discontinued in July 2001. |
In fiscal 2008, the plant at our Kalgold operations recovered approximately 86.89% of the gold
contained in the ore delivered for processing.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Kalgold |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
1,687 |
|
|
|
1,740 |
|
|
|
2,008 |
|
Recovered grade (ounces/ton) |
|
|
0.055 |
|
|
|
0.032 |
|
|
|
0.038 |
|
Gold sold (ounces) |
|
|
93,172 |
|
|
|
56,129 |
|
|
|
77,071 |
|
58
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Kalgold |
|
2008 |
|
2007 |
|
2006 |
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales ($) |
|
|
77 |
|
|
|
36 |
|
|
|
39 |
|
Cash cost ($) |
|
|
38 |
|
|
|
27 |
|
|
|
32 |
|
Cash profit ($) |
|
|
39 |
|
|
|
9 |
|
|
|
8 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
411 |
|
|
|
485 |
|
|
|
412 |
|
Capex ($) |
|
|
1 |
|
|
|
|
|
|
|
|
|
Ounces sold decreased to 56,129 in fiscal 2007, compared with 77,071 in fiscal 2006, due to a
combination of lower tons milled as well as a lower recovered grade. Tons milled decreased from
2,008,000 in fiscal 2006 to 1,740,000 in fiscal 2007. This decrease was due to lower plant
throughput as a result of water shortages encountered from March 2007. The recovered grade
decreased to 0.032 in fiscal 2007, compared with 0.038 in fiscal 2006. Mining was stopped on the A
Zone pit during the December 2006 quarter for geotechnical reasons.
Cash costs at Kalgold were U.S.$485 per ounce in fiscal 2007, compared with U.S.$412 per ounce
in fiscal 2006. This increase was due to the lower volumes produced.
Tons milled decreased from 1,740,000 in fiscal 2007 to 1,687,000 in fiscal 2008. Ounces sold
increased to 93,172 in fiscal 2008, compared with 56,129 in fiscal 2007, primarily due to the
higher grade mined from the D Zone pit. The recovered grade increased to 0.055 in fiscal 2008,
compared with 0.032 in fiscal 2007.
Cash costs increase from U.S.$27 million in fiscal 2007 to U.S.$38 million in 2008 as result
of the write off of the deferred stripping account as mining in the D-zone pit reached completion.
In spite of this, cash costs at Kalgold were U.S.$411 per ounce in fiscal 2008, compared with
U.S.$485 per ounce in fiscal 2007. The decrease was mainly due to the increase in ounces produced
as a result of higher recovered grade.
The processing capacity of the Kalgold operation is 165,000 tons per month. The average tons
milled in fiscal 2008 were 140,580 tons per month.
Active use of heap leaching was discontinued in July 2001; however, Harmony expects to put the
material on the heap leach pad through the processing mills at the end of the life of mine to
recover the residual gold.
On a simplistic basis, assuming no additional reserves are identified and at expected
production levels, it is foreseen that the reported proven and probable ore reserves of 14.3
million tons (0.40 million ounces) will be sufficient for the Kalgold operations to maintain
production until approximately fiscal 2016. However, any future changes to the assumptions upon
which the reserves are based, as well as any unforeseen events affecting production levels, could
have a material effect on the expected period of future operations.
Capital Expenditure: We incurred approximately R9.8 million (U.S.$1.3 million) in capital
expenditures at the Kalgold operations in the fiscal 2008. We have budgeted R8.8 million (U.S.$1.2
million) for capital expenditures in fiscal 2009, primarily for exploration drilling and mining of
the new orebodies.
Phoenix
Introduction: Phoenix is a tailings retreatment operation, located at Virginia and adjacent to our
current and historical mining operations in the Free State province.
History: The project commenced during fiscal 2007 and is aimed at treating the surface sources from
our operations in the Free State province.
Mining operations: Slimes tonnage reclamation steadily increased during fiscal 2008, to an average
of 550,000 tons per month by year end, which is full capacity. The focus during the year was on
improving efficiencies, recoveries and ultimately profitability.
During fiscal 2008, Phoenix accounted for 2% of our total gold sales (less than 1% in fiscal 2006
and 2007).
59
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Free State (Phoenix) |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
7,033 |
|
|
|
2,368 |
|
|
|
897 |
|
Recovered grade (ounces/ton) |
|
|
0.005 |
|
|
|
0.009 |
|
|
|
0.018 |
|
Gold sold (ounces) |
|
|
32,215 |
|
|
|
21,346 |
|
|
|
15,902 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
26 |
|
|
|
14 |
|
|
|
9 |
|
Cash cost |
|
|
12 |
|
|
|
6 |
|
|
|
6 |
|
Cash profit |
|
|
14 |
|
|
|
8 |
|
|
|
3 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
381 |
|
|
|
293 |
|
|
|
404 |
|
Capex (millions) ($) |
|
|
5 |
|
|
|
5 |
|
|
|
4 |
|
Tons treated from Phoenix were 2,368,000 in fiscal 2007, compared with 897,000 in fiscal 2006,
primarily due to Phoenix having been fully commissioned during the year and treating 500,000 tons
per month tailings material. The recovered grade decreased to 0.009 in fiscal 2007, compared with
0.018 in fiscal 2006 as a result of an increase in slimes dam reclamation. Ounces sold increased to
21,346 in fiscal 2007, compared with 15,902 in fiscal 2006, primarily due to the increase in tons
treated.
Cash costs per ounce decreased during fiscal 2007 to U.S.$293 per ounce, compared with
U.S.$404 in fiscal 2006, due to the increase in ounces produced.
Tons treated from Phoenix were 7,033,000 in fiscal 2008, compared with 2,368,000 in fiscal
2007. Ounces sold increased to 32,215 in fiscal 2008, compared with 21,346 in fiscal 2007,
primarily due to the increase in tons treated. The recovered grade decreased from 0.009 in fiscal
2007 to 0.005 in fiscal 2008. The grade of the tons treated is dependent on the time at which the
original deposition was done.
Cash costs were U.S.$12 million in fiscal 2008, compared with U.S.$6 million in fiscal 2007,
primarily due to the increase in volumes as well as the higher costs of reagents. Cash costs per
ounce increased during fiscal 2008 to U.S.$381 per ounce, compared with U.S.$293 in fiscal 2007 due
to increase in volume and increase in transport rates and the price of consumables.
Capital Expenditure: We incurred approximately R33.3 million (U.S.$4.6 million) in capital
expenditures at the Free State operations in fiscal 2008. We have budgeted R14.2 million (U.S.$2
million) for Phoenix, primarily for upgrading of major equipment at Central Plant.
Cooke operations
Introduction: The Cooke operations are located in the Gauteng Province of South Africa,
approximately thirty kilometers west of Johannesburg. These operations are owned by Randfontein.
The operations currently operate under a mining authorization with an area of 7,875 hectares.
Production is treated at the Doornkop plant.
During fiscal 2008, an agreement was entered into for the sale of the Cooke operations,
together with the associated surface assets. As a result, the assets and related liabilities have
been classified as held for sale and the results from operations have been included under
Discontinued Operations in the income statement.
Geology: These operations are situated in the West Rand Goldfield of the Witwatersrand Basin, the
structure of which is dominated by the Witpoortjie and Panvlakte Horst blocks, which are
superimposed over broad folding associated with the southeast plunging West Rand Syncline. At the
Cooke operations, two major fault trends are present. The first is parallel to the Panvlakte Fault
and strikes north to north-east, having small throws and no lateral shift. The second trend, which
runs north-west to west, has small throws, but significant lateral shift, resulting in the
payshoots becoming displaced.
There are six identified main reef groupings in the area of these operations: the Black Reef;
the Ventersdorp Contact Reef; the Elsburg Formations; the Kimberleys; the Livingstone Reefs; and
the South Reef. Within these, several economic reef horizons have been mined at depths below
surface between 600 and 1,260 meters.
60
The reefs comprise fine to coarse grained pyritic mineralization within well developed thick
quartz pebble conglomerates or narrow single pebble lags, which in certain instances are replaced
by narrow carbon seams.
Mining Operations: These operations are subject to the underground and waste rock mining risks
detailed in the Risk Factors section. Due to the shallow to moderate depths of the operations,
seismicity and pressure related problems are infrequent. There is a risk of subterranean water
and/or gas intersections in some areas of the mines. However, this risk is mitigated by active and
continuous management and monitoring, which includes the drilling of boreholes in advance of faces.
Where water and/or gas are indicated in the drilling, appropriate preventative action is taken.
The Cooke assets and related liabilities were classified as a disposal group and held for sale
during fiscal 2008.
We incurred R53.7 million (U.S.$7.4 million) in capital expenditure in fiscal 2008 at Cooke 3
Shaft for accessing the reserves in the 128 South Area to extend the life of mine reserves. The
area contains an estimated total insitu resource of approximately 4.9 million tons at 5.5 grams per
ton. It is intended to extract the UE1A reef band which is mainly a conglomerate type reef.
Production at the Cooke operations was negatively affected in fiscal 2008 by a change in the mining
mix, with less ore from the high grade VCR reef at Cooke 3 shaft and lower than expected grades
from 128 South project at Cooke 3 shaft and from the 90 North 6 area at Cooke 2 shaft. The power
shortages during the third quarter in 2008 also impacted negatively on volumes.
During fiscal 2008, the Cooke operations accounted for 12% (10% in 2006 and 2007) of our total
gold sales.
Safety: The safety record at these operations during fiscal 2008 was as follows: in terms of LTFR
of 8.98 per million hours worked achieved compared favourably with the group average of 12.83. The
FFR (0.38) at Cooke compared unfavorably with the group average of 0.18.
Safety at the operations receives constant and high-level attention and where problems are
identified steps are taken to address the situation.
Plants: The processing facilities at the operations presently comprises of the Cooke metallurgical
plant, which is serviced by a surface rail network. The Cooke metallurgical plant, commissioned in
1977, is a hybrid CIP/CIL plant, which processes the tailings from the surface sands dumps around
Randfontein.
Feasibility studies are being done for a proposed Uranium Plant of an approximate capacity of
500,000 tons per month. It is envisaged that the plant will be completed in approximately three
years when it will treat uranium ore from the Cooke dumps as well as from the Cooke 3 underground
operations.
The following table sets forth processing capacity and average tons milled during fiscal 2008
for the Cooke plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for the |
|
|
Processing |
|
Fiscal Year Ended |
Plant |
|
Capacity |
|
June 30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Cooke |
|
|
280,000 |
|
|
|
215,241 |
|
In fiscal 2008, the Cooke plant recovery has been approximately 81% of the gold contained in
the ore delivered for processing. During fiscal 2006, the Doornkop plant was upgraded and all
underground tons were moved from Cooke to Doornkop plant. Cooke plant was mothballed in January
2006; however, it was re-commissioned during fiscal 2007 to treat surface sources.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Cooke operations |
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
3,906 |
|
|
|
2,327 |
|
|
|
2,034 |
|
- Underground |
|
|
1,323 |
|
|
|
1,432 |
|
|
|
1,495 |
|
- Surface |
|
|
2,583 |
|
|
|
895 |
|
|
|
539 |
|
61
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Cooke operations |
|
2008 |
|
2007 |
|
2006 |
Recovered grade (ounces/ton) |
|
|
0.060 |
|
|
|
0.105 |
|
|
|
0.126 |
|
- Underground |
|
|
0.153 |
|
|
|
0.157 |
|
|
|
0.163 |
|
- Surface |
|
|
0.013 |
|
|
|
0.021 |
|
|
|
0.022 |
|
Gold sold (ounces) |
|
|
236,242 |
|
|
|
243,219 |
|
|
|
256,739 |
|
- Underground |
|
|
201,937 |
|
|
|
224,245 |
|
|
|
245,089 |
|
- Surface |
|
|
34,305 |
|
|
|
18,974 |
|
|
|
11,650 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
194 |
|
|
|
154 |
|
|
|
137 |
|
Cash cost |
|
|
123 |
|
|
|
118 |
|
|
|
102 |
|
Cash profit |
|
|
71 |
|
|
|
36 |
|
|
|
35 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
517 |
|
|
|
484 |
|
|
|
396 |
|
- Underground |
|
|
516 |
|
|
|
499 |
|
|
|
395 |
|
- Surface |
|
|
520 |
|
|
|
305 |
|
|
|
431 |
|
Capex (millions) ($) |
|
|
22 |
|
|
|
19 |
|
|
|
25 |
|
During fiscal 2008, the assets and related liabilities for Cooke 1, 2 and 3 as well as the
Cooke plant were classified as a disposal group and are held for sale. The results from the
operations were also classified as discontinued operations in the income statement. As a result,
the table above and the discussion below include the results of the surface operations.
Tons milled from the Cooke operations were 2,327,000 in fiscal 2007, compared with 2,034,000
in fiscal 2006, and ounces sold were 243,219 in fiscal 2007, compared with 256,739 in fiscal 2006.
The increase in tons milled was due to the recommissioning of the Cooke Plant to treat surface
sources. The decrease in ounces sold was primarily due to a decrease in the recovery grade for the
underground operations. The decrease in recovery grade at the underground operations from 0.163
ounces per ton in fiscal 2006 to 0.157 in fiscal 2007 was due to lower volumes from the high grade
VCR reef at Cooke 3 shaft and lower than expected grades from the 128 South project at Cooke 3
shaft and from the 90 North 6 area at Cooke 2 shaft.
Cash costs per ounce of gold were U.S.$484 in fiscal 2007, compared with U.S.$396 in fiscal
2006. This increase was attributable primarily to the decrease in grade from the underground
operations, as well as an increase in the amount of pillar mining from Cooke 1 at higher cost.
Pillar mining is more costly to undertake due to increased support cost and lower mining volumes.
Increases in the costs of labor and supplies and the effect of inflation on supply contracts
resulted in an increase in cash costs. Electricity increases in excess of current inflation also
negatively impacted on costs
Tons milled were 3,906,000 in fiscal 2008, compared with 2,327,000 in fiscal 2007, and ounces
sold were 236,242 in fiscal 2008, compared with 243,219 in fiscal 2007. The increase in tons milled
can mainly be attributed to the Cooke plant, used for the treating of tailings from sand surface
dumps, coming into full production during fiscal 2008. The plant is treating on average of 215,000
tons per month. This was offset by a decrease in tons milled from underground due to the stopping
of Conops, electricity constraints and a reduction in volume from Cooke 1. The decrease in ounces
sold was primarily due to lower volumes from underground as a result of the reasons mentioned
above. . The recovery grade from surface decreased from 0.021 in fiscal 2007 to 0.013 in fiscal
2008, mainly due to the replacement of higher grade waste rock with lower grade sand from Dump 20.
Cash costs per ounce of gold were U.S.$517 in fiscal 2008, compared with U.S.$484 in fiscal
2007. The increase was influenced by decreased efficiency of the machinery in the Trackless areas,
increased maintenance cost on those machines, increases in the costs of labor and supplies and the
effect of inflation on supply contracts also negatively affected cash costs.
Capital Expenditure: We incurred approximately R158.8 million (U.S.$21.9 million) in capital
expenditures at the Cooke operations in fiscal 2008 for ongoing development and other abnormal
expenditure seen as capital.
62
Also included was expenditure for accessing the reserves in the 128 South Area at Cooke 3. We have
budgeted R201.7 million (U.S.$27.8 million) in fiscal 2009, mostly for ongoing development as well
as the upgrade of all Rail Bound Equipment to comply with the legislation and improve safety.
Other Discontinued operations
Introduction: The results of operation from Other Discontinued Operations consists of results
from the Orkney operations, Mt Magnet and South Kalgoorlie. Mt Magnet and South Kalgoorlie form
part of our International operations. Refer to Western Australia below for a discussion on their
operations and results.
The discussion on Orkney follows below.
Introduction: We acquired the Orkney operations when on September 22, 2003, we merged with ARMgold
via a share exchange which resulted in ARMgold becoming our wholly-owned subsidiary. In September
2007, we announced that we had entered into formal agreements with Pamodzi for the sale of the
Orkney Shafts. The sale was finalized on February 27, 2008 and the related assets and liabilities
derecognized.
History: Exploration and development at Orkney started from 1886 and following dormant periods,
large-scale production commenced during the 1940s with the formation of Vaal Reefs Gold Mining and
Exploration Company Limited in 1944.
Geology: At the Orkney operations, the Vaal Reef is the most significant reef mined. The reef
strikes northeast, dipping southeast and is heavily faulted to form a series of graben structures.
The dip is generally less than 30 degrees but can vary locally in direction and magnitude to exceed
45 degrees. The VCR is also exploited, as well as the Elsburg Reef. There are several major faults
in the lease area, being Nooitgedacht, Buffelsdoorn, Witkop, WK2, No 3 BU, No 5 BU and No 2 BU
Fault. These faults typically have throws of tens of meters and further divide the reef into blocks
of up to 100 meters in width.
Mining operations: These operations are subject to all of the underground mining risks detailed in
the Risk Factors section. Mining depths ranged from 1,600 meters to 2,000 meters below the surface
at the Orkney operations.
During February 2008, the Orkney shafts were sold to Pamodzi. These shafts had been managed by
Pamodzi since October 2007.
For fiscal years 2008, 2007 and 2006, the Orkney operations accounted for approximately 5% of
our total gold sales.
Safety: For the eight months to February 2008, the safety record at the Orkney operations in terms
of LTFR of 19.07 million hours worked compared unfavorably with the group average of 11.55 at that
time. The FFR of nil compared favorably with the group average of 0.14.
Plants: Ore from the Orkney operations was treated at Vaal River Operations (VRO) No. 1 Gold
Plant (of Anglo Gold Ashanti). Various agreements between us and VRO governed the supply and
quality of the ore and gold apportionment.
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
Orkney operations |
|
2008(1) |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
571 |
|
|
|
947 |
|
|
|
753 |
|
Recovered grade (ounces/ton) |
|
|
0.100 |
|
|
|
0.126 |
|
|
|
0.171 |
|
Gold sold (ounces) |
|
|
57,132 |
|
|
|
119,109 |
|
|
|
128,774 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
40 |
|
|
|
77 |
|
|
|
68 |
|
Cash cost |
|
|
52 |
|
|
|
64 |
|
|
|
59 |
|
Cash (loss)/profit |
|
|
(12 |
) |
|
|
13 |
|
|
|
9 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
910 |
|
|
|
543 |
|
|
|
458 |
|
Capex (millions) ($) |
|
|
4 |
|
|
|
15 |
|
|
|
7 |
|
63
|
|
|
(1) |
|
The results are for the eight months ended February 2008. |
Tons milled from the Orkney operations were 947,000 in fiscal 2007, compared with 753,000 in
fiscal 2006. The increase is as a result of the approval of the re-opening of the Orkney 7 shaft.
The shaft started producing in the first quarter of fiscal 2007. This was offset by a decrease in
tons milled due to seismic events resulting in the loss of face length flexibility and volume at
Orkney 2.
Ounces sold were 118,984 in fiscal 2007, compared with 128,774 in fiscal 2006. The decrease in
ounces sold is primarily attributed to lower recovery grade. Recovered grade was 0.126 in fiscal
2007, compared with 0.171 in fiscal 2006. The increase is due to the reopening of Orkney 7. This
was offset by a change in mining mix at Orkney 4 as a result of seismicity experienced from the
higher grade shaft pillar to lower grade areas. There was also down scaling of production in the
shaft pillar area which resulted the mining of more remote areas.
Cash costs were U.S.$65 million in fiscal 2007 compared with U.S.$59 million in fiscal 2006.
Cash costs per ounce were U.S.$543 in fiscal 2007 compared with U.S.$458 in fiscal 2006. This
increase was attributable primarily due to increases in the costs of labor and supplies and the
effect of inflation on supply contracts.
The Orkney operations were sold to Pamodzi during fiscal 2008 and therefore the results for
fiscal 2008 are only for eight months.
Capital Expenditure: We incurred R26.3 million (U.S.$3.6 million) on capital expenditures at the
Orkney operations in fiscal 2008.
64
International Mining Operations
Western Australia Operations
We had two operational mines in Western Australia during fiscal 2008, the Mt. Magnet
operations and the South Kalgoorlie operations. These operations were acquired as part of the
purchase of two Australian gold mining companies: New Hampton, acquired in April 2001 and Hill 50
acquired in April 2002. The New Hampton transaction included two operations in Western Australia,
Big Bell in the Murchison region (which ceased operations in July 2003 and its plant sold in
November 2003) and Jubilee in the Eastern Goldfields near Kalgoorlie as well as two processing
plants associated with these operations and related exploration rights. The Hill 50 transaction
included the Mt. Magnet operations in the Murchison region, the New Celebration operations in the
Eastern Goldfields near Kalgoorlie as well as two plants associated with these operations and
related exploration rights.
Each of our Australian operations conducted surface mining (principally through open-pit
methods) and underground mining, with access through two declines at Mt. Magnet and one decline at
South Kalgoorlie. The Mt. Marion underground mine at South Kalgoorlie Mine ceased operating in June
2007. Open-pit mining at South Kalgoorlie recommenced during fiscal 2007 with the start-up of the
Shirl and Hampton Boulder Jubilee (HBJ) open-pit projects. We used mostly mechanized mining at
our Australian operations in comparison to the South African operations (excluding operations at
Target). Contractors conducted much of this mechanized mining. The contractors were responsible for
provision of the equipment and personnel needed for production of the ore under guidance of
management.
We have classified our Western Australian assets as being held for sale as of April 2007 as
they do not fit with our strategy for operating large, long-life mines. These operations also met
the criteria for discontinued operations.
In July 2007, we entered into an agreement with Dioro pursuant to which Dioro acquired our
South Kalgoorlie assets. The total purchase price was A$45 million (U.S.$39.8 million), consisting
of both a cash and share component. The share component entailed the issuance of 11.4 million Dioro
shares (valued at A$20 million (U.S.$17.7 million)), and a cash component of A$25 million
(U.S.$22.1 million). The transaction was subject to various conditions precedent, including a
minimum capital raising by Dioro of A$35 million (U.S.$30.9 million) by the completion date. On
November 30, 2007, all conditions precedent were satisfied, and the transaction was completed and
accounted for on that date. The results of production below therefore reflect only the 5 months
ended November 30, 2007.
During
fiscal 2008, we entered into an agreement with Monarch Gold for the sale of our Mount
Magnet operations. However, subsequent to year-end, we were advised
that Monarch had placed itself in voluntary administration and, on
August 1, 2008, the Administrator indicated that Monarch will not
proceed with the proposed purchase and consequently the purchase
agreement has been terminated. We have since resumed management of the St. Magnet operations which is still
classified as for sale.
As of June 30, 2008, our Western Australian operations had 2 employees (the care and
maintenance personnel on the Mt. Magnet site).
In fiscal 2008, our Australian operations accounted for approximately 5% of our total gold
sales, as compared to 10% in fiscal years 2007 and 2006.
Mt. Magnet Operations
Introduction. In 2002, we acquired Mt. Magnet as part of the Hill 50 transaction. In fiscal 2008,
Mt. Magnets operations accounted for approximately 4% of our total gold sales, as compared to 6%
in fiscal years 2007 and 2006. This change was the result of the site being placed on care and
maintenance as from December 31, 2007.
History: Mining at Mt. Magnet began after the discovery of gold in 1896. From that time to June 30,
2008, the Mt. Magnet area has produced approximately 5.8 million ounces. The current Mt. Magnet
operations commenced production in the late 1980s on the Hill 50 and Star underground mines and
nearby open-pits, and the processing of low grade ore from previously accumulated stockpiles.
Production ceased at the Star underground mine in June 2005. The Star underground mine was
subsequently replaced by St. George, a new underground mine. The Mt. Magnet site was put on care
and maintenance as from December 31, 2007 until such time that the site is sold.
65
Geology: The Mt. Magnet operations are located near the town of Mt. Magnet in the Murchison region,
560 kilometers northeast of Perth. The geology consists of folded basaltic and komatiitic
greenstones with intercalated banded iron formations and volcaniclastic units. In addition to
having been intensely folded, the area has undergone substantial faulting and later intrusion by
felsic intrusives. Mineralization within the Murchison belt consists of sulphide replacement style
(characteristic of the Hill 50 mine) and quartz lode and shear-hosted hydrothermally emplaced
bodies proximal to fault conduits. Smaller stockwork bodies within felsic intrusives are also
common. As is typical of the Archaean Shield, the deep weathering profile at Mt. Magnet has
resulted in supergene enrichment and hypogene dispersion of gold in the oxidizing environments.
These effects lend themselves well to the process of small scale open-pit mining. Historically
underground mining of primary lodes was the largest contributor to Mt. Magnets gold production.
Mining Operations:. The Mt. Magnet operations were engaged in underground, open-pit and waste rock
mining prior to site closure. These operations are subject to the underground, open-pit, and waste
rock mining risks detailed in the Risk Factors section.
Underground operations at Mt. Magnet consisted of the Hill 50 and St. George mines, each of
which operates a decline. The Hill 50 mine, which is approaching 1,525 meters in depth, was one of
Australias deepest underground mines. The St. George Mine was approximately 300 meters in depth.
Underground mining was conducted by decline tunnel access. The principal challenges confronted by
the Hill 50 underground mine related to its continuing depth and the geotechnical, ventilation and
cost impediments that increased depth imposes, including increased ground stress and potential
increased seismic activity. A decision was made in May 2007 which placed the Hill 50 mines decline
development on hold due to significant seismic activity, and effectively put the mine in harvest
mode.
With the closure of Star, the development of the new underground mine at the St. George
open-pit provided additional underground tonnage for the Mt. Magnet operations. Underground
development at St. George started in December 2005. The first stope was mined in the second quarter
of fiscal 2006. Underground mining continued at this mine during fiscal 2007. This mine reached its
economic depth limit during fiscal 2007, and was put in harvest mode, with mining operations
ceasing in October 2007. Open-pit production was hindered by the delay in the start up of the Cue
open-pits until the last quarter of fiscal 2005 as a result of delayed mining approvals and
extended contractor negotiations, although these were subsequently resolved and mining commenced in
fiscal 2006. Open-pit mining mainly took place around Mt. Magnet during fiscal years 2007 and 2008.
Surface operations at Mt. Magnet exploited several medium-sized open-pits, as well as numerous
smaller open-pits. Surface materials from areas previously involved in production, including waste
rock dumps and tailings dams, are also processed at Mt. Magnet. The principal challenge faced by
the Mt. Magnet operations involved the short mine lives which result from that the open-pits being
situated on small orebodies. The Mt. Magnet site was put on care and maintenance as from December
31, 2007 until such time that the site is sold.
Plant: The Mt. Magnet operations include one metallurgical plant which was built in 1989 as a CIL
plant and upgraded in 1999 to a CIP plant. Actual throughputs of the Mt. Magnet plant varies based
upon the blend of oxide and sulphide ores in their feed. Processing capacity is an estimate of
nominal throughput based on a 70% hard (sulphide) and 30% oxide (soft) blend.
The following table sets forth processing capacity and average tons milled during fiscal 2008
for the Mt. Magnet plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for |
|
|
|
|
|
|
the Year Ended June 30, 2008 |
Plant |
|
Processing Capacity |
|
(for 6 operational months) |
|
|
(tons/month) |
|
(tons/month) |
Mt. Magnet |
|
|
243,000 |
|
|
|
161,000 |
|
Throughput rates at Mt. Magnet decreased in fiscal 2008 due to the site being closed and the
plant being placed on care and maintenance.
In fiscal 2008, the Mt. Magnet plant recovered approximately 91.9% of the gold contained in
the ore delivered for processing.
66
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
966 |
|
|
|
1,875 |
|
|
|
1,918 |
|
Recovered grade (ounces/ton) |
|
|
0.080 |
|
|
|
0.073 |
|
|
|
0.078 |
|
Gold sold (ounces) |
|
|
77,097 |
|
|
|
136,428 |
|
|
|
148,822 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
56 |
|
|
|
86 |
|
|
|
80 |
|
Cash cost |
|
|
41 |
|
|
|
71 |
|
|
|
59 |
|
Cash profit |
|
|
15 |
|
|
|
15 |
|
|
|
21 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold ($) |
|
|
537 |
|
|
|
518 |
|
|
|
399 |
|
Capex (millions) ($) |
|
|
4 |
|
|
|
20 |
|
|
|
24 |
|
Tons milled in fiscal 2007 were 1,875,000 compared with 1,918,000 in fiscal 2006, and ounces
sold in fiscal 2007 were 136,428, compared with 148,822 in fiscal 2006, mainly as a result of
significantly less production from open-pits during the year and a seismic event at Hill 50 in May
2007, which also resulted in the reduction in the recovery grade from 0.078 ounces per ton in
fiscal 2006 to 0.073 ounces per ton in fiscal 2007. Cash costs per ounce were U.S.$518 in fiscal
2007 compared to U.S.$399 in fiscal 2006, this increase mainly the result of an increase in
underlying mining costs in Western Australia.
Recovered grade was 0.080 ounces per ton in fiscal 2008 compared to 0.073 ounces per ton in
fiscal 2007. This was due to higher grades produced from the Hill 50 underground mine. Tons milled
were 966,000 in fiscal 2008 compared to 1,785,000 in fiscal 2007. Ounces sold decreased to 77,097
in fiscal 2008, compared to 136,428 in fiscal 2007. The decrease in both tons and ounces in fiscal
2008 are a reflection of the Mt. Magnet production figures representing just 6 months of production
due to the site being placed on care and maintenance.
Cash costs per ounce were U.S.$537 for fiscal 2008, compared to U.S.$518 for fiscal 2007. This
increase was due to higher underground and open-pit contracting cost due to the underlying mining
cost increases in the Western Australian and a wider Australian mining market environment.
The majority of declared ore reserves were mined during fiscal 2008. The mines were closed
and the processing plant has been put on care and maintenance until such time that the site is
sold.
Capital Expenditure: We spent U.S.$4.3 million in capital expenditure at the Mt. Magnet operations
in fiscal 2008, primarily for underground development and plant components. We have not budgeted
for capital expenditure for fiscal 2009, as we will only undertake critical maintenance in
anticipation of the Mt. Magnet site being sold.
Exploration: Activities at Mt. Magnet, Western Australia, were performed to the minimum level
required to keep the tenements in good standing as the site and plant is currently on care and
maintenance. We expended A$2.9 million (U.S.$2.7 million) on exploration during fiscal 2008.
South Kalgoorlie Operations
Introduction: The South Kalgoorlie Operations are made up of New Hamptons Jubilee Operations and
Hill 50s New Celebration operations. Since the commencement of operations to November 30, 2007,
total gold production from the mines in the South Kalgoorlie area has exceeded 2.5 million ounces.
In fiscal 2008, South Kalgoorlie operations accounted for 1% of Harmonys total gold sales, and
accounted for 4% of our total gold sales in 2007 and 3% in fiscal 2006.
In July 2007, we announced the sale of the South Kalgoorlie Mine to Dioro. The total purchase
price was A$45 million (U.S.$39.8 million), which consists of a cash component and a shares
component. On November 30, 2007, all conditions precedent to the transaction were satisfied. The
results for fiscal 2008 below reflect only the 5 months ended November 30, 2007.
History: The South Kalgoorlie operations included several open-pits at Jubilee and New Celebration,
as well at the Mt. Marion underground
67
mine. The Jubilee operations were originally comprised of the
large Jubilee open-pit and a number of smaller open-pits. The New Celebration operations were initially developed in
1987 by Newmont exploiting the same ore body that hosted the Jubilee Pit. Hill 50 acquired these
operations from Newcrest Mining Ltd. in June 2001. The Mt. Marion decline was established in 1998.
Open-pit mining ceased at the South Kalgoorlie Operations at the end of fiscal 2005, with only low
grade stockpiles treated during fiscal 2006 together with Mt. Marion ore. During fiscal years 2008
and 2007, open-pit mining recommenced at South Kalgoorlie Mines, with a cutback on the HBJ pit, as
well as the Shirl open-pit.
Geology: The South Kalgoorlie mines were located approximately 30 kilometers south of Kalgoorlie in
the Eastern Goldfields region of Western Australia. The South Kalgoorlie orebodies were located in
a number of geological domains including the Kalgoorlie-Kambalda belt, the Boulder-Lefroy
Structure, the Zuleika Shear, the Coolgardie Belt and Yilgarn-Roe Structures. At South Kalgoorlie,
the mining tenure and geology straddled the three major fault systems or crystal sutures considered
to be the main ore body plumbing systems of the Kalgoorlie Goldfield. The geology consisted of
Archaean greenstone stratigraphy of basalts and komatiites with intercalated sediments, tuffs,
volcaniclastics and later felsic intrusives. Late stage and large scale granitic (Proterozoic)
intrusion stoped out large sections of the greenstone. Quartz filled lode and shear-hosted bodies
are the most dominant among many mineralization styles. Large scale stockwork bodies hosted in
felsic volcanics were an important contributor to bulk tonnage of relatively low grade deposits.
Mining Operations: The South Kalgoorlie operations are engaged in open-pit, underground and waste
rock mining. These operations are subject to the underground, open pit and waste rock mining risks
detailed in the Risk Factors section.
At the South Kalgoorlie operations during fiscal 2008, open cast mining took place at Shirl
open-pit, together with a cutback project on the HBJ open-pit. The HBJ open-pit will have a mine
life of three years and consist of 3.3 million tons of 0.048 ounces per ton. The Shirl and HBJ
open-pit feedstock as well as low grade stockpiles were processed during the year. The discovery of
the Shirl prospect during fiscal 2006, which resulted in an open-pit reserve of 50,000 ounces and a
15 month mine life, together with an improved gold price environment, lead to the recommencement of
open-pit mining at South Kalgoorlie mines during fiscal years 2008 and 2007. The primary challenge
that faced the South Kalgoorlie operations involved identifying adequate sources of new open-pit
and underground reserves and managing the geotechnical risk on the HBJ pit cutback. See Risk
Factors Risks Relating to Our Business and Our Industry To maintain gold production beyond
the expected lives of Harmonys existing mines or to increase production materially above projected
levels, Harmony will need to access additional reserves through development or discovery.
Plant:. The South Kalgoorlie operation had a metallurgical plant located at Jubilee. This CIL
treatment plant was capable of treating the planned production from the mining operations. Ore was
hauled from the open-pits and from low grade Shirl stockpiles to the treatment plant by
conventional road trains. Actual throughputs of the Jubilee plant varied based upon the blend of
oxide and sulphide ores in their feed. Processing capacity was an estimate of nominal throughput
based on a 70% hard (sulphide) and 30% soft (oxide) blend.
The New Celebration plant was sold during fiscal 2006 for A$3.0 million. This plant was
originally commissioned in 1986 as a CIP plant and later upgraded in 1988 by the addition of a
larger parallel circuit.
The following table sets forth processing capacity and average tons milled during fiscal 2008,
prior to the completion of the sale of the South Kalgoorlie plant:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Milled for |
|
|
|
|
|
|
the Year Ended June |
Plant |
|
Processing Capacity |
|
30, 2008 |
|
|
(tons/month) |
|
(tons/month) |
Jubilee |
|
|
122,000 |
|
|
|
95,400 |
|
Throughput rates in fiscal 2008 were lower than capacity due to tank refurbishments at the
Jubilee plant.
In fiscal 2008, the Jubilee plant recovered approximately 82.4% of the gold contained in the
ore delivered for processing compared to 89% in 2007.
68
Production analysis:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended June 30, |
|
|
2008(1) |
|
2007 |
|
2006 |
Production |
|
|
|
|
|
|
|
|
|
|
|
|
Tons (000) |
|
|
477 |
|
|
|
1,391 |
|
|
|
1,480 |
|
Recovered grade (ounces/ton) |
|
|
0.058 |
|
|
|
0.064 |
|
|
|
0.056 |
|
Gold sold (ounces) |
|
|
27,778 |
|
|
|
88,371 |
|
|
|
82,639 |
|
Results of operations (millions) ($) |
|
|
|
|
|
|
|
|
|
|
|
|
Product sales |
|
|
19 |
|
|
|
56 |
|
|
|
42 |
|
Cash cost |
|
|
14 |
|
|
|
45 |
|
|
|
38 |
|
Cash profit |
|
|
5 |
|
|
|
11 |
|
|
|
4 |
|
Cash costs |
|
|
|
|
|
|
|
|
|
|
|
|
Per ounce of gold($) |
|
|
517 |
|
|
|
504 |
|
|
|
454 |
|
Capex (millions)($) |
|
|
12 |
|
|
|
7 |
|
|
|
4 |
|
|
|
|
(1) |
|
The results are for the five months ended November 2007. |
Tons milled in fiscal 2007 were 1,391,000, compared to 1,480,000 in fiscal 2006, while ounces
recovered in fiscal 2007 were 88,371 as compared to 82,639 in fiscal 2006. This increase in ounces
compared with the decrease in milled tons in fiscal 2007 were primarily attributable to the
increases in the recovery grade from 0.056 ounces per ton from fiscal 2006 to 0.064 ounces per ton
in fiscal 2007. The increase in the recovery grade resulted from the mining of predominantly
higher-grade underground ore. The decrease in throughput in fiscal 2007 from 2006 was due largely
to tank refurbishments at the Jubilee plane.
Cash costs per ounce were U.S.$504 for fiscal 2007, compared to U.S.$454 for fiscal 2006. This
increase was due to higher underground and open-pit contracting costs due to the continuing
increase in the underlying Western Australian mining environment and higher gold production levels.
Tons milled in fiscal 2008 were 477,000 compared with 1,391,000 in fiscal 2007, and ounces
sold in fiscal 2008 were 27,778 compared with 88,371 in fiscal 2007. This decrease in ounces, and
increase in tons, was primarily attributable to the sale of the South Kalgoorlie operations to
Dioro on November 30, 2007.
Cash costs per ounce were U.S.$517 for fiscal 2008, compared to U.S.$504 for fiscal 2007.
This increase was due to the higher underground and open-pit contracting costs due to the
underlying market increase in the Australian mining environment and lower gold production levels.
Recovered grade was 0.058 ounces per ton in fiscal 2008, compared to 0.064 ounces per ton in fiscal
2007. This decrease in ounces and tons was primarily attributable to a number of factors, namely
the open pit throughout for the year being replaced by low grade stockpiles (which also caused the
reduction in grade) and the sale of the operations to Dioro.
Capital Expenditure: In fiscal 2008, we spent U.S.$12 million in capital expenditures at South
Kalgoorlie, primarily for the Shirl open-pit and plant refurbishments. Due to the sale of the South
Kalgoorlie operations, we have not budgeted for capital expenditures for fiscal 2009.
Exploration: Exploration activities were scaled back in the first half of fiscal 2008 in
anticipation of the sale of the South Kalgoorlie operations, with A$1 million expended.
PNG Operations
Overview
Introduction: As at the end of fiscal 2008, our lease holding in PNG is located southwest of Lae
in the Morobe Province and encompasses over 3,480 square kilometers of tenure. The tenements are
outlined in the figure below and fall into three main blocks centered in the Morobe province. These
include the Wafi leases (440 square kilometers), the Morobe Hidden Valley leases (971 square
kilometers) and the Morobe Coast EL (2,069 square kilometers).
Harmony PNG tenement locations. In terms of regional geological setting, the tenements cover a
portion of the PNG mobile belt. The mobile belt comprises tract of metamorphosed Lower Jurassic and
Cretaceous sediments and oceanic crust. These rocks have undergone deformation
69
in the collision
zone between the Australian and Pacific Plates and multiple intrusive events including Tertiary granodiorite and younger
mineralized porphyries. The PNG mobile belt hosts a number of major gold and copper-gold deposits
including the Wafi-Golpu and Hidden Valley Projects which are 100% owned by us.
Exploration expenditure outlook for fiscal 2009 is currently estimated at A$19.6 million. Results
from this work have been highly encouraging, as a number of targets with the potential for major
stand-alone gold and copper/gold deposits have been identified and advanced to the drill testing
phase.
We currently have offices in Lae, Wau and at the Hidden Valley site, to facilitate the
development of the Hidden Valley project and support both the exploration efforts in the region and
the pre-feasibility work on the Wafi Golpu copper gold project. In 2006 a technical support office
was opened in Brisbane to support the construction phase of the Hidden Valley project as well as
the evaluation of the Wafi and Golpu prospects.
We completed stand alone PFS in Golpu during the June 2007 quarter and in Wafi during the
December 2007 quarter, which included the Wafi gold resources and examined the development of three
production scenarios:
|
|
|
Golpu stand alone (an update of the Golpu PFS scenario); |
|
|
|
|
Golpu + Link Zone; and |
|
|
|
|
Golpu + Link Zone + NRG1; |
The PFS reports were subject to Gate Reviews and a CPR. Neither the Gate Reviews nor the CPR
identified any fatal flaws in the PFS reports. However, a number of outstanding issues were
identified. The returns projected by the studies did not meet our requirements, and it was decided
then not to immediately proceed to the feasibility stage. Further studies are planned for fiscal
2009 to address outstanding issues and to investigate alternative production scenarios which may
improve projected returns.
Hidden Valley Project
Introduction: The Hidden Valley project entails the construction of a significant gold and silver
mine. This mine will process 4.6Mt of ore a year from the two open-pits. The Hamata orebody is one
small pit and the Hidden Valley and Kaveroi orebodies are in a much larger open-pit. The mine is
located in a highly prospective exploration lease area and it is envisaged that, as active
exploration continues, the life of the process facility may be extended as it is fed from a number
of sources. We own the Hidden Valley Project through our wholly-owned PNG subsidiary, Morobe
Consolidated Goldfields Ltd. Subsequent to the year ended 2008, our interest in the Hidden Valley
project and other PNG assets and tenements were reduced to 69.99% due to Newcrest Mining Limited
(Newcrest) acquiring interests in the PNG assets. See Recent Developments.
The project comprises four exploration licenses of 966 square kilometers in the Wau District
of Morobe Province, PNG and is located 210 kilometers north-northwest of Port Moresby and 90
kilometers south-southwest of Lae, the two largest cities in PNG. Access to the project is
presently by sealed road from the deepwater port of Lae to Bulolo. We have constructed an
all-weather gravel road from Bulolo to the Hidden Valley mine site to access the site.
History: Alluvial gold was first discovered at Hidden Valley in 1928 but it was not until the early
1980s that the area was investigated by CRA Exploration using modern exploration techniques that
resulted in the discovery of the Hidden Valley and Kaveroi gold deposits on EL 677. A number of
feasibility studies have been prepared for the Hidden Valley Project by the various owners,
including one by Abelle in 2003. We have extensively reviewed and updated the Abelle feasibility
study during fiscal 2006 in order to: (a) reflect changes in the projects ore body interpretation;
(b) incorporate increases in capital and operating costs as a result of energy prices and scarce
resources in the mining industry as well; and (c) resolve technical aspects that were outstanding
from the previous study. The updated feasibility study was presented to the Board during June 2006
and they approved construction of the project. In late 2007, we began a search for a partner to
partake in all of our PNG mining and exploration activities. Following a selection process, we
selected Newcrest to buy into our PNG activities and to form a joint venture with us. Newcrests
holdings in the PNG assets and tenements is expected to increase to 50% up to a maximum of U.S.$306
million by the middle of calendar year 2009.
Site Access. The Hidden Valley site is located approximately 90 kilometers south-southwest of
Lae, which is the nearest deepwater port for the project, and the Capital of Morobe Province.
Access to the site from Lae uses an existing 110 kilometers sealed two-lane main road to the town
of Bulolo, continuing to Hidden Valley via an all-weather two-lane access road constructed by us.
Work commenced on the construction of the Hidden Valley access road to the site from Bulolo town in
October 2005. The road reached the mining lease boundary in May 2006 and the in-filled road network
has been extended to the Hidden Valley deposit, Pihema Creek and the Hamata plant site. Pihema
Creek has been
70
diverted
and platforms have been established for most of the project infrastructure, such as the permanent camp and the administration building. Work has commenced on
the Tailings Storage Facility and the Hamata plant site. We contracted a road construction manager
and a core of operators with extensive PNG road-building experience to undertake this part of the
project, utilizing equipment we bought for construction purposes.
Engineering Procurement and Construction Management Contract. Following Board approval, a
small owners team of experienced construction professionals was recruited, including several key
individuals with extensive PNG experience, to ensure that project objectives, scope of work and all
other project requirements are met. In July 2006 an agreement was reached with the engineering
group Ausenco Limited to provide engineering procurement and construction management services for
the project. Ausenco started immediately with the preparation of a project execution plan as well
as the detailed design stage of the project which is set for completion at the end of December
2007. At the end of fiscal 2008, the detailed design was approximately 90% complete and 100 out of
110 planned procurement/contract packages have been put out to enquiry. To date, 100 packages have
been awarded.
Power supply. The ability to obtain an alternate power supply from PNGs national power
supplier, PNG Power Limited (PPL), is of critical importance to the economics of the project. On
May 14, 2007, we announced that we had signed an agreement with PPL to supply the Hidden Valley
mine with electricity. PPL has committed to construct new transmission lines and infrastructure in
order to supply hydro-electricity from the Yonki Dam. Contracts for this work have already been
awarded, and supply is expected to commence by the middle of calendar 2010.
In addition, we acquired diesel generators and will install them for the purpose of providing
100% backup power supply to the project, if required, and will be powering the site until
hydro-electricity is supplied.
Customs and Excise. In November 2006 the PNG National Executive Committee approved exemptions
to customs and excise on a range of commodities that will be required for the construction of the
project. This was gazetted, and customs officials at Lae port are already applying the exemptions,
based on the draft gazettal notice.
Mining Fleet. The mining equipment required for the project consists of: four 180t excavators,
a fleet of nine 175t haul trucks and a range of ancillary equipment. Supply and maintenance
agreements for this fleet were signed in September 2006. The delivery of the first batch of mining
equipment for pre-stripping took place in the second quarter of fiscal 2007 and the delivery of the
remainder of the fleet was taken during fiscal 2008.
Geology: The proven and probable gold reserves for the Hidden Valley/Kaveroi/Hamata deposits are
2.02 million ounces at 0.062 ounces per ton. Silver proven and probable reserves at Hidden
Valley/Kaveroi and Hamata amount to 30.71 million ounces at 1.093 ounces per ton. Extensive
drilling is currently being undertaken at the Kaveroi prospect adjacent to the Hidden Valley ore
body, with the intention to add additional reserves to the project.
Environment. The Environment Management Plan, which is a requirement of the mining lease, has
been approved by the PNG Department of Environment. The key environmental issue for the project is
the effective management of water quality in the Bulolo and Watut rivers. A range of control
measures will be implemented for acid rock drainage, sediment runoff and tailings facility
discharge water quality. Work continues on baseline studies and monitoring programs required for
both the construction and operational phases of the project. Re-engineered surface designs have led
to the tailings storage facility capacity being increased to 46.3 million tons and the waste dumps
design now complying with acid rock drainage and other environmental commitments.
Community affairs/landowner discussions. Community support and development of the mine in
compliance with the memorandum of agreement with landowner groups is critical to the success of the
project. Meetings are held regularly with these groups and officials from the provincial and
national government to monitor progress and ensure these objectives are met. A range of
opportunities for the commercial participation of landowner groups in the development of the
project are being considered as a priority, and community relations initiatives focused on positive
outcomes for health, education and infrastructure are ongoing.
Project Overview: Once fully developed, the Hidden Valley Mine is expected to process 4.6 million
tons of ore per annum from ore mined at two open-pits, the Hamata ore body in one small pit and the
Hidden Valley and Kaveroi orebodies in a much larger pit. Expected annual production will be
250,000 ounces of gold per annum, with a peak production of 275,000 ounces, and 4 million ounces of
silver. Expected mine life is 14 years. The construction period is estimated to be 30 months, with
the mine expected to be commissioned by March 2009.
The resources will be mined in a sequence that sees the low silver, high gold Hamata ore mined
first, with plant and infrastructure
71
development for the project developed in close proximity to
the Hamata deposit. The next ore mined will be the Hidden Valley/Kaveroi oxide/transition ores (high silver) followed by
the Hidden Valley/Kaveroi primary ores.
Plant: As part of the project a treatment plant was brought from Misima Mines Limited and
transported to Lae in April 2005. Parts of the plant that will be utilized in the project have been
identified and refurbished in fiscal 2007 with the remainder to be disposed of. The plant is stored
in Lae and its components will be transported to Hidden Valley for installation as the project
proceeds.
Once completed, the processing plant is expected to process ore at a rate of approximately 4.6
million tons per annum and has been designed with three distinct process routes that complement the
metallurgical characteristics of the three ore types to be mined. The processing plant will
commence as a primary crushing, grinding (with the incorporation of a gravity gold recovery
circuit), CIL, Merrill-Crowe zinc precipitation, goldroom and tailings detox plant for the low
silver Hamata ores, revert to a primary and secondary crushing, grinding, flotation, concentrate
regrind, counter-current decantation circuit with Merrill-Crowe zinc precipitation, flotation
concentrate and tailing CIL, goldroom and tailings detox for the high silver oxide/transition ores
and then a similar circuit without flotation tail CIL for high silver sulphide ores from Hidden
valley/Kaveroi ores. The gravity gold recovered will be processed through an intensive cyanide
leach followed by electrowinning circuit to produce a high quality ore product.
Ore will be delivered by truck to the Hamata and Hidden Valley crusher stations. Crushed
Hamata ore will be delivered by conventional conveyor to the primary stockpile and Hidden Valley
ore will be delivered via an overland pipe conveyor to the same stockpile.
All tailings will be stored in a tailings storage facility, and all water recovered will be
subject to detoxification prior to being re-cycled or released to the environment. The processing
plant and tailings storage facility will be built to meet or exceed the requirement of the
International Cyanide Management Code. Construction completion is planned for the second quarter of
fiscal 2009 with initial gold production anticipated by middle of calendar 2009.
Government royalty and other rights. The gold and silver production from the Hidden Valley
Project will be subject to a 2% royalty, payable on the net return from refined production if
refined in PNG or 2% royalty on the realized price if refined out of PNG.
The government of PNG also has a statutory right to acquire up to a 30% participatory interest
in mining development projects, at sunk cost. However the memorandum of agreement signed between
the government and ourselves reduced the participation right to 5%, should the government wish to
exercise it. Once an interest is acquired by the government of PNG, it contributes to the further
exploration and development costs on a pro rata basis.
Third Party Royalties. On March 28, 2007, we announced that we had concluded negotiations with
Rio Tinto pursuant to which we would purchase the Rio Tinto rights under a royalty agreement
relating to Hidden Valley, which was entered into prior to our acquisition of the Hidden Valley and
Kerimenge deposits in PNG. Under the royalty agreement, Rio Tinto had the right to receive a
portion of between 2% and 3.5% of future ounces produced by the Hidden Valley mine in PNG. The
consideration we paid to Rio Tinto totaled U.S.$22.5 million, which was settled with our issue of
ordinary shares valuing U.S.$20 million, with the balance of U.S.$2.5 million paid in cash.
The transaction will reduce the cash costs per ounce of gold produced at Hidden Valley, and
all further extensions to the project, mine life and reserves will be free of this royalty.
Capital Expenditure: Capital expenditure on the project for fiscal 2008 was U.S.$162 million (A$181
million) compared to the U.S.$71 million (A$90 million) spent in fiscal 2007. Capital was mainly
spent on completing earthworks within the mining lease, particularly the process plant platform,
construction of the Hamata permanent camp and related infrastructure. Other areas of significant
expenditure were for process equipment and management related costs.
The total project capital cost is estimated to be U.S.$579 million (A$605 million), which
represents a 27% increase in A$ terms on the last reported budget. Increases in costs were
primarily caused by market forces resulting from the high demand created by resource development
projects in the region. There were no significant changes in the scope of work of the project.
This value excludes U.S.$37 million for mine fleet repayments post the construction phase as well
as U.S.$22.5 million for the Rio Tinto royalty buy-out which is not considered part of the
construction capital.
72
Morobe Consolidated Goldfields Limited (MCG) Tenements
The MCG tenements comprises some 2,157 square kilometers of tenure and include the Hidden
Valley Mining lease (ML151), four granted Exploration licenses (EL497, EL677, EL1193 and EL1403)
and three Exploration Licenses (EL1629, EL1630 and EL1631). The tenement boundaries are outlined
below in figure 1.
The tenements are under-explored and remain highly prospective for large-scale porphyry Cu-Au
deposits, low-grade bulk mineable epithermal Au-Ag deposits (similar to Hidden Valley) and for
high-grade epithermal Au satellite resources. Focus of the exploration program on the Morobe
Consolidated tenements is three-fold:
|
|
|
Major new stand alone discoveries; |
|
|
|
|
High-grade drivers to improve cash flows of the Hidden Valley Project; and |
|
|
|
|
Additional reserves to substantially increase mine life of the Hidden Valley Project. |
Exploration programs undertaken during fiscal 2008 included those on the Hidden Valley Mining
Lease, the area surrounding the Kerimenge Prospect, and on the Morobe Coast EL1403. However, in
addition to these areas, project generation continued, such as the capturing of historical data and
grassroots exploration activities (which include mapping, stream sediment sampling and integration
of results with regional magnetic data).
Hidden Valley ML
Introduction: Minimal drilling occurs outside of the deposit areas at Hidden Valley. Project
generation work which comprised ridge and spur soil sampling (2,824 samples), mapping (over 25 line
kilometers) and sampling new road cuttings (7,675 samples) were completed during fiscal 2008. Work
integrating the geological and geochemical datasets together with detailed helimagnetics is in
progress, and will provide a new solid geology interpretation to identify additional targets on the
Hidden Valley Mining Lease.
Project Status: Continuous channel sampling on new trenches has resulted in some major intercepts
of high grade gold mineralization at the Upper Bulolo prospect, located approximately 1 km east of
the Hidden Valley open-pit. Trenching work designed to scope out the extent of surface
mineralization continues and, due to high grades, first pass drilling at this prospect will be a
priority in fiscal 2009.
Kerimenge and the broader prospect potential
Introduction: The Kerimenge deposit lies approximately 7 kilometers east of the proposed Hamata
Processing Plant site. Work completed during fiscal 2008 was focused on trenching and
reconnaissance away from the deposit area to outline mineralization controls. Some 2,036 samples
were collected and assayed from over 4 line kilometers of hand-dug trenches.
Project Status: Results from the trenching work have identified 2 drill targets for follow-up work
in fiscal 2009. If successful, this drilling should also increase understanding of the main
mineralization controls of this highly prospective project. Compilation work has also highlighted
the Kauri Prospect (located approximately 1 kilometer north of the Kerimenge deposit) as having
potential for a major stand-alone Au deposit similar to that of Hidden Valley. Certain follow-ups
in this area are planned for the third quarter of fiscal 2009.
73
Figure 1: Tenement Location Map
Morobe Coast Exploration License
Introduction: The Morobe Coast exploration license, EL1403, encompasses some 1,041 square
kilometers of tenure. A compulsory 50% reduction was completed in April 2008. The area lies to the
southeast of the Morobe Goldfield, and we believe it presents grassroots exploration potential.
Historical exploration work has been limited, but returned anomalous gold assays in rock chip and
stream sediment samples from the Lokaniu volcanics.
Giu Prospect. The Giu prospect falls approximately 10 kilometers southwest of the Morobe township
on the east coast of PNG, and has been the main focus of exploration activities on EL1403. The
prospect represents a district scale anomaly, 20 kilometers in diameter with elevated gold rock
chip and stream sediment geochemistry. The aim of the work programs is to identify and develop
prospect areas with the potential for stand-alone-gold (+/- related metal) orebodies.
Mapping to date has outlined several areas of structurally controlled epithermal vein
mineralization, hosted in vesicular basalts. Rock chip results have been encouraging with anomalous
values of copper, gold, molybdenum and zinc returned.
Project Status: Some 400 stream sediment and rock chip samples were collected during fiscal 2008,
and several highly anomalous drainages have been identified. Field work in the form of ridge and
spur soil sampling is scheduled for fiscal 2009 in order to trace the anomaly to its bedrock
source. Airborne magnetics are also planned for fiscal 2009 to provide additional base data for
integration with surface geochemical results and assist with drill targeting.
Wafi Golpu Project Area
Introduction: The Wafi prospect is owned through Wafi Mining Limited, our wholly-owned subsidiary.
The first exploration at Wafi dates back to the nationwide porphyry copper search by CRA
Exploration Ltd in the late 1960s. Elders Resources farmed-in to the project from 1989-1991, and
AGF subsequently farmed-in to the project for a short period in 1997 prior to going into
administration in 1998. Aurora subsequently acquired the project from Rio Tinto (CRA) in 1999, with
ownership passing to Abelle when it merged with Aurora in 2002. We assumed control of the Wafi
Project by way of its acquisition of Abelle in 2003.
74
The project is held under 4 contiguous exploration licenses (EL 440, EL 1316, EL 1103 and EL 1105),
totaling 440.6 square kilometers. A further 688.7 square kilometers of tenure has been applied for
in 2 separate exploration license applications, namely ELA 590 and ELA 1612. Tenements are outlined
above in figure 1. The Wafi Golpu Project comprises 2 separate ore systems located within close
proximity of each other known as the Wafi Gold Project and the Golpu Copper/Gold Project,
respectively. The Wafi gold mineralization is hosted by sedimentary/volcanoclastic rocks of the
Owen Stanley Formation which surrounds the intrusive Wafi Diatreme. Gold mineralization occurs in
the form of extensive high-sulphidation epithermal alteration overprinting porphyry mineralization
and epithermal style vein-hosted and replacement gold mineralization with associated wall-rock
alteration. Exploration expenditure (including Pre-feasibility studies) on the project for fiscal
2008 was U.S.$13.2 million (K38 million).
Geography: The Wafi prospect is located near Mt. Watut in the Morobe Province of PNG, approximately
60 kilometers southwest of Lae and about 60 kilometers northwest of Wau. The Wafi camp is located
at an elevation of approximately 400 meters above sea level in terrain that is mountainous and
forested in most areas. The site is accessed by sealed road (Lae to Bulolo) which comes within 5
kilometers of the eastern edge of the tenements and 15 kilometers from the Wafi camp. From the
sealed road, a 38 kilometer dirt-base access track to the prospect is accessible during dry weather
conditions. The site is serviced by helicopter when the road access is cut due to wet weather.
Watut Valley is located immediately west of the project, and the foothills of Watut Valley are
planned to be utilized for placement of ore processing and mine infrastructure.
Mining Reserves. Following completion of the Golpu Copper/Gold pre-feasibility study, a probable
ore reserve has been declared. See Item 4. Reserves.
The Golpu Ore Reserve is derived from the Golpu Stand Alone Project Pre Feasibility Study.
This study assumes a block cave underground mine with ore processed on site to produced a copper
and gold concentrate for shipping to smelter. Metallurgical Studies indicate that recoveries of 88%
for copper, 54% for gold and 36% for molybdenum can be expected. Metal prices are assumed at
U.S.$2.30/lb for copper, U.S.$520/oz gold and U.S.$20/lb for molybdenum.
In declaring the probable reserve, the following considerations are required:
|
1. |
|
The PFS is completed to industry accepted standards for a PFS (±20-25% accuracy). The outcome of
further more detailed studies may affect the reserve. |
|
|
2. |
|
The location for the tailings storage facility has not been finalized, however two potential sites
proximal to the project have been defined. |
|
|
3. |
|
There are outstanding issues associated with traditional land owners required to be resolved before
the project is able to be constructed. |
|
|
4. |
|
The Board has not yet committed to completing subsequent phases of study, or to project construction. |
A reserve for the Wafi gold ore bodies has not been declared.
Government Royalty and Other Rights. The metal production from the Wafi Project is subject to a 2%
royalty payable on the net return from refined production if refined in PNG or a 2% royalty payable
on the realized price if refined outside of PNG. The government royalty has been accounted for in
project financial models. PNG also has a statutory right to acquire up to a 30% participatory
interest in mining development projects at sunk cost. Once an interest is acquired by the
government of PNG, it contributes to the further exploration and development costs on a pro rata
basis.
Third Party Royalties. Pursuant to the sale agreement of Wafi Mining Ltd to Abelle (via wholly
owned subsidiary companies) from Rio Tinto, a royalty of 2% on gold production or a 2% NSR (net
smelter return) from copper-gold concentrates is payable to Rio Tinto as a deferred acquisition
cost. The royalty has been accounted for in project financial models.
Capital Expenditures: No capital expenditures were incurred during fiscal 2008 as the
pre-feasibility study was still underway, and costs were expensed as a result.
Pre-Feasibility Studies: Two pre-feasibility studies for the Wafi Golpu project have been
completed in the past year:
The Golpu stand alone Pre-Feasibility Study (Golpu PFS), dated July 2007, which
examined solely the development of Golpu copper gold resources;
The Wafi Pre-Feasibility Study (Wafi PFS), dated October 2007, which included
the Wafi gold resources and examined the development of the following three
product scenarios:
75
|
|
|
Golpu stand alone (an update of the Golpu PFS scenario); |
|
|
|
|
Golpu + Link Zone; and |
|
|
|
|
Golpu + Link Zone + NRG1; |
The PFS reports were subject to Gate Reviews and a Competent Persons Report. Neither the Gate
Reviews nor the CPR identified any fatal flaws in the PFS reports but a number of outstanding
issues were identified. The returns projected by the studies did not meet our requirements and it
was decided not to immediately move to Feasibility stage. Further studies are planned for the
fiscal 2009 to address outstanding issues and investigate alternative production scenarios which
may improve projected returns.
Wafi Gold Projects
Introduction: The Wafi Gold resource is comprised of three main zones: Zone A, Zone B and the Link
Zone (high grade lenses within Zone B). In addition to the Wafi resource, the Western Zone is an
advanced exploration project.
Geology: The pre-feasibility study we undertook focused on extraction of the high grade Link Zone
material, and on delineation of shallower oxidized mineralization, amenable to high gold recovery
under standard cyanide leach conditions (associated with Zones A and B). Additional exploration
activities have focused on the discovery of additional Link Zone style mineralization (such as the
Western Zone) which may have the potential to improve Wafi gold project economics.
Metallurgical test work for the Link Zone has focused on comminution test work and whole ore
pressure oxidation that has demonstrated the technical viability of the processing method, with
gold recoveries of approximately 95% achieved. The Wafi PFS showed the Link Zone not to be an
economic scenario based on estimated costs and the assumed gold price.
Metallurgical test work for the Non-Refractory gold ore (NRG1) focused on the establishment
of cyanide recoveries in both the transitional and fully oxidized ores across the known
mineralization. Test work has shown that the 95% recovery of gold in completely oxidized ores was
consistently achieved. Recovery in the transitional material remains variable with indications
that recoveries averaging 84% to 86% are able to be achieved. The Wafi PFS showed the NRG1 resource
not to be an economic scenario based on estimated costs and the assumed gold price.
Project Status: Geotechnical, mining, infrastructure, and environmental investigations were
undertaken as part of the Link Zone and NRG1 study, in parallel with the Golpu studies. Synergies
between the Wafi Gold projects and the Golpu Copper project were utilized during the studies to
minimize cost as far as possible. Despite these synergies the gold resources were not determined to
be economic. Further work to expand gold resources and examine development alternatives are planned
for the coming year.
Golpu Copper-Gold Project
Introduction: The Golpu Copper-Gold Project, or Golpu Project, is located approximately one
kilometer northeast of the Wafi gold orebodies.
Geology: The Golpu host lithology is a typical zoned porphyry copper alteration halo, grading from
potassic to phyllic to advanced argillic upwards in the core. Outwards from the core, the
alteration grades from the above to argillic potassic, to propylitic. The mineralized body is a
porphyry copper-gold pipe with approximately 200 meters by 200 meters plan dimensions, slightly
north plunging and still displaying strong mineralization at grades similar to those in the rest of
the potassic alteration zone at 1.2 kilometers depth (the maximum depth to which it has been
drilled). Recent drilling and reinterpretation have shown that copper and gold mineralization
extend some way into the metasediment host rock immediately adjacent to the porphyry body. The
mineralized metasediment has potential to add up to 75% to the volume of the porphyry stock if
additional exploration defines the mineralization as part of the resource.
The surface expression is oxidized and leached to about 150 meters vertical depth, resulting
in a residual gold only mineralization from which the copper has been leached. At the oxidation
interface, a strong 20- to 30 meters thick zone of supergene copper enrichment is developed which
transitions at depth into a lower grade covellite-enargite ore. Beneath this is a zone of more
covellite rich mineralization that contains lesser enargite and consequently less arsenic. From
approximately 300 meters below surface, the ore exists in a covellite-rich (arsenic-poor) form
grading into a chalcopyrite-bornite rich zone from approximately 500 meters to its current
known depth of approximately 1.2 kilometers. We completed the pre-feasibility study for Golpu
during the last quarter of fiscal 2007. The PFS identified a reserve of 78.5Mt at
76
1.1% Cu, 0.6g/t
gold and 121 ppm Molybdenum. There is potential to significantly increase the mining inventory if
additional mineralized metasediment material is able to be included in the resource estimate
following further exploration activities.
The metasediment domain comprises mineralization peripheral to the porphyry stock that is
hosted in the metasediments. Mineralization in this zone is distributed irregularly around the
porphyry stock with the majority occurring on the western side of the porphyry. Mineralization
occurs in all three alteration types: advanced argillic, phyllic and potassic. Further work during
subsequent phases of study will be planned with a view to converting the mineralized metasediment
to an indicated resource, and subsequently a probable reserve.
Project Status: The Golpu PFS was undertaken as a standalone scenario and also in parallel with the
Link Zone and NRG1 resources (Wafi PFS). The pre-feasibility studies indicate that an annual
production rate of 10 million tons is achievable, utilizing the block cave mining method. Ore is
planned to be mined from the block cave, and conveyed via an underground decline to a processing
plant located in the Eastern foothills of the Watut River Valley, some 4 kilometers west of the
deposit. Concentrate produced will be either pumped or truck-hauled to the port of Lae for
dispatch to smelting markets. Production of copper metal on site has not been considered during
the current phase of study. The cost of power at the site is presently high, with on site heavy
fuel oil generation. It is not expected that on-site metal production will be viable unless power
cost can be substantially reduced.
Additional Prospects and Exploration Potential: The Golpu and Wafi pre-feasibility studies focused
on developing the Golpu copper-gold, the high-grade gold link zone mineralization and the
non-refractory (oxide) portion of the A and B zone gold mineralization. However, excellent
prospects remain in the immediate vicinity of the existing resource areas for porphyry Cu-Au and
related epithermal Au mineralization. During fiscal 2008, the focus of the exploration program was
within a 2 km radius of the Wafi Golpu deposits, and the Nambonga North Prospect has been
identified where drilling has obtained a number of significant porphyry Cu-Au intercepts. At
Western Zone, drilling has intersected high-grade Au mineralization similar to that of the Link
Zone.
Nambonga North
Introduction: Nambonga North prospect lies approximately 2 km northwest of the Golpu deposit off
the northwest margin of the diatreme. Initial exploration drilling tested a magnetic target with a
coincident Cu-Mo geochemical anomaly at surface, and an Electromagnetic anomaly at depth outlined
potential for a major zone of Au-Cu stock work mineralization associated with a separate porphyry
intrusive. The drilling also intersected massive sulphide mineralization containing zinc lead and
silver. Drilling during fiscal 2008 totaled 13 holes for 5,827m.
Project Status: Systematic step-out drilling at the prospect remains in progress on sections spaced
80m apart. This program will continue into the first half of fiscal 2009 to outline the limits of
mineralization.
Western Zone
Introduction: Western Zone is located approximately 1.8 km west of the Golpu deposit and lies
approximately 400m north of the Link zone off the western margin of the diatreme. Drilling during
fiscal 2008 comprised 3 holes for 1,484m. Several intervals of high grade gold mineralization have
been intersected, and like the Link Zone mineralization are associated with arsenical pyrite.
Project Status: Additional drill testing are planned in fiscal 2009 to test the down dip
continuity of the mineralization.
Wafi Regional Exploration
Introduction: Porphyry copper-gold and stand-alone gold targets represent the best potential to
crystallize value from the Wafi tenement group. Reprocessing of regional magnetics has outlined 7
discrete magnetic targets within a 14 km radius of the Wafi Golpu project. These all have the
potential to deliver major gold or copper-gold systems in areas where there has been little or no
previous exploration.
Project Status: Fiscal 2008 exploration focused on the Biamena Prospect. Planned for fiscal 2009
is first-pass exploration by way of soil and stream sediment sampling, mapping and reconnaissance
rock chip sampling, and first pass reconnaissance drilling is planned for the remaining 6 targets
(Mt. Tonn, Kendix, Bawaga, Zenapu, Mid Nambonga Yor Creek, Kesiago).
Biamena
Introduction: Biamena prospect lies approximately 12 km south of the Golpu deposit on EL1316. The
prospect area was prioritized for follow-up work based on highly anomalous Cu-Au stream sediment
geochemistry coincident with an intrusive unit evident in the magnetics.
77
Project Status: Work during fiscal 2008 has included surface trenching and soil sampling (1500
Samples), IP survey (80 line kilometers), and first pass drilling (2 holes 749m). Gold and copper
results obtained from this work have been encouraging. Follow-up diamond drilling will be planned
and scheduled based on integrated geochemical, geological and geophysical datasets during fiscal
2009.
78
REGULATION
Mineral Rights
South Africa
South African law provides for the separate ownership of surface and mineral rights. Prior to
the promulgation of the MPRDA on May 1, 2004, it was therefore possible for one person to own the
surface of a property, another to own rights to precious metals, and yet another to own rights to
base minerals. In terms of the MPRDA, all mineral rights in South Africa are now vested in the
South African state. The principal objectives of the Act are:
|
|
|
to recognize the internationally accepted right of the state of South Africa to exercise full and
permanent sovereignty over all the mineral and petroleum resources within South Africa; |
|
|
|
|
to give effect to the principle of South Africas custodianship of its mineral and petroleum resources; |
|
|
|
|
to promote equitable access to South Africas mineral and petroleum resources to all the people of
South Africa; |
|
|
|
|
to substantially and meaningfully expand opportunities for HDSAs including women, to enter the mineral
and petroleum industry and to benefit from the exploitation of South Africas mineral and petroleum
resources; |
|
|
|
|
to promote economic growth and mineral and petroleum resources development in South Africa; |
|
|
|
|
to promote employment and advance the social and economic welfare of all South Africans; |
|
|
|
|
to provide security of tenure in respect of prospecting, exploration, mining and production operations; |
|
|
|
|
to give effect to Section 24 of the South African Constitution by ensuring that South Africas mineral
and petroleum resources are developed in an orderly and ecologically sustainable manner while
promoting justifiable social and economic development; and |
|
|
|
|
to ensure that holders of mining and production rights contribute towards socio-economic development
of the areas in which they are operating. |
Under the MPRDA, tenure over established mining operations is secured for up to 30 years (and
renewable for periods not exceeding 30 years each thereafter), provided that mining companies apply
for new order mining rights over existing operations within five years of May 1, 2004, or before
the existing right expires, whichever is the earlier date and fulfill requirements specified in the
MPRDA and the Mining Charter.
The Mining Charter was signed by government and stakeholders in October 2002 and contains
principles relating to the transfer, over a ten-year period, of 26% of South Africas mining assets
(as equity or attributable units of production) to HDSAs, as defined in the Mining Charter. An
interim target of 15% HDSA participation over 5 years has also been set and to this end, the South
African mining industry has committed to securing financing to fund participation of HDSAs in an
amount of R100.0 billion within the first five years of the Mining Charters tenure. The Mining
Charter provides for the review of the participation process after five years to determine what
further steps, if any, are needed to achieve the 26% target participation. In order to measure
progress in meeting the requirements of the Mining Charter, companies are required to complete a
Scorecard, in which the levels of compliance with the Mining Charter can be ticked-off after five
and ten years respectively. The Mining Charter and Scorecard require programs for black economic
empowerment and the promotion of value-added production, such as jewelry-making and other gold
fabrication, in South Africa. In particular, targets are set out for broad-based black economic
empowerment in the areas of human resource and skills development; employment equity; procurement
beneficiation and direct ownership. In addition, the Mining Charter addresses socio-economic issues
such as migrant labor, mine community and rural development, and housing and living conditions.
We actively carry out mining and exploration activities in all of our material mineral rights
areas. Accordingly, the MPRDA has not had a significant impact on these mining and exploration
activities because we are eligible to apply for new licenses over our existing operations, provided
that we continue to comply with the Mining Charter. All of our new order licenses have been
granted.
We have already complied with the requirements of the Mining Charter, with an equivalent of
34% of production ounces qualifying as empowerment credit ounces. We have been working on our
program of licensing since 2004, which involved the compilation of a mineral assets register and
the identification of all of our economic, mineral and mining rights. We have secured all old
mining rights and validated existing mining authorizations. Our strategy has been to secure all
strategic mining rights on a region-by-region basis. The first application for conversion from old
order to new order mining rights was for the Evander Operations and was lodged on May 21, 2004.
The Evander
79
mining license was the first conversion application in the region and
in October 2004 we became the first senior company to convert old order to new order mining
rights for our Evander and Randfontein operations. We have worked closely with the DME to help
ensure, to the extent we are able, that the licenses are granted as swiftly as possible. The
conversion of licenses for all our remaining operations were granted during November 2007 and
Doornkop will be executed in October 2008.
The MPRDA makes reference to royalties being payable to the South African government in terms
of the Mineral and Petroleum Resources Royalty Bill which has not yet been enacted by Parliament.
The fourth draft of the Mineral and Petroleum Resources Royalty Bill was tabled in Parliament on
August 21, 2008 and provides for the payment of a royalty according to a formula based on earnings
before interest, tax and depreciation. This rate is then applied to revenue to calculate the
royalty amount due, with a minimum of 0.5% and a maximum of 5% for gold. It is estimated that the
formula could translate to a royalty rate of more than 2% of gross sales in terms of current
pricing assumptions. The latest proposal results in a large increase from the 1.5% rate proposed in
the second draft in 2006. Should the bill be passed by Parliament in its current form, the royalty
will become effective on May 1, 2009.
The MPRDA intends to, among other things:
|
|
|
give effect to the Ministers stated intention to promote investment in the South
African mining industry; |
|
|
|
|
establish objective criteria for compliance with the MPRDAs socio- economic objectives; |
|
|
|
|
remove the technical deficiencies of the MPRDA; |
|
|
|
|
align the MPRDA with the Promotion of Administrative Justice Act, 2000; and |
|
|
|
|
coordinate the environmental requirements between the MPRDA and the National
Environmental Management Act. |
PNG
The Mining Act of 1992 (PNG) is based on Australian legislation. Accordingly, mineral rights
in PNG also belong to the government of PNG and they have a statutory right to obtain up to a 30%
participating interest in mining development projects. The government then issues and administers
mining tenements under the relevant mining legislation, and mining companies must pay royalties to
the government based on production.
The key difference in PNG is that citizens have the right to carry out non-mechanized mining
of alluvial minerals on land owned by them. These customary rights do not extend over a mining
lease, unless an alluvial mining lease is obtained.
Almost all land in PNG is owned by a person or group of persons, and is not generally overlaid
by landowner title issues. There is, however, considerable difficulty in identifying landowners of
a particular area of land because land ownership may arise from both contract and inheritance, and
because of the absence of a formal written registration system.
Prior to commencing exploration, compensation for loss or damage must be agreed with the
landowners. Prior to commencing mining, a written agreement must be entered into with landowners
dealing with compensation and other matters.
In PNG, Morobe Consolidated Goldfields Limited (Morobe") holds a mining lease and various
exploration licenses granted by the Department of Mining for the Hidden Valley Project. Morobe has
also entered into a memorandum of agreement with the state, local government and the landowners.
Wafi Mining Limited holds various exploration licenses granted by the Department of Mining for
the Wafi/Golpu Project, and has entered into a compensation agreement with landowners on one of its
exploration licenses.
In PNG there are no applicable exchange control restrictions but the PNG central bank does
have to be informed of all transactions and has to approve lending facilities and interests rates
charged.
Environmental Matters
South Africa
We are committed to conducting our business in an ethically, morally socially and
environmentally responsible manner that will protect human health, natural resources and the
environment in which we live. We aim to balance our economic, social and environmental goals and
responsibilities to achieve sustainable, profitable growth in our business and, more importantly,
to work with communities and regulatory agencies to implement sound management practices which will
ensure that our mining is conducted in an environmentally-safe manner. In addition, with regard to
legacy mining impacts, we remain committed to identifying and implementing coordinated remediation
plans that are acceptable to all relevant parties.
80
In support of the above commitment, our environmental policy stipulates that:
|
|
|
Compliance |
|
|
|
|
We will integrate environmental policies, programs and practices into
all activities and policies of the organization as well as monitor the
performance of these programs. We will strive to comply with all
applicable municipal, provincial and national laws and regulations, as
well as the other requirements to which we subscribe that are relevant
to the environmental aspects of our activities, and encourage such
compliance from those organizations with whom we do business; |
|
|
|
|
Continual Improvement
We will evaluate and continually improve the effectiveness of our
environmental management system through periodic audits, management
reviews, and by achieving our environmental objectives. We will review
this Environmental Policy annually and make it available to the
public; |
|
|
|
|
Pollution Prevention
We will actively design, operate, and maintain our mining activities
with a focus on pollution prevention. We will strive towards the
continual reduction of adverse environmental effects, supporting the
principle of sustainable development; |
|
|
|
|
Awareness
We will communicate this Environmental Policy to employees,
contractors and suppliers to ensure their awareness of our commitment
to the environment. We will provide appropriate training to all
employees to ensure their continuing awareness of environmental
responsibilities. |
In order to address and minimize the impact of our operations on the environment and take
cognizance of the regulatory requirements, the following 5-year targets have been approved by the
Board:
|
|
|
|
|
|
|
|
|
|
|
Scope of |
|
|
|
|
|
Measurement |
|
Comparable |
|
|
Regulation |
|
Aspect |
|
Element |
|
Criteria |
|
Standard (GRI) |
|
Target |
APPA/AQA
|
|
Air Emissions
|
|
Electricity
|
|
kWh/ton
treated/mined
|
|
x
|
|
15% reduction |
|
|
|
|
Fuels
(Diesel/Petrol)
|
|
Litres/CO2
equivalents
|
|
√ |
|
15% reduction |
|
|
|
|
Dust
|
|
g/m2/day
|
|
x
|
|
15% reduction |
|
|
|
|
Methane
|
|
CO2 equivalents
|
|
√ |
|
30% reduction |
|
|
|
|
Coal (domestic)
|
|
t/year
|
|
√ |
|
50% reduction |
NWA
|
|
Water
|
|
Consumptive Use
|
|
m3/ton
treated/mined
|
|
x
|
|
10% reduction |
|
|
|
|
Metal/Salt
Discharge: |
|
|
|
|
|
|
|
|
|
|
- surface
|
|
tons
|
|
x
|
|
70% reduction |
|
|
|
|
- underground
|
|
tons
|
|
x
|
|
20% reduction |
MPRDA and NNRA
|
|
Land - recycle
|
|
steel
|
|
tons
|
|
√ |
|
All waste will be
handled through
designated areas. |
|
|
|
|
plastic
|
|
tons
|
|
x |
|
|
|
|
|
timber
|
|
tons |
|
√ |
|
|
|
|
|
Oil/grease
|
|
litres
|
|
√ |
|
50% recycled |
|
|
Land - use
|
|
impacted
|
|
ha
|
|
√ |
|
10% reduction |
Our approach to environmental management encompasses the following four broad principles:
|
|
|
all relevant environmental risks should be identified and prioritized; |
|
|
|
|
environmental issues should be dealt with promptly; |
|
|
|
|
environmental issues, particularly relating to continuous
non-compliance or potentially serious environmental impacts, should be
notified and dealt with at the board level; and |
81
|
|
|
we will adopt the best practicable environmental option; that is, the
option that has most benefit, or causes the least damage to the
environment, at a cost acceptable to society and affordable to us. |
We developed our environmental policy in consultation with various stakeholders such as mine
managers, employees and unions, and which has the approval of the Chairman of the Sustainable
Development Committee and the Chief Executive. It has also been adopted by each mine manager at
signing ceremonies held at each shaft. It commits shafts to returning their areas of operation as
close as possible to the pre-mining state, thus creating sustainability and economic viability for
generations to come.
The main areas of the policy are:
|
|
|
that environmental management is a corporate priority; |
|
|
|
|
that environmental policies, programs and practices will be integrated into our activities; |
|
|
|
|
that we will strive for continued improvement and efficiency; |
|
|
|
|
that we will work with government departments and the public to come up with the best
sustainable solutions; |
|
|
|
|
that contractors and suppliers will be required to comply with our policy; and |
|
|
|
|
that employees will be informed and educated regarding their environmental responsibilities. |
The focus was on implementing an environmental management policy at an operational level
during fiscal 2007. During fiscal 2008, we continued the adoption of the ISO 14001 specification as
the Environmental Management System (EMS) for the South African operations. The EMS is a
structured approach for addressing the triple bottom-line (that is, social, economic and
environmental), and forms the basis of environmental management at an operation level. ISO 14001
is a recognized and widely adopted EMS framework.
The ISO4001 EMS is being introduced progressively throughout our South African operations.
The planned program completion for this region is 2012. As at September 30, 2008, the
implementation status is as follows:
|
|
|
Operation:
|
|
Implementation Status: |
Doornkop
|
|
85%
(with the Stage 1 external audit scheduled by end of November
2008) |
Target
|
|
65% |
Elandsrand
|
|
65% |
Phakisa
|
|
55% |
Environmental policy and strategy within our business, as well as the environmental impact of
our operations on regional communities, are overseen by the Sustainable Development Committee. The
management of environmental issues at operational level is the responsibility of each divisional
Chief Operational Officer, who is supported by line management in the various regions. Structure
and reporting mechanisms are in place to ensure that the Board is kept fully informed, on a
quarterly basis, of environmental matters within the group as well as progress made towards
achieving targets set for key parameters.
The Environmental Management Function (EMF) has been structured to support operational
goals. Primarily, this means it will ensure reasonably practicable compliance with legislation, and
the promotion of environmental awareness. At a regional level, environmental management managers
provide advice and support to the relevant operational management teams. Given the diversity of the
environmental issues being dealt with, one of the environmental challenges facing the operations is
to effectively access the diverse range of skills necessary to address environmental issues.
Concurrent rehabilitation and mitigation capacity resides within the various operational functions,
such as surface engineering, metallurgy, etc. Where specific capacity is lacking in-house, use is
made of external consultants with appropriate specialist expertise. Operational personnel are
assisted by the EMF to determine the scope of work and consultants are selected and employed as the
need arises. Their selection is conducted in terms of our procurement policy. Regional
environmental managers meet on a quarterly basis as part of a process to encourage networking,
information sharing and joint problem-solving. Staff members are encouraged to develop their skills
through on-the-job training and external opportunities such as conferences and short courses.
Current complements provide for further strengthening of the skills base of the EMF in line with
our commitments. We support future staffing in the environmental area by mentoring two graduates
(in the discipline) to fill future roles within our business. The process of rehabilitation has
been given a boost with the appointment of a group level
82
Environmental Manager specifically
charged with accelerating the rehabilitation of specific target areas with a view to obtain
concurrent closure instead of the approach of viewing final mine closure at the end of life of
mine.
With this new appointment, we have initiated a process of identification and planning around
environmentally sensitive sites in both the north and south regions to be rehabilitated in line
with the requirements of the MPRDA and other relevant legislation. These areas have been
identified for rehabilitation as part of our progressive rehabilitation and closure planning
program, a predecessor program to the final mine closure plan (for the entire mine) for activities
which must be carried out after production of minerals from the mine or when mining has ceased.
Rehabilitation and closure plans are being developed internally for targeted areas where an
urgent need for rehabilitation and formal closure has been identified. External expertise will be
utilized should the need arise. Obtaining approval from the relevant authorities (notably DME,
Department of Water Affairs and Forestry (DWAF) and, in some cases, National Nuclear Regulator
(NNR)) for the rehabilitation and closure plans is essential.
The rehabilitation programs are aimed at making the area suitable for future land development
with a goal of achieving positive socio-economic spin-offs.
Land use objectives are established in consultation with relevant government departments,
local authorities, landowners and all relevant Interested and Affected Parties (IAP). IAP
consultation forms part of the planning and development process as it is a prerequisite to closure
plan approval. Obtaining the authorities approval (notably DME, DWAF and in some cases the NNR)
on the rehabilitation and closure plans is of the essence. The rehabilitation programme is aimed
at making the area suitable for future land development with positive socio- economic spin- offs to
be realised therefrom. Land use objectives are established in consultation with relevant government
departments, local authorities, landowners and all relevant interested and affected parties. IAP
consultation forms part of the planning and development process which is a prerequisite to closure
plan approval.
Our environmental management strategy, which has been updated and given the full support of
our Board and CEO, is guided by the environmental policy by prevailing environmental laws and the
EMPRs developed by us for each operation and approved by the DME which are legally binding. We are
not aware of any litigation, current or pending, against us in this regard.
During the fiscal 2005, we were issued with directives from DWAF related to the collection,
removal and re-use or disposal of extraneous groundwater in the Klerksdorp, Orkney, Stilfontein and
Hartebeestfontein (KOSH) area. This follows the liquidation of the DRDGOLD North West operations
in this area and the subsequent liquidation of Stilfontein, which brought an end to their pumping
activities and threatened to flood other mines in the area. In February 2007, Harmony, AngloGold
Ashanti and Simmer Jack Mines Limited entered into an agreement pursuant to which Margaret Water
Company (MWC) was formed to manage the water emanating from the now defunct Stilfontein Gold
Mine. MWC and the three mining companies entered into a loan agreement for the provision of a loan
of R18.0 million (U.S.$2.56 million) from each mining company to MWC as seed funding for
stabilization of the infrastructure.
The Western Basin Environmental Corporation (WBEC) is in the process of funding the
necessary infrastructure improvements to ensure the sustainability of the pumping operations. It
continues to be managed by directors appointed by each of the relevant mining houses. The Western
Utilities Corporation (WUC) established in order to fund the treatment of the water on a
sustainable basis has secured sufficient offshore funding from offshore investor. WUC has entered
into a management agreement with WBEC and has built and successfully operated three pilot plants
over the last 8 months. The results of these trials are being analyzed and the full viability
report will be available by the end of calendar 2008.
The KOSH obligations have passed to Pamodzi with the sale of the Orkney operations to that
company.
We are expecting a revised DWAF directive pertaining to the water management of the Western
Mining Void water decant during October 2008, which is expected to cover operating conditions
leading up to final solution following the pilot work. Currently, we are in compliance with the
regulators requirements within the operating constraints of the water treatment plan. We are also
in regular contact with DWAF in this regard, and are actively minimizing our water discharge
quantity by re-use in our metallurgical facilities.
EMS forms the basis for the implementation of the environmental policy and monitoring
compliance. All of the South African operations function within the requirements and conditions of
the EMPRs that have been approved by the DME. These EMPRs contain specific as well as generic
principles relating to environmental management during the operation of the mine. Closure
objectives are set and closure plans
83
formulated within the
EMPR. The latter includes investigation of the potential for re-use of existing infrastructure,
preparation of a rehabilitation plan, rehabilitation and vegetation of the affected area and
post-closure monitoring. Conversion to new order mining rights in line with the MPRDA requires that
mining companies report on the extent of compliance with their approved EMPRs. The EMPRs identify
individual impacts, mitigation measures and rehabilitation requirements. These have been used as
the basis for the development of a proprietary EMS, which is currently being tested, populated with
information, and rolled out to the various operations. This proprietary EMS, which encompasses the
principles of ISO 14000, is an electronic-based system. The proprietary EMS encompasses the
following activities:
|
|
|
Environmental inspection: general inspections are performed routinely and systematically with
collected data entered into the system to enable follow-up actions. |
|
|
|
|
Risk assessment: detailed and specific risk assessments are conduced to help identify
deviations that may not have been otherwise anticipated. |
|
|
|
|
Stakeholder communication: all communication is managed and may result in action items for
the organization for which the stakeholder will require follow-up feedback. All such
communication is logged. |
|
|
|
|
Monitoring: impact monitoring is focused on collecting and analyzing environmental data that
may well result in follow-up actions. |
|
|
|
|
Licenses/permits: all details relating to licenses or permits can be registered in the system. |
|
|
|
|
Major loss, incident and accident notification: when an incident occurs, initial information
about the incident is recorded to trigger a notification process. |
The bulk of our significant impacts are historic, and are currently managed in terms of
site-specific procedures or codes of practice. Any major operational changes will, in future, take
cognizance of the Environmental Impact Assessment (EIA) process and adhere to the outcomes of
such studies. Furthermore, the continued development of EMSs, with respect to site monitoring and
risk assessment, will allow for the inclusion of specific evaluation criteria in the
decision-making process. We have conducted internal compliance assessments on all of our EMPRs.
Assessments and non-compliance areas are being addressed. The results of the compliance assessment
have been included in the application for conversion to new order mining rights.
In accordance with legislation, we have established seven independent environmental
rehabilitation trust funds to make adequate financial provision for the expected cost of
environmental rehabilitation at mine closure and for the discharge of our obligations and
contingency liability. Each operation estimates its expected environmental closure liability
annually and this estimated amount is used to calculate the contributions to be made to the
rehabilitation trust funds. The contributions are spread over the operational life-of-mine and
contributions are made by each operation on an annual basis. The accumulated amount in the various
South African rehabilitation trust funds as at June 30, 2008 was U.S.$205.5 million, while the
total rehabilitation liability was U.S.$173.6 million in current monetary terms.
The assets of each mine within each fund are ring-fenced and may not be used to
cross-subsidize one another. Contributions to the various funds will continue to be made over the
operations life-of-mine and each fund is expected to be fully-funded at the time of closure.
Sudden and accidental pollution is covered under our public liability insurance policy. The Asset
Management Committee formed during fiscal 2006 continues to co-ordinate the activities related to
the disposal of assets and subsequent closure of redundant operational sites to an environmentally
acceptable standard. The EMF is represented on the committee at senior management level. An
important element of this committees work is to investigate alternative and appropriate land use,
particularly in respect of those assets for which closure is being planned.
Pursuant to South African law, mine properties must be rehabilitated upon closure. Mining
companies are required by law to submit EMPRs, to the DME. EMPRs identify the rehabilitation issues
for a mine and must also be approved by other South African government departments including, but
not restricted to the DWAF.
EMPRs have been prepared and submitted for all of our South African operations. All of our
South African mining operations have permanent mining authorizations as required in terms of the
previous Minerals Act 1991. We have already obtained all new order mining rights. We meet with and
intend to continue to meet on a regular basis with the relevant government departments to continue
the information sharing process that we have with them and to ensure the environmental impact of
our mining operations are managed in accordance with applicable regulatory requirements and
industry standards.
84
All water uses are now in the process of being licensed, and we have submitted water-use
registrations required by the National Water Act of 1998. We have also developed water management
plans for all of our South African operations. This process is now extended to a full review and submission of Water Use
License applications, which will take into account all water-related issues as well as planned
projects.
In addition, an environmental surveillance system has been implemented at slimes dams at our
operations to monitor dust generation and fall-out in residential and other areas. This will assist
in future dust suppression and the design and measurement of rehabilitation programs. In excess of
R5 million (U.S.$0.7 million) has been spent in contouring the tops of the slimes dams concerned
and to provide wind erosion containment measures and the supply of sewage discharge water to
initiate vegetation growth in the coming season has been completed. In addition, spraying of the
leading edges of the dams and dumps with eco-friendly palliatives to bind the soils in the short
term is ongoing, although the palliatives have had limited success in binding the dust particles,
further tests are ongoing.
Australia
Our Western Australian Mt. Magnet operations are subject to applicable environmental
legislation, and also specific site conditions attaching to the mining tenements imposed by the
Department of Industry and Resources, to the operating licenses issued by the Department of
Environmental Protection, and also to the water abstraction licenses issued by the Water and Rivers
Commission.
As a result, we must make provision for environmental rehabilitation whenever mining
operations are conducted. While we believe that our current provision for compliance with such
requirements is reasonable, any future changes and development in Australian environmental laws and
regulations may adversely affect these Australian operations. The total Australian rehabilitation
liability was A$20.3 million (U.S.$19.4 million) at the end of fiscal 2008.
In Western Australia, rehabilitation obligations under the Mining Act are covered by
environmental securities issued by us, or by performance bonds issued by our bankers and
cash-backed by us. These bonds cannot be relinquished or cancelled without the approval of the
Department of Industry and Resources. The amount of the bond is established prior to issuance of
the tenement and commencement of operations, and generally is audited by the regional inspector.
Thereafter, the amount is reviewed on an annual basis following our issuance of an annual
environmental report. As areas are successfully rehabilitated, the bond requirement is reduced.
Audits are generally conducted on a bi-annual basis by the Australian Department of
Environmental Protection to determine compliance with the relevant operating license(s). There are
currently no outstanding material non-compliance issues against our licenses.
At each of our mines, we appointed a person dedicated to environmental matters who, in
addition to organizing the implementation of the environmental management programs, monitors the
impact of mining on the environment and responds to impacts that require specific attention outside
of the normal program of environmental activities.
The primary environmental focus at most of our operations is water management and the
administration of areas outside the operating plants and shafts. The major objective is to ensure
that water is of a quality fit for use by downstream users.
Based on current environmental and regulatory requirements, we accrue for the estimated
rehabilitation expense in full when mining commences and then amortizes these environmental
rehabilitation costs over the operating life of a mine.
PNG
Our PNG operations are in exploration, pre-feasibility study and project construction phases,
and mining has not yet commenced. We are subject to applicable environmental legislation including
specific site conditions attaching to the mining tenements imposed by the PNG Government Department
of Environment and Conservation (DEC), to the terms and conditions of operating licenses issued
by the Department of Mines and DEC, and also to the environment permit for water abstraction and
discharge issued by DEC.
The current status of our PNG projects can be summarized as follows:
The Hidden Valley project is in the construction phase. The project has obtained and is in
compliance with all permits and licenses required for the current stage of the projects
development. The access road to the Hidden Valley project site has been completed with part of the
road sides successfully re-vegetated. The foundations have been completed for accommodation and
administration buildings for the general mine
85
infrastructure. Excavation is underway for the plant
site, tailings storage facility and the access road to the open-pit. Government approval has been given to amend the environment permit based on an updated
feasibility study for the site.
The Wafi Golpu project is presently undertaking pre-feasibility studies. The project has
obtained, and is in compliance with, all permits and licenses for the current stage of the
projects development.
Harmony PNG is committed to working within the framework of corporate EMS in accordance with
the international EMS standard, ISO 14001:2004, adapted for use in Australia and New Zealand as
AS/NZS ISO 14001:2004 and the Equator Principles of the World Bank. These standards provide Harmony
PNG with the elements of an effective EMS, that is, a procedure for implementing, achieving,
reviewing and maintaining our environmental policy, and also incorporates good industry
environmental management practices, which form the basis of a project-specific EMS.
An EMS is a structured approach to managing an environmental program, and provides a quality
system to guide:
|
|
|
development and implementation of environmental management procedures; |
|
|
|
|
monitoring of environmental impacts and performance; and |
|
|
|
|
review of procedures to ensure continual improvement. |
86
Health and Safety Matters
South Africa
The Mine Health and Safety Act
For many years, the safety of persons working in South African mines and quarries was
controlled by the Mines and Works Act of 1956 and then by the Minerals Act of 1991 which was
replaced by the Mine Health and Safety Act. The Minerals Act of 1991 has subsequently been repealed
and the MPRDA promulgated. The findings of the Leon Commission of Inquiry into Health and Safety in
the Mining Industry (held in April 1994) culminated in the Mine Health and Safety Act, which was a
product of intensive discussion and debate between government, employers and employee
representatives over an extended period of time. The objectives of the Mine Health and Safety Act
are:
|
|
|
to protect the health and safety of employees and other persons at mines; |
|
|
|
|
to promote a culture of health and safety; |
|
|
|
|
to require employers and employees to identify hazards and eliminate, control
and minimize the risks relating to health and safety at mines; |
|
|
|
|
to give effect to the public international law obligations of South Africa that
concern health and safety at mines; |
|
|
|
|
to provide for employee participation in matters of health and safety through
health and safety representatives and health and safety committees at mines; |
|
|
|
|
to provide for the effective monitoring of health and safety conditions at mines; |
|
|
|
|
to provide for the enforcement of health and safety measures at mines; and |
|
|
|
|
to foster and promote co-operation and consultation on health and safety between
the Department of Minerals and Energy, employers, employees and their
representatives. |
The Mine Health and Safety Act prescribes general and specific duties for employers and
others, determines penalties and a system of administrative fines, and provides for employee
participation by requiring the appointment of health and safety representatives and the
establishment of health and safety committees. It also entrenches the right of employees to refuse
to work in dangerous conditions. Finally, it describes the powers and functions of the mine health
and safety inspectorate and the process of enforcement.
Government, through the Department of Minerals and Energy, ordered the institution of audit
teams to conduct legal compliance and systems and explosives control audits on mines across all
commodities.
It is anticipated that mining companies will incur additional expenditure in order to comply
with the prescribed legislative requirements. Management anticipates that such additional
expenditure will not have a material adverse effect upon our operational results or financial
condition.
HIV
& AIDS Policy
We are actively pursuing holistic HIV & AIDS awareness campaigns with our South African
workforce and are also providing medical assistance and anti-retroviral treatment. Employees who
decide to leave their place of work and return home for care are cared for at their homes through
the TEBA home based care system, to which we contribute. See Risk Factors Risks Relating to Our
Business and Our Industry HIV & AIDS poses risks to Harmony in terms of productivity and costs
and Risk Factors Risks Relating to Our Business and Our Industry The cost of occupational
healthcare services may increase in the future.
In South Africa, we have an agreement with the relevant stakeholders concerning the management
of HIV & AIDS in the workplace. This agreement, originally signed in 2002 with the National Union of
Mine Workers (NUM) and the United Association of South Africa (UASA) was amended for the third
time in August 2006. While many aspects of the policy have remained unaltered, the most fundamental
change is the inclusion in the policy of a broad spectrum of chronic manageable diseases other than
HIV & AIDS such as diabetes, asthma and hypertension. This was done in order to minimize the stigma
surrounding stand alone HIV & AIDS treatment centers and also to emphasize our view that HIV & AIDS
should no longer be viewed as a death sentence, but rather a chronic, manageable disease. The
agreement also serves to reassure our employees of our commitment to the respect of all human
rights. During the early stages of the implementation of the HIV & AIDS program, the agreement was
also used as a marketing tool to encourage employee participation in the Harmony HIV & AIDS Program.
Our HIV & AIDS Program, fully supported at all levels of management, is overseen by a qualified
medical practitioner together with the assistance of qualified consultants and experts. In
September 2005, an independent consultant, the Health Monitor Group, undertook a second
87
business
impact assessment for the group. Based on actuarial information, the
assessment revealed that the prevalence rates of HIV & AIDS within our
business have stabilized at around 30%. This result was in line with the first or baseline
assessment that was done in 2003. The introduction of Highly Active Anti-Retroviral Therapy has
also helped to manage the treatment of HIV & AIDS infected employees. The effectiveness of these
measures will only be determined over time. We are currently negotiating an agreement on the
Traditional Health Practitioners with the NUM and we have a contracted a dually qualified Western
Doctor/Traditional Health Practitioner who attends to patients once weekly at the clinic in
Randfontein and also advises us in view of the pending National Traditional Health Practitioners
Bill. A third HIV & AIDS impact assessment will be completed by the end of December 2008, and the
effects of the availability of anti-retroviral drugs will only begin to show on the current
analysis. The issue has not yet been finalized by the Harmony Council because through these
negotiations management identified a need for a workshop on the bill to ensure that all negotiating
parties have the same information and understanding on the contents of the bill. We are currently
awaiting a date for the workshop from the National Department of Healths Traditional Health
Practitioners Office.
In fiscal 2008, there were 82 documented AIDS related deaths as compared to 52 in fiscal 2007
and 49 in 2006. In addition, 166 employees left as a result of medical repatriation in fiscal 2008
as compared to 783 in fiscal 2007 and 1,572 in fiscal 2006. Medical repatriations refer to those
employees who are not sufficiently well to continue working with us and are thus provided with an
early and humane exit.
We embarked upon a holistic and integrated campaign in fiscal 2008 in which approximately
R19.0 million (U.S.$2.6 million) was spent.
Australia
Australia has a well regulated system of occupational health and safety, comprised of
legislation and regulations in each of its states. Several of these specifically apply to the
mining industry, including extensive codes of practice and guidelines. There is also a well
developed certification and licensing system for employees and the usage of certain items of
equipment. The legislation and regulations governing this area include the Australian Standards
4804, the Safety Management Systems and the Western Australian Mining Regulation Act 1994, the
Occupational Safety and Health Act 1984 (WA), the Occupational Safety and Health Regulations 1996,
the Mines Safety and Inspection Act 1994 (WA) and the Mines Safety and Inspection Regulations 1995.
In the event of injury while at work, employees are protected by a compulsory workers
compensation scheme.
We currently believe that the prevalence of HIV & AIDS-related diseases among our Australian
workforce is not material to our Australian operations.
PNG
PNG has a significant mining industry, and a developing system of occupational health and
safety. The Mining (Safety) Act of 1977 (PNG) is the principal legislation that addresses a range
of issues such as working hours, minimum safety and reporting requirements. Other legislation and
regulations also apply.
Although reliable statistics with regard to infection rates are not readily available,
preliminary results indicate that PNG is in the early stages of an AIDS pandemic. As part of the
development of the Hidden Valley project, and other exploration activities carried out by us in
PNG, we have rolled out a health care strategy for our employees to increase Aids awareness. See
Risk Factors Risks Relating to Our Business and Our Industry HIV/AIDS poses risks to Harmony
in terms of productivity and costs and Risk Factors Risks Relating to Our Business and Our
Industry The cost of occupational healthcare services may increase in the future.
88
Item 4A. UNRESOLVED STAFF COMMENTS
Not applicable.
89
Item 5. OPERATING AND FINANCIAL REVIEW AND PROSPECTS
You should read the following discussion and analysis together with the consolidated financial
statements, including the related notes, appearing elsewhere in this annual report.
Overview
We conduct underground and surface gold mining and related activities, including exploration,
processing, smelting and beneficiation. Our operations have grown significantly since 1995, largely
through acquisitions. Since 1995, we have expanded from a lease-bound mining operation into an
independent world-class gold producer. We are currently the third largest producer of gold in South
Africa, producing some 23.4% of the countrys gold output, and are among the worlds top ten gold
producers. Our gold sales have increased from 650,312 ounces of gold in fiscal 1995 to
approximately 1.9 million ounces of gold in fiscal 2008. As at June 30, 2008, our mining operations
reported total proven and probable reserves of approximately 50.5 million ounces and in fiscal
2008, we processed approximately 25.4 million tons of ore.
Previously, the South African underground operations were treated as three separate reporting
segments for management and reporting purposes, being Quality, Leveraged and Growth. After
the Back to Basics restructuring, management now distinguishes between Underground and
Surface, with each shaft or group of shafts managed by a team (headed by a single general
manager) being considered to be an operating segment.
Our South African reportable segments are as follows:
|
|
|
Tshepong, Phakisa, Bambanani, Doornkop, Elandsrand, Target, Evander
operations, Masimong, Virginia operations and Cooke operations
(classified as discontinued operations); and |
|
|
|
|
all other shafts and surface operations, including those that treat
historic sand dumps, rock dumps and tailings dams, are grouped
together under Other Underground or Other Surface. |
Critical Accounting Policies and Estimates
The preparation of our financial statements in accordance with IFRS as issued by the IASB
requires management to make estimates and assumptions that affect the reported results of our
operations. Actual results may differ from those estimates. We have identified the most critical
accounting policies upon which our financial results depend. Some of our accounting policies
require the application of significant judgment and estimates by management in selecting the
appropriate assumptions for calculating financial estimates. By their nature, these judgments are
subject to an inherent degree of uncertainty and are based on our historical experience, terms of
existing contracts, managements view on trends in the gold mining industry and information from
outside sources.
Our significant accounting policies are described in more detail in note 2 to the consolidated
financial statements. This discussion and analysis should be read in conjunction with the
consolidated financial statements and related notes included in reporting Item 18. Financial
Statements. Management has identified the following as critical accounting policies because
estimates used in applying these policies are subject to material risks and uncertainties.
Management believes the following critical accounting policies, together with the other significant
accounting policies discussed in the notes to the consolidated financial statements, affect its
more significant judgments and estimates used in the preparation of the consolidated financial
statements and could potentially impact our financial results and future financial performance.
Depreciation and Amortization of Mining Assets
Depreciation and amortization expense is calculated using the units of production method and
is based on our current gold production as a percentage of total expected gold production over the
lives of our mines. The lives of the mines are estimated by our geology department using proven and
probable mineral reserves, as determined in accordance with SAMREC, JORC and SEC Industry Guide 7.
The estimate of the total expected future lives of our mines could be materially different
from the actual amount of gold mined in the future and the actual lives of the mines due to changes
in the factors used in determining our mineral reserves, such as the gold price, foreign currency
exchange rates, working costs and working rates. We regularly review the lives of the mines and
economic capacity of those assets with reference to any events or circumstances that may indicate
an adjustment is needed. Given the significance of mining assets to our financial statements, any
changes to the life of mine could have a material impact on the annual amortization charge and
materially impact on our results of operations and financial conditions. See Item 3.
Key Information Risk Factors Harmonys gold reserve figures are estimated based on
90
a number
of assumptions, including assumptions as to mining and recovery factors, future cash costs of
production and the price of gold and may yield less gold under actual production conditions than
currently estimated.
Impairment of Property, Plant and Equipment
We review and evaluate our mining assets for impairment when events or changes in
circumstances indicate the related carrying amounts may not be recoverable. An impairment loss is
recognized for the amount by which the assets carrying amount exceeds its recoverable amount. The
recoverable amount is the higher of an assets fair value less costs to sell and value in use. For
the purposes of assessing impairment, assets are grouped at the lowest levels for which there are
separately identifiable cash flows (cash generating units). Each operating shaft, along with
allocated common assets such as plants and administrative offices, is considered to be a cash
generating unit as each shaft is largely independent of the cash flows of other shafts and assets.
Future cash flows are estimated based on estimated quantities of recoverable minerals, expected
gold prices (considering current and historical prices, price trends and related factors),
production levels and cash costs of production, capital and reclamation costs, all based on
detailed life-of-mine plans. The significant assumptions in determining the future cash flows for
each individual operating mine at June 30, 2008, apart from production cost and capitalized
expenditure assumptions unique to each operation, included a long-term gold price of U.S.$750 per
ounce and South African and Australian dollar exchange rates of U.S.$1 = R7.46 and A$1 = U.S.$0.80,
respectively. The term recoverable minerals refers to the estimated amount of gold that will be
obtained from proven and probable reserves and related exploration stage mineral interests, except
for other mine-related exploration potential and Greenfields exploration potential discussed
separately below, after taking into account losses during ore processing and treatment. Estimates
of recoverable minerals from such exploration stage mineral interests are risk adjusted based on
managements relative confidence in such materials. With the exception of other mine-related
exploration potential and Greenfields exploration potential, estimates of future undiscounted cash
flows are included on an area of interest basis, which generally represents an individual operating
mine, even if the mines are included in a larger mine complex. In the case of mineral interests
associated with other mine-related exploration potential and Greenfields exploration potential,
cash flows and fair values are individually evaluated based primarily on recent exploration results
and recent transactions involving sales of similar properties.
As discussed above under Depreciation and amortization of mining assets, various factors
could impact our ability to achieve our forecasted production schedules from proven and probable
reserves. Additionally, gold prices, capital expenditure requirements and reclamation costs could
differ from the assumptions used in the cash flow models used to assess impairment. The ability to
achieve the estimated quantities of recoverable minerals from exploration stage mineral interests
involves further risks in addition to those factors applicable to mineral interests where proven
and probable reserves have been identified, due to the lower level of confidence that the
identified mineralized material can ultimately be mined economically. Assets classified as other
mine-related exploration potential and Greenfields exploration potential have the highest level of
risk that the carrying value of the asset can be ultimately realized, due to the still lower level
of geological confidence and economic modeling.
During fiscal 2008, we recorded impairments of U.S.$27 million, and during fiscal 2007 and
2006, reversals of impairments of U.S.$19 million and U.S.$30 million, respectively, on property,
plant and equipment, all from continuing operations. Material changes to any of these factors or
assumptions discussed above could result in future impairment charges.
Carrying Value of Goodwill
We evaluate, on at least an annual basis, the carrying amount of goodwill to determine whether
current events and circumstances indicate that such carrying amount may no longer be recoverable.
For the purposes of assessing impairment, assets are grouped at the lowest levels for which there
are separately identifiable cash flows (cash generating units). Each operating shaft, along with
allocated common assets such as plants and administrative offices, is considered to be a cash
generating unit as each shaft is largely independent of the cash flows of other shafts and assets.
To accomplish this, we compare the recoverable amounts of our cash generating units to their
carrying amounts. The recoverable amount is the higher of an assets fair value less costs to sell
and value in use. If the carrying value of a cash generating unit were to exceed its recoverable
amount at the time of the evaluation, we would compare the implied fair value of the cash
generating units goodwill to its carrying amount and any shortfall would be charged to
consolidated income statements. Assumptions underlying fair value estimates are subject to risks
and uncertainties. If these assumptions change in future, we may need to record impairment charges
on goodwill not previously recorded.
During fiscal 2008, we recorded an impairment of U.S.$13 million on goodwill.
91
Provision for environmental rehabilitation
Our mining and exploration activities are subject to various laws and regulations governing
the protection of the environment. Estimated long term environmental obligations, comprising
pollution control, rehabilitation and mine closure, are based on the Groups environmental
management plans. Annual changes in the provision consist of finance costs relating to the change
in the present value of the provision and inflationary increases in the provision estimate, as well
as changes in estimates. The present value of environmental disturbances created is capitalized to
mining assets against an increase in the rehabilitation provision. The rehabilitation asset is
depreciated as discussed above. Rehabilitation projects undertaken, included in the estimates are
charged to the provision as incurred. The cost of ongoing current programs to prevent and control
pollution is charged against income as incurred.
Deferred Tax Asset
We do not recognize a deferred tax asset when it is more likely than not that the asset will
not be utilized. Assessing recoverability of deferred tax assets requires management to make
significant estimates related to expectation of future taxable income. Estimates of future taxable
income are based on forecasted cash flows from operations, reversals of deferred tax liabilities
and the application of existing tax laws in each jurisdiction. To the extent that future taxable
income differs significantly from estimates, our ability to realize the net deferred tax assets
recorded at the balance date could be impacted. Additionally, future charges in tax laws in the
jurisdictions in which we operate could limit our ability to obtain the future tax benefits
represented by deferred tax assets recorded at the balance date.
Revenue
Substantially all of our revenues are derived from the sale of gold. As a result, our
operating results are directly related to the price of gold. Historically, the price of gold has
fluctuated widely. The gold price is affected by numerous factors over which we do not have
control. See Item 3. Key Information Risk Factors The profitability of Harmonys operations,
and the cash flows generated by those operations, are affected by changes in the market price for
gold, which in the past has fluctuated widely.
As a general rule, we sell our gold produced at market prices to obtain the maximum benefit
from increases in the prevailing gold price and do not enter into hedging arrangements such as
forward sales or derivatives that establish a price in advance for the sale of our future gold
production.
A substantial proportion of the production at each of New Hampton and Hill 50 in Australia was
already hedged when we acquired them. Since fiscal 2002, in line with our strategy of being
generally unhedged, we evaluated the hedge agreements as well as market conditions and closed out
the hedge contracts at the time that provided the most benefits. The last of the contracts were
closed out during fiscal 2007, which resulted in our being unhedged in line with our stated company
policy to give shareholders full exposure to the gold price.
Our costs of closing out certain operations hedge positions in fiscal years 2007 and 2006 was
approximately U.S.$60 million and U.S.$34 million, respectively, before taxes.
Significant changes in the price of gold over a sustained period of time may lead us to
increase or decrease our production in the near-term.
Harmonys Realized Gold Price
The average gold price in U.S. dollars received by us has generally increased since January 1,
2002. In fiscal 2008, the average gold price in U.S. dollars received by us for continuing
operations was U.S.$818 per ounce. The market price for gold (and, accordingly, the price received
by us) is affected by numerous factors over which we have no control. See Item 3. Key Information
Risk Factors The profitability of Harmonys operations, and the cash flows generated by those
operations, are affected by changes in the market price for gold, which in the past has fluctuated
widely.
The following table sets out the average, the high and the low London Bullion Market price of
gold and our average U.S. dollar sales price during the past three fiscal years:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended |
|
|
June 30 |
|
|
2008 |
|
2007 |
|
2006 |
|
|
|
|
|
|
($/oz) |
|
|
|
|
Average |
|
|
821 |
|
|
|
638 |
|
|
|
527 |
|
High |
|
|
1,011 |
|
|
|
692 |
|
|
|
726 |
|
Low |
|
|
649 |
|
|
|
561 |
|
|
|
418 |
|
92
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year Ended |
|
|
June 30 |
|
|
2008 |
|
2007 |
|
2006 |
|
|
|
|
|
|
($/oz) |
|
|
|
|
Harmonys average sales price continuing operations (1) |
|
|
818 |
|
|
|
638 |
|
|
|
529 |
|
|
|
|
(1) |
|
Our average sales price differs from the average gold price due to the timing of our sales
of gold within each year. |
Costs
Our cash costs and expenses typically make up over 80% of our total costs. The remainder of
our total costs consists primarily of exploration costs, employment termination costs, corporate
and sundry expenditure, and depreciation and amortization. Our cash costs consist primarily of
production costs exclusive of depreciation and amortization. Production costs are incurred on
labor, stores and utilities. Labor costs are the largest component and typically comprise
approximately 50% of our production costs.
Our cash costs for continuing operations has increased from U.S.$440 per ounce in fiscal 2006
to U.S.$591 per ounce in fiscal 2008, mainly as a result of lower production volumes, the impact of
increased labor and energy costs as well as inflationary pressures on supply contracts. In U.S.
dollar terms, these increases were offset by the depreciation of the Rand-U.S. dollar exchange
rate.
Our U.S. translated costs are very sensitive to the exchange rate of the Rand and other
non-U.S. currencies to the U.S. dollar. See Item 5. Operating and Financial Review and Prospects
Exchange Rates. Appreciation of the Rand and other
non-U.S. currencies against the U.S. dollar increases working costs at our
operations when those costs are translated into U.S. dollars. See Item 3. Key
Information Risk Factors Because most of Harmonys production costs are in Rand and other
non-U.S. currencies, while gold is generally sold in U.S. dollars, Harmonys financial condition
could be materially harmed by an appreciation in the value of the Rand and other non-U.S.
currencies.
The South African Rand depreciated approximately 11% against the U.S. dollar in fiscal 2008
compared to fiscal 2007. In the case of our International operations, both the Australian dollar
and Kina appreciated 13% and 12%, respectively, against the U.S. dollar in fiscal 2008 compared to
fiscal 2007.
Reconciliation of Non-GAAP Measures
Total cash costs and total cash costs per ounce are non-GAAP measures.
Our cash costs consist primarily of production costs and are incurred to access ore to produce
current mined reserves and are expensed as incurred. Cash costs do not include capital development
costs, which are incurred to allow access to the ore body for future mining operations and are
capitalized and amortized when the relevant reserves are mined.
We have calculated total cash costs and total cash costs per ounce by dividing total cash
costs, as determined using the guidance provided by the Gold Institute, by gold ounces sold for all
periods presented. Total cash costs, as defined in the guidance provided by the Gold Institute,
include mine production costs, transport and refinery costs, applicable general and administrative
costs, costs associated with movements in production inventories and ore stockpiles and ongoing
environmental rehabilitation costs as well as transfers to and from deferred stripping and costs
associated with royalties. Ongoing employee termination cost is included, however, employee
termination costs associated with major restructuring and shaft closures are excluded.
Changes in cash costs per ounce are affected by operational performance, as well as changes in
the currency exchange rate between the Rand and the U.S. dollar and, in the case of the
International operations, the Australian dollar and Kina. Total cash costs and total cash costs per
ounce are non-GAAP measures. Total cash costs and total cash costs per ounce should not be
considered by investors in isolation or as an alternative to production costs, cost of sales, or
any other measure of financial performance calculated in accordance with IFRS as issued by the
IASB. In addition, while the Gold Institute has provided a definition for the calculation of total
cash costs and total cash costs per ounce, the calculation of total cash costs and total cash costs
per ounce may vary from company to company and may not be comparable to other similarly titled
measures of other companies. However, we believe that cash costs per ounce is a useful indicator to
investors and management of a mining companys performance as it provides (1) an indication of the
cash generating capacities of our mining operations, (2) the trends in cash costs as the companys
operations mature, (3) a measure of a companys
performance, by comparison of cash costs per ounce to the spot price of gold and (4) an internal
benchmark of performance to allow for comparison against other companies.
93
The following is a reconciliation of total cash costs, as a non-GAAP measure, to the nearest
comparable GAAP measure, cost of sales under IFRS:
Continuing operations
The following is a reconciliation of total cash costs from continuing operations, as a
non-GAAP measure, to the nearest comparable GAAP measure, cost of sale from continuing operations:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
|
(in $ millions, except per ounce amounts) |
Total cost of sales from continuing operations under IFRS |
|
|
1,122 |
|
|
|
929 |
|
|
|
909 |
|
Depreciation and amortization expense |
|
|
(117 |
) |
|
|
(106 |
) |
|
|
(138 |
) |
(Provision)/reversal of provision for rehabilitation costs |
|
|
(1 |
) |
|
|
6 |
|
|
|
3 |
|
Care and maintenance costs of restructured shafts |
|
|
(10 |
) |
|
|
(8 |
) |
|
|
(22 |
) |
Employment termination and restructuring costs |
|
|
(29 |
) |
|
|
|
|
|
|
12 |
|
Share-based payments |
|
|
(6 |
) |
|
|
(6 |
) |
|
|
(15 |
) |
(Impairment)/reversal of impairment of assets |
|
|
(40 |
) |
|
|
19 |
|
|
|
30 |
|
Provision for post retirement benefits |
|
|
(1 |
) |
|
|
2 |
|
|
|
(1 |
) |
Total cash costs from continuing operations using Gold Institute guidance |
|
|
918 |
|
|
|
836 |
|
|
|
778 |
|
Per ounce calculation: |
|
|
|
|
|
|
|
|
|
|
|
|
Ounces sold |
|
|
1,550,527 |
|
|
|
1,747,071 |
|
|
|
1,769,951 |
|
Total cash cost per ounce from continuing operations using Gold
Institute guidance |
|
|
591 |
|
|
|
479 |
|
|
|
440 |
|
Discontinued operations
The following is a reconciliation of total cash costs from discontinued operations, as a
non-GAAP measure, to the nearest comparable GAAP measure, cost of sales from discontinued
operations:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
|
(in $ millions, except per ounce amounts) |
Total cost of sales from discontinued operations under IFRS |
|
|
237 |
|
|
|
418 |
|
|
|
300 |
|
Depreciation and amortization expense |
|
|
(7 |
) |
|
|
(57 |
) |
|
|
(35 |
) |
(Provision)/reversal of provision for rehabilitation costs |
|
|
(1 |
) |
|
|
(5 |
) |
|
|
(1 |
) |
Care and maintenance costs of restructured shafts |
|
|
|
|
|
|
(1 |
) |
|
|
(6 |
) |
Employment termination and restructuring costs |
|
|
(4 |
) |
|
|
|
|
|
|
1 |
|
Share-based payments |
|
|
|
|
|
|
(1 |
) |
|
|
(1 |
) |
(Impairment)/reversal of impairment of assets |
|
|
5 |
|
|
|
(56 |
) |
|
|
|
|
Total cash costs from discontinued operations using Gold
Institute guidance |
|
|
230 |
|
|
|
298 |
|
|
|
258 |
|
Per ounce calculation: |
|
|
|
|
|
|
|
|
|
|
|
|
Ounces sold |
|
|
398,249 |
|
|
|
587,127 |
|
|
|
616,974 |
|
Total cash cost per ounce from discontinued operations
using Gold Institute guidance |
|
|
576 |
|
|
|
507 |
|
|
|
418 |
|
94
Total Harmony Continuing and discontinued operations
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
|
(in $ millions, except per ounce amounts) |
Total production costs under IFRS |
|
|
1,359 |
|
|
|
1,347 |
|
|
|
1,209 |
|
Depreciation and amortization expense |
|
|
(124 |
) |
|
|
(163 |
) |
|
|
(173 |
) |
(Provision)/reversal of provision for rehabilitation costs |
|
|
(2 |
) |
|
|
1 |
|
|
|
2 |
|
Care and maintenance costs of restructured shafts |
|
|
(10 |
) |
|
|
(9 |
) |
|
|
(28 |
) |
Employment termination and restructuring costs |
|
|
(33 |
) |
|
|
|
|
|
|
13 |
|
Share-based payments |
|
|
(6 |
) |
|
|
(7 |
) |
|
|
(16 |
) |
(Impairment)/reversal of impairment of assets |
|
|
(35 |
) |
|
|
(37 |
) |
|
|
30 |
|
Provision for post retirement benefits |
|
|
(1 |
) |
|
|
2 |
|
|
|
(1 |
) |
Total cash costs using Gold Institute guidance |
|
|
1,148 |
|
|
|
1,134 |
|
|
|
1,036 |
|
Per ounce calculation: |
|
|
|
|
|
|
|
|
|
|
|
|
Ounces sold |
|
|
1,948,776 |
|
|
|
2,334,198 |
|
|
|
2,386,925 |
|
Total cash cost per ounce using Gold Institute guidance |
|
|
589 |
|
|
|
486 |
|
|
|
436 |
|
Within this disclosure document, our discussion and analysis is focused on the total cash
costs measure as defined by the Gold Institute.
While recognizing the importance of reducing cash costs, our chief focus is on controlling
and, where possible, reducing total costs, including overhead costs. We aim to control total unit
costs per ounce produced by maintaining our low total cost structure at our existing operations. We
have been able to reduce total costs by implementing a management structure and philosophy that is
focused on reducing management and administrative costs, implementing an ore reserve management
system that allows for greater grade control and acquiring higher grade reserves. See Item 4.
Information on the Company Business Strategy.
Exchange Rates
Our revenues are very sensitive to the exchange rate of the Rand and other non-U.S. currencies
to the U.S. dollar.
Currently, the majority of our earnings are generated in South Africa and, as a result, most
of our costs are incurred in Rand. Since gold is generally sold in U.S. dollars, most of our
revenues are received in U.S. dollars. The average gold price received by us during fiscal 2008
increased U.S.$180 per ounce to U.S.$818 per ounce from U.S.$638 per ounce during fiscal 2007.
Appreciation of the Rand against the U.S. dollar increases our U.S. dollar working costs at our
South African operations when those costs are translated into U.S. dollars, which serves to reduce
operating margins and net income from our South African operations. Depreciation of the Rand
against the U.S. dollar reduces these costs when they are translated into U.S. dollars, which
serves to increase operating margins and net income from our South African operations. Accordingly,
strength in the Rand generally results in poorer earnings for us if there is not a similar increase
in the gold price.
The exchange rates obtained when converting U.S. dollars to Rand are determined by foreign
exchange markets, over which we have no control. The conversion rate for balance sheet items as at
June 30, 2008 is R7.80 per U.S.$1.00, expect for specific items within equity that are converted at
the exchange rate prevailing on the date the transaction was entered into. This compares with a
conversion rate of R7.04 per U.S.$1.00 as at June 30, 2007, reflecting a depreciation of 11% of the
Rand against the U.S. dollar when compared with June 30, 2007. Income statement items were
converted at the average exchange rate for the fiscal 2008 (R7.26 per U.S.$1.00), reflecting a
depreciation of 1% of the Rand against the U.S. dollar when compared with fiscal 2007. The majority
of our working costs are incurred in Rands and as a result this depreciation of the Rand against
the U.S. dollar would reduce our working costs when translated into U.S. dollars. This effect was
however negated by increases in our labor costs as well as inflationary pressures on our consumable
stores and energy cost, which served to decrease operating margins and net income reflected in our
consolidated income statement for fiscal 2008. Depreciation of the Rand against the U.S. dollar
would cause a decrease in our costs in U.S. dollar terms. Similarly, at our International
operations, depreciation of the Australia dollar or Kina against the U.S. dollar would cause a
decrease in our costs in U.S. dollar terms. See Item 3. Key Information Risk Factors Because
most of Harmonys production costs are in Rand and other non-U.S. currencies, while gold is
generally
sold in U.S. dollars, Harmonys financial condition could be materially harmed by an appreciation
in the value of the Rand and other non-U.S. currencies.
95
Inflation
Our operations have been materially impacted by inflation in recent years. At the end of
fiscal 2008, inflation in South Africa was 11.6%, a high level in recent years, and may rise
further. Because our costs are primarily in Rand and we generally sell our gold in U.S. dollars,
movements in the Rand U.S. dollar exchange rate may further influence the impact of inflation on
our profits. To the extent the Rand depreciates against the U.S. dollar, this depreciation may
offset the impact of inflation. The Rand depreciated approximately 11% in fiscal 2008, as compared
to a 2% strengthening in fiscal 2007 and 7% weakening in fiscal 2006.
South African Socio-Economic Environment
We are a South African company and the majority of our operations are in South Africa. As a
result, we are subject to various economic, fiscal, monetary and political policies and factors
that affect South African companies generally. See Item 3. Key Information Risk Factors
Socio-economic instability in South Africa or regionally may have an adverse effect on Harmonys
operations and profits.
South African companies are subject to significant exchange control limitations. While
exchange controls have been relaxed in recent years, South African companies remain subject to
significant restrictions on their ability to deploy capital outside of the Southern African Common
Monetary Area. As a result, we have historically financed our offshore acquisitions with offshore
long-term debt. See Item 10. Additional Information Exchange Controls.
Social and Labor Plans, or SLPs, have been developed for each of our South African operations.
These SLPs are prepared in line with legislation governing the participation of HDSAs in mining
assets.
We have been granted all of our mining licenses under the MPRDA. We have therefore already
started to incur expenses relating to HDSA participation. We believe the biggest challenge will lie
in maintaining these licenses, as we will have a responsibility in respect of human resource
development, procurement and local economic development. We are unable, however, to provide a
specific amount of what the estimated cost of compliance will be but we will continue to monitor
these costs on an ongoing basis.
Royalties
The MPRDA makes reference to royalties being payable to the South African government in terms
of the Mineral and Petroleum Resources Royalty Bill which has not yet been enacted by Parliament.
The fourth draft of the Mineral and Petroleum Resources Royalty Bill was tabled in Parliament on
August 21, 2008 and provides for the payment of a royalty according to a formula based on earnings
before interest, tax and depreciation and after the deduction of capital expenditure. This rate is
then applied to revenue to calculate the royalty amount due, with a minimum of 0,5% and a maximum
of 5% for gold. It is estimated that the formula could translate to a royalty rate of more than 2%
of gross sales in terms of current pricing assumptions. The latest proposal results in a large
increase from the 1.5% rate proposed in the second draft in 2006. The royalty is to become
effective on May 1, 2009, if the Bill is passed by Parliament in its current form.
Costs
In order to better control our costs, we have reinstated the focus on monthly reviews to
ensure that stringent cost control measures are in place and enforced. This will assist us in
monitoring and reducing consumable costs.
Due to the fact that the new mines are expected to start producing high volumes of ore, due to
better economics of scale, at higher grades, we expect that cash operating costs in dollar per
ounce terms will be reduced. This will be dependent on our achieving our operational plans. The
higher grade is expected to balance the decrease in volume, ensuring that there is consistency in
the ounces produced, with an increase expected in revenue due to the increase in the gold price, as
per our long term view on the various factors influencing the Rand gold price.
We reassessed our labor force and implemented several measures to reduce labor costs. These
measures included terminating some contractors and offering voluntary severance packages to
employees.
Conops
For some years, mining companies have been trying to implement the concept of Conops on the
basis that it is, in theory, a better practice to utilize the companys capital intensive, fixed
assets for every day (excluding public holidays) of the year rather than for 80% of the year. It
was estimated that Conops should result in
increased production of around 25%, with a cost increase in the region of 18%, which would lead to
increased profitability. We have been one of the few companies that had actually been able to
implement Conops, with some degree of success and with the cooperation of the labor unions.
However
as part of our complete review of the operations in fiscal 2008, our
Executive Committee took a
long and hard look at the real benefits of Conops. In essence, we undertook a due diligence as if
we were evaluating it for the first time. These internal due diligences were
96
conducted
at the
Tshepong, Elandsrand, Masimong, Evander No 8 and Winkelhaak shafts, as well as at Cooke 2
operations (Target is the only other shaft in the group that uses Conops).
A thorough fact-finding process was conducted within the mining, engineering (production as
well as shafts and services), human resources and financial disciplines in order to understand the
reasons behind the gaps that prevented the full realisation and potential of Conops. As part of the
process, all service functions, engineering maintenance, response time to breakdowns, weekend
service level requirements as well as commissioning and maintaining of related equipment were
scrutinized.
Conops proved to be unsuitable at Masimong and was discontinued here in November 2007, with
the additional workforce being transferred to Phakisa. Action plans were drawn up by each shaft
management team for the remaining operations to address those issues that were identified as
requiring attention. Based on these assessments, Conops was stopped at Tsephong in January 2008,
and at Elandsrand in February 2008 and Evander 2 and 5 and at Randfonteins Cooke 1, 2 and 3
operations by the end of fiscal 2008. Conops continued at Evander 8.
Productivity
The decline in productivity has been one of the challenges facing the South African gold
industry for a number of years. This decline in our productivity mainly came as a result of an
aging workforce, the health of the workforce that has been negatively impacted by HIV/Aids,
increased working distances from shafts and aging infrastructure. We reacted to these challenges
through various initiatives including the Healthy workforce drive, the VCT campaign (voluntary
testing and counseling), upgrade of rail bound equipment and track work and other improvement
projects.
Electricity Supply
On January 24, 2008, ESKOM (the South African electricity supply body) advised us that it
would be interrupting the power supply to our South African operations. As the safety of the miners
could not be guaranteed, mining was halted for four days, after which shafts operated at between
60% 80% of capacity. A meeting between ESKOM and its industrial consumers was held on January
29, 2008, whereby ESKOM committed to supplying 90% of our electricity demand prior to the shut
down. This came into effect on February 1, 2008. Management has restructured operating processes in
order to gain the most effective and efficient use of the electricity allotted. We have devised new
strategies on optimizing operations to produce at 90% of previous electricity supply to ensure that
we deliver in line with our strategic plans.
Results of Operations
Years Ended June 30, 2008 and 2007
Continuing Operations
Revenues
Revenue increased U.S.$153 million, or 14%, from U.S.$1,116 million in fiscal 2007 to
U.S.$1,269 million in fiscal 2008. This increase is attributable primarily to the higher average
price of gold received by us, U.S.$818 per ounce in 2008 compared to U.S.$638 per ounce in 2007.
This increase was partially offset by a decrease in ounces produced.
Our gold sales decreased 196,544 ounces, or 11%, from 1,747,071 in fiscal 2007 to 1,550,527 in
fiscal 2008. The grade recovered was lower, at 0.08 ounces per ton in fiscal 2008 compared to 0.10
ounces per ton in fiscal 2007, negatively impacting on the ounces produced. The lower recovery
grade was as a result of the increase in tons treated from surface tailings dams at a lower
recovery grade.
At Bambanani ounces produced decreased by 19%, from 189,683 in fiscal 2007 to 158,985 in
fiscal 2008. This was due to the restructuring of the shaft as a result of power constraints. This
was offset by a better recovery grade which increased from 0.154 ounces per ton in fiscal 2007 to
0.174 ounces per ton in fiscal 2008.
At Doornkop ounces produced decreased from 57,364 in fiscal 2007 to 44,143 in fiscal 2008.
Production volumes decreased by 103,000 tons, or 37%, primarily due to an 18 day production
stoppage to facilitate shaft work related to the South Reef project as well as three days lost due
to Eskoms power management process.
At Elandsrand ounces produced decreased from 194,710 in fiscal 2007 to 158,631. This was due
to a decrease in volumes mainly as a result of days lost due to the accident in October 2007, as
well as a decrease in grade.
97
At Target ounces produced decreased by 40% from 142,433 in fiscal 2007 to 85,006 in fiscal
2008. Production volumes decreased by 24% mainly due to issues relating to the massive stopes,
which also impacted on the grade.
At Masimong ounces produced decreased by 21%, or 30,383 ounces, from 147,958 in fiscal 2007 to
117,575 in fiscal 2008. This was due to a decrease in production volumes from 1,0740,000 tons to
892,000 tons as a result of the restructuring process at the shaft.
The ounces produced at Kalgold increased by 66% from 56,129 in fiscal 2007 to 93,172 in fiscal
2008. This was due to a 72% increase in recovery grade from 0.032 ounces per ton in fiscal 2007 to
0.055 ounces per ton in fiscal 2008. This was due to the higher grade mined in the D-zone pit.
Cost of sales
Cost of sales includes production costs, depreciation and amortization, impairment of assets and
employment termination and restructuring costs.
a) Production costs
The following table sets out our total ounces sold and weighted average cash costs per ounce
for fiscal 2008 and fiscal 2007:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Percentage |
|
|
Year Ended June 30, |
|
Year Ended June 30, |
|
Increase |
|
|
2008 |
|
2007 |
|
in Cash |
|
|
(oz) |
|
($/oz) |
|
(oz) |
|
($/oz) |
|
Costs per ounce |
SOUTH AFRICA |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tshepong |
|
|
273,119 |
|
|
|
457 |
|
|
|
318,887 |
|
|
|
351 |
|
|
|
30 |
|
Phakisa |
|
|
4,212 |
|
|
|
558 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Bambanani |
|
|
158,985 |
|
|
|
641 |
|
|
|
197,060 |
|
|
|
586 |
|
|
|
9 |
|
Doornkop |
|
|
44,143 |
|
|
|
703 |
|
|
|
57,364 |
|
|
|
439 |
|
|
|
60 |
|
Elandsrand |
|
|
158,631 |
|
|
|
652 |
|
|
|
194,710 |
|
|
|
527 |
|
|
|
24 |
|
Target |
|
|
85,006 |
|
|
|
605 |
|
|
|
142,433 |
|
|
|
370 |
|
|
|
64 |
|
Masimong |
|
|
117,575 |
|
|
|
745 |
|
|
|
147,958 |
|
|
|
559 |
|
|
|
33 |
|
Evander operations |
|
|
240,037 |
|
|
|
525 |
|
|
|
235,443 |
|
|
|
481 |
|
|
|
9 |
|
Virginia operations |
|
|
250,324 |
|
|
|
719 |
|
|
|
266,948 |
|
|
|
546 |
|
|
|
32 |
|
Other underground |
|
|
69,574 |
|
|
|
744 |
|
|
|
104,507 |
|
|
|
488 |
|
|
|
52 |
|
Other surface |
|
|
148,921 |
|
|
|
390 |
|
|
|
81,761 |
|
|
|
428 |
|
|
|
(9 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
INTERNATIONAL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PNG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total continuing operations |
|
|
1,550,527 |
|
|
|
|
|
|
|
1,747,071 |
|
|
|
|
|
|
|
|
|
Weighted average |
|
|
|
|
|
|
591 |
|
|
|
|
|
|
|
479 |
|
|
|
23 |
|
Our average cash costs from continuing operations increased by U.S.$112 per ounce, or 23%,
from U.S.$479 per ounce in fiscal 2007 to U.S.$591 per ounce in fiscal 2008. Cash costs per ounce
vary with the working costs per ton (which is, in turn, affected by the number of tons processed)
and grade of ore processed. Cash costs expressed in U.S. dollars per ounce also vary with
fluctuations in the Rand-U.S. dollar exchange rate, because most of our working costs are incurred
in Rand. The increase in cash cost expressed in U.S. dollars per ounce in fiscal 2008 was
attributable primarily to an increase in operating cost as well as the decrease in ounces produced
when compared to fiscal 2007. Annual increases in labor cost as well as inflationary pressures on
our consumable stores and energy costs were the main contributors towards a higher operating cost.
At Tshepong, the cash costs increased from U.S.$351 in fiscal 2007 to U.S.$457, or 30%, in
fiscal 2008. This was due to the decrease in ounces produced in fiscal 2008 as well an increase of
11% related to increases in labor and supply costs.
At Doornkop, the cash costs increased by 60%, from U.S.$439 in fiscal 2007 to U.S.$703 in
fiscal 2008, primarily due to lower production volumes and industry-wide cost increases.
98
At Target, the cash costs increased from U.S.$370 in fiscal 2007 to U.S.$605 in fiscal 2008,
or by 64%, primarily due to lower recovery grades and volumes resulting from issues experienced
during fiscal 2008.
At Masimong, the cash costs increased by 33% from U.S.$559 in fiscal 2007 to U.S.$745 in
fiscal 2008, primarily due to the restructuring and cessation of Conops, as well as a decrease in
ounces produced.
Under Other Underground, the cash costs at Joel increased from U.S.$418 in fiscal 2007 to
U.S.$639 in fiscal 2008, or 53%. This was due to the decrease in tonnage after re-equipping
resulted in the shaft not being fully operational for the first six months of fiscal 2008. Costs
were also 17% higher in fiscal 2008. Also, at St. Helena, cash costs increased by 81% from U.S.$840
per ounce in fiscal 2007 to U.S.$1,523 per ounce in fiscal 2008. This was due to the fact that the
shaft was closed during fiscal 2008.
Under Other Surface, the cash costs at Kalgold decreased by 15% from U.S.$485 in fiscal
2007 to U.S.$411 in fiscal 2008, primarily due to the increase in ounces produced. This was offset
by an increase of 30% at Phoenix, from U.S.$293 to U.S.$381, as a result of a decrease in grade and
an increase in volumes and transport costs
b) Depreciation and amortization
Depreciation and amortization increased to U.S.$117 million in fiscal 2008, from U.S.$106
million in fiscal 2007. This increase relates primarily to the increase in depreciation on
non-mining assets (U.S.$4 million) and borrowings issue costs (U.S.$3 million). The commencement
of depreciation on the two completed levels on the Elandsrand New Mine during July 2007 resulted in
a depreciation charge of U.S.$2 million. These increases offset the decrease resulting from a
decrease in production.
c) Employment termination and restructuring costs
The charge for employment termination and restructuring costs increased from U.S.$nil in
fiscal 2007 to U.S.$29 million in fiscal 2008. The charge in fiscal 2008 relates to the voluntary
retrenchment process that was initiated in December 2007 when management decided to decentralize
central services and the cessation of Conops at several of the operations. By the end of fiscal
2008, the process had been completed.
d) Impairment of assets
The impairment charge increased from a credit of U.S.$19 million in fiscal 2007 to a charge of
U.S.$40 million in fiscal 2008. The charge in fiscal 2008 relates to impairments at the Evander and
other underground operations as well as surface operations (Kalgold). Included in the amount is
U.S.$13 million for goodwill related to certain shafts that were included under Other
Underground. These impairments resulted primarily from a decrease in the expected life of mine of
these operations, as well as an increase in the costs to operate the shafts. These changes resulted
in the carrying amount exceeding the recoverable amount. The credit in fiscal 2007 resulted from
reversals at surface operations (Kalgold) and other underground operations. This was offset by a
charge of U.S.$2 million relating to the cessation of operations at the Refinery in the Free State.
Other expenses/income
Charges for other expenses increased to U.S.$15 million, compared with a credit of U.S.$25
million in fiscal 2007. This was primarily due to the decrease of profit on disposal of property,
plant and equipment from U.S.$25 million in fiscal 2007 to U.S.$nil in fiscal 2008. Also
contributing was the increase in provision for bad debts from U.S.$1 million in fiscal 2007 to
U.S.$14 million in fiscal 2008. This provision relates to trade and loans receivables that have
exceeded their payment terms, and where we believe that recoverability is doubtful.
These charges were offset by the increase of U.S.$15 million in foreign exchange gains related
to the loans to the International operations. These loans, which was previously designated as net
investments of the Groups International operations, were de-designated in fiscal 2008, mainly as a
result of the expected proceeds from the PNG Partnership Agreement (see Recent Developments).
Accumulated exchange gains/(losses) that arose while the loans were considered to form part of the
Groups net investment in its International operations will be reclassified to the consolidated
income statement as and when the loans are repaid.
Loss from associates
The loss from associates increased from U.S.$3 million in fiscal 2007 to U.S.$11 million in
fiscal 2008. The increase relates primarily to inclusion of losses from Pamodzi from since
acquisition on February 27, 2008.
Profit on sale of investment in associate
The profit on sale of investment in associate decreased to U.S.$nil in fiscal 2008 from
U.S.$33 million in fiscal 2007. The amount in 2007 was as a result of the disposal of our interest
in Western Areas in exchange for Gold Fields shares.
99
Impairment of investment in associate
The charge relating the impairment of investment in associate increased from U.S.$nil in
fiscal 2007 to U.S.$12 million in fiscal 2008. The amount in fiscal 2008 relates primarily to the
impairment of the investment in Pamodzi. The recoverable amount was determined with reference to
the market value of the listed shares, which would be the amount we would receive on disposal of
the shares. As the carrying value exceeded the recoverable amount, the investment was impaired down
to this amount.
Fair value of non-derivative financial instruments
The gains in fiscal years 2007 and 2008 are related to the investment in ARM held by the ARM
Empowerment Trust, where the increase in the share value of the ARM shares above R29 (U.S.$4.62)
per share is limited to the interest capitalized on the Nedbank loan.
Loss on sale of listed investments
The loss on sale of listed investments increased from U.S.$5 million in fiscal 2007 to U.S.$63
million in fiscal 2008. The amount in 2008 relates to the sale of the remainder of the investment
in Gold Fields. The loss in fiscal 2007 arose when we disposed of a portion of our interest in Gold
Fields through various transactions.
Investment income
Investment income increased from U.S.$27 million in fiscal 2007 to U.S.$39 million in fiscal
2008, primarily to the increase in interest received on loans (U.S.$4 million) and held-to-maturity
investments, being our environmental trust funds (U.S.$4 million). Also contributing was an
increase in dividends received from U.S.$3 million in fiscal 2007 to U.S.$5 million in fiscal 2008,
which related to the Gold Fields shares.
Finance costs
Finance costs increased from U.S.$65 million in fiscal 2007 to U.S.$70 million in fiscal 2008.
This was due primarily to the increase in interest rates as well as the increase in the balance of
the outstanding debt. This was offset by the increase in interest capitalized to qualifying assets,
from U.S.$10 million in fiscal 2007 to U.S.$22 million in fiscal 2008. See Recent Accounting
Pronouncements for a discussion on the early-adoption of IAS 23 (Revised) Borrowing Costs.
Income and Mining Taxes
South Africa. We pay taxes on mining income and non-mining income. The amount of our South
African mining income tax is calculated on the basis of a formula that takes into account our total
revenue and profits from, and capital expenditures for, mining operations in South Africa. 5% of
total mining revenue is exempt from taxation in South Africa as a result of the application of the
applicable gold mine formula. The amount of revenue subject to taxation is calculated by deducting
qualifying capital expenditures from taxable mining income. The amount by which the taxable mining
income exceeds 5% of mining revenue constitutes taxable mining income. We and our subsidiaries each
make our own calculation of taxable income.
The tax rate applicable to the mining and non-mining income of a gold mining company depends
on whether the company has elected to be exempt from the Secondary Tax on Companies, (STC). The
STC is a tax on dividends declared and, at present, the STC tax rate is equal to 10% (previously
12,5%). To the extent we receive dividends, such dividends received are offset against the amount
of dividends paid for purposes of calculating the amount subject to STC. In 1993, all existing
South African gold mining companies had the option to elect to be exempt from STC. If the election
was made, a higher tax rate would apply for both mining and non-mining taxable income. In 2008, the
tax rates for companies that elected the STC exemption were 43% for mining income and 35% for
non-mining income, compared with 34% for mining income and 28% for non-mining income if the STC
exemption election was not made. In 2007, the tax rates for companies that elected the STC
exemption were 45% for mining income and 37% for non-mining income, compared with 35% for mining
income and 29% for non-mining income if the STC exemption election was not made. In 1993, we
elected to pay the STC tax. All of our South African subsidiaries, excluding Avgold, elected the
STC exemption.
|
|
|
|
|
|
|
|
|
Income and Mining Tax |
|
2008 |
|
2007 |
Effective tax rate (expense)/benefit |
|
|
172 |
% |
|
|
(25 |
)% |
The effective tax rate for fiscal 2008 was higher than the statutory tax rate of 43% for us
and our subsidiaries as a whole. The most
100
significant reasons for the increase in the effective tax
rate in fiscal 2008 relates to non-deductible expenses and prior year adjustments. Offsetting this
is the difference between the SA mining statutory tax rate and the rate used to provide deferred
tax and other tax dispensations granted on certain mining assets. Included in the non-deductible
expenses is the impairment on investment in associate (U.S.$11 million) and loss on sale of
investments (U.S.$63 million).
PNG. We are in the process of developing the Hidden Valley Project in PNG. We are also
reviewing other potential projects and carrying out extensive exploration.
PNG mining projects are taxed on a project basis. Therefore each project is taxed as a
separate entity, even though it may be one of a number of projects carried on by the same company.
In certain circumstances there is an ability to transfer the tax benefit obtained through
exploration expenditure between projects and wholly owned companies. Tax losses are generally
quarantined and cannot be transferred between projects.
PNG mining companies are taxed at a rate of tax of 30%.
Capital development and exploration expenditure incurred in PNG is capitalized for tax
purposes and can be generally deducted at 25% per annum on a diminishing value basis against
project income.
PNG imposes dividend withholding tax of 10% on dividends paid by PNG mining operations to non
residents. Although PNG also imposes interest withholding tax on interest off shore, PNG mining
operations may qualify for an exemption.
Discontinued Operations
Revenues
Revenues decreased from U.S.$372 million in fiscal 2007 to U.S.$312 million in fiscal 2008,
due to the fact that South Kalgoorlie and Orkney operations were sold in December 2007 and February
2008, respectively, as well as Mt Magnet being placed on care and maintenance. Also contributing is
lower ounces produced at the Cooke operations. These decreases were offset by an increase in the
average gold price received.
Costs
Costs decreased from U.S.$374 million in fiscal 2007 to U.S.$236 million in fiscal 2008. This
was due to the sale of South Kalgoorlie and Orkney operations during fiscal 2008. Also contributing
is the decrease in the depreciation and amortization charge from U.S.$57 million in fiscal 2007 to
U.S.$7 million in fiscal 2008. This was due to the cessation of charging depreciation on assets
classified as held for sale. The profit on sale of the South Kalgoorlie and Orkney operations
amounted to a credit of U.S.$13 million.
Impairment of assets
The impairment of assets charge decreased from a charge of U.S.$56 million in fiscal 2007 to a
credit of U.S.$5 million in fiscal 2008. These amounts in fiscal 2007 and 2008 relate to
adjustments to the carrying value of Australian operations assets when they were classified as
held for sale and subsequent reporting dates.
Income and Mining Taxes
South Africa. We pay taxes on mining income and non-mining income. For details, refer to the
discussion under Income and Mining Taxes in the Continuing Operations section.
In 2008, the tax rates for companies that elected the STC exemption were 43% for mining income
and 35% for non-mining income, compared with 34% for mining income and 28% for non-mining income if
the STC exemption election was not made. In 2007, the tax rates for companies that elected the STC
exemption were 45% for mining income and 37% for non-mining income, compared with 35% for mining
income and 29% for non-mining income if the STC exemption election was not made.
Australia. Generally, Australia imposes tax on the worldwide income (including capital gains)
of all of our Australian incorporated and tax resident entities. The current income tax rate for
companies is 30%. Ongoing business, mining, exploration and rehabilitation costs incurred each year
are fully deductible. The cost of plant and capital mining expenditure may be depreciated and
deducted over its effective life.
The Australian legislature has introduced a Tax Consolidations Regime, under which from July
1, 2003, Harmony Gold Australia Proprietary Limited and its wholly owned Australian subsidiary
companies are recognised and taxed as a single entity. Under the consolidations rules all of the
Australian subsidiary companies are treated as divisions of Harmony Gold Australia. As a result all
inter company transactions between group members are ignored for tax purposes. This allows the
group to transfer assets between group members without any tax consequences, and to utilize all tax
losses incurred by each company in the group.
101
Mining operations (other than operations on freehold land) are also subject to a 2.5% gold
royalty because the mineral rights are owned by the state. All gold production from the Mt. Magnet
operations is subject to this royalty. Most of the production from the South Kalgoorlie operations
is from freehold land and is, accordingly, exempt from this royalty.
Withholding tax is payable on dividends, interest and royalties paid by Australian residents
to non-residents, which would include any dividends on the shares of our Australian subsidiaries
that are paid to us. In the case of dividend payments to non-residents, a 30% withholding tax
applies. However, where the recipient of the dividend is a resident of a country with which
Australia has concluded a double taxation agreement, the rate of withholding tax is generally
limited to 15% (or 10% where the dividend is paid to a companys parent company). Where dividends
are fully franked, an effective credit is allowed against any withholding tax otherwise payable,
regardless of whether a double taxation agreement is in place.
Continuing and discontinued operations
Net (loss)/profit
The net (loss)/profit decreased from a net profit of U.S.$51 million in fiscal 2007 to a net loss
of U.S.$30 million. This is due to the factors discussed above.
Years Ended June 30, 2007 and 2006
Continuing Operations
Revenues
Revenue increased U.S.$179 million, or 19%, from U.S.$937 million in fiscal 2006 to U.S.$1,116
million in fiscal 2007. This increase is attributable primarily to the slightly higher average
price of gold received by us, U.S.$638 per ounce in 2007 compared to U.S.$529 per ounce in fiscal
2006. Also contributing to the increase was an increase in ounces produced.
Our gold sales decreased 22,880 ounces, or 1%, from 1,769,951 in fiscal 2006 to 1,747,071 in
fiscal 2007. The grade recovered was lower, at 0.11 ounces per ton in fiscal 2007 compared to 0.12
ounces per ton in fiscal 2006, negatively impacting on the ounces produced.
At Doornkop ounces produced increased by 31,6% from 43,593 in fiscal 2006 to 57,364 in fiscal
2007. This was mainly due to an increase in production volumes. Volumes increased, mainly as a
result of flexibility created during the year by increasing development of the orebody.
At Elandsrand ounces produced increased from 170,867 in fiscal 2006 to 194,710 in fiscal 2007.
This can primarily be attributed to an increase in production volumes.
At the Evander operations, ounces produced decreased by 14% to 235,443 ounces in fiscal 2007
from 274,439 ounces in fiscal 2006. This was primarily attributable to lower tons milled from
Evander 5 as well as a lower recovery grade from Evander 7. Tons milled for Evander 5 decreased
from 450,000 in fiscal 2006 to 377,000 in fiscal 2007. The decrease in tons milled was mainly due
to the depletion of the open raise lines on 24 level and 80% of the mining was done in pillars. The
recovery grade at Evander 7 dropped from 0.191 in fiscal 2006 to 0.137 in fiscal 2007. Ounces
produced for Evander 7 decreased by 26.6% from 83,202 in fiscal 2006 to 61,044 in fiscal 2007. The
grade decrease at Evander 7 was mainly due to the depletion of a very high grade pay shoot in the
No.3 decline area as well as an increase in mining in the upper area of the shaft (pillar area)
that was of lower grade.
Under OtherUnderground, ounces produced at Joel increased by 36,4% from 58,595 in fiscal
2006 to 79,923 in fiscal 2007. The increase in ounces produced was due to an increase in tons
milled as well as an increase in recovered grade. The increase in tons milled was primarily
attributable to the commissioning of the midshaft loading arrangement on 137 level, which was
commissioned on February 28, 2006.
Under Other Surface, ounces produced at Kalgold decreased from 77,071 in fiscal 2006 to
56,129 in fiscal 2007. Tons milled decreased from 2,008,000 in fiscal 2006 to 1,740,000 in fiscal
2007. These decreases were due to lower throughput into the plant due to a water shortage
encountered in March 2007.
Cost of sales
Cost of sales includes production costs, depreciation and amortization, impairment of assets
and employment termination and restructuring costs.
102
a) Production costs
The following table sets out our total ounces sold and weighted average cash costs per ounce
for fiscal 2007 and fiscal 2006:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Percentage |
|
|
Year Ended June 30, |
|
Year Ended June 30, |
|
Increase |
|
|
2007 |
|
2006 |
|
in Cash |
|
|
(oz) |
|
($/oz) |
|
(oz) |
|
($/oz) |
|
Costs per ounce |
SOUTH AFRICA |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tshepong |
|
|
318,887 |
|
|
|
351 |
|
|
|
335,289 |
|
|
|
335 |
|
|
|
5 |
|
Phakisa |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bambanani |
|
|
197,06 |
|
|
|
586 |
|
|
|
200,739 |
|
|
|
502 |
|
|
|
17 |
|
Doornkop |
|
|
57,364 |
|
|
|
439 |
|
|
|
43,593 |
|
|
|
558 |
|
|
|
(21 |
) |
Elandsrand |
|
|
194,710 |
|
|
|
527 |
|
|
|
170,867 |
|
|
|
523 |
|
|
|
1 |
|
Target |
|
|
142,433 |
|
|
|
370 |
|
|
|
150,196 |
|
|
|
346 |
|
|
|
7 |
|
Masimong |
|
|
147,958 |
|
|
|
559 |
|
|
|
136,153 |
|
|
|
489 |
|
|
|
14 |
|
Evander operations |
|
|
235,443 |
|
|
|
481 |
|
|
|
274,439 |
|
|
|
403 |
|
|
|
19 |
|
Virginia operations |
|
|
266,948 |
|
|
|
546 |
|
|
|
276,285 |
|
|
|
488 |
|
|
|
12 |
|
Other Underground |
|
|
104,507 |
|
|
|
488 |
|
|
|
77,652 |
|
|
|
541 |
|
|
|
(8 |
) |
Other Surface |
|
|
81,761 |
|
|
|
428 |
|
|
|
104,738 |
|
|
|
439 |
|
|
|
(3 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
INTERNATIONAL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PNG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total continuing operations |
|
|
1,747,071 |
|
|
|
|
|
|
|
1,769,951 |
|
|
|
|
|
|
|
|
|
Weighted average |
|
|
|
|
|
|
479 |
|
|
|
|
|
|
|
440 |
|
|
|
9 |
|
Our
weighted average cash costs from continuing operations increased by
U.S.$39 per ounce, or
9%, from U.S.$440 per ounce in fiscal 2006 to U.S.$479 per ounce in fiscal 2007. Cash costs per
ounce vary with the working costs per ton (which is, in turn, affected by the number of tons
processed) and grade of ore processed. Cash costs expressed in U.S. dollars per ounce also vary
with fluctuations in the Rand-U.S. dollar exchange rate, because most of our working costs are
incurred in Rand. The increase in cash cost expressed in U.S. dollars per ounce in fiscal 2007 was
attributable primarily to an increase in operating cost as the ounces produced remained almost
unchanged when compared to fiscal 2006. Annual increases in labor cost as well as inflationary
pressures on our consumable stores and energy costs were the main contributors towards a higher
operating cost.
At Bambanani, cash costs increased from U.S.$502 per ounce in fiscal 2006 to U.S.$586 per
ounce in fiscal 2007, primarily as a result of higher labor costs as well as a lower recovery grade
due to underground fires during fiscal 2007.
At Doornkop, cash costs decreased from U.S.$558 per ounce in fiscal 2006 to U.S.$439 per ounce
in fiscal 2007. This increase was primarily attributable to the increase in production levels at
Doornkop.
Cash costs at Target increased from U.S.$346 per ounce in fiscal 2006 to U.S.$370 per ounce in
fiscal 2007. This resulted mainly from a lower recovery grade as well as an increase in cash costs
due to higher production levels and labor costs.
At Masimong, cash costs increased by 15% from U.S. U.S.$489 per ounce in fiscal 2006 to
U.S.$559 per ounce in fiscal 2007. This was due to higher labor costs as a result of the
implementation of Conops.
Cash costs at Evander operations increased by 19% from U.S.$403 per ounce in fiscal 2006 to
U.S.$481 per ounce in fiscal 2007. The decrease ca primarily be attributed to lower recovery grades
at Evander 7 and 8 shafts, grade dropped by 28% and 11% respectively.
At our Virginia operations, cash costs increased by 12% from U.S.$488 per ounce in fiscal 2006
to U.S.$546 per ounce in fiscal 2007. The increase was due to a combination of higher total cost as
well as lower recovery grade. Total cost increased by 9% from U.S.$135 million in fiscal 2006 to
U.S.$147 million in fiscal 2007. The recovery dropped by 9% during fiscal 2007, this was partly
attributable to the production at Harmony 2. Production at Harmony 2 was hampered by a fire in the
high grade basal pillar.
103
Under Other Underground, cash costs at Joel decreased from U.S.$498 per ounce in fiscal
2006 to U.S.$418 per ounce in fiscal 2007. This decrease was primarily attributable to higher
production as well as an improved recovery grade.
b) Depreciation and Amortization
Depreciation
and amortization charges decreased U.S.$32 million, or 23%, from U.S.$138 million
in fiscal 2006 to U.S.$106 million in fiscal 2007. This resulted mainly from decreased production.
c) Care and Maintenance Cost of Restructured Shafts
The charge for the care and maintenance cost of restructured shafts decreased from U.S.$22
million in fiscal 2006 to U.S.$8 million in fiscal 2007. This resulted from lower labor costs
relating to the termination of non-productive employees.
d) Employment Termination Costs
No charge was recorded for employment termination costs in fiscal 2007, a decrease from a
credit of U.S.$12 million in fiscal 2006. During fiscal 2006, we continued with the process of a
final restructuring process in the Free State region. This process was announced in fiscal 2005.
This affected the Free State, Freegold, ARMgold and Avgold operations.
e) Impairment of Assets
Impairment charges decreased from a net reversal of U.S.$30 million in fiscal 2006 to a net
reversal of U.S.$19 million in fiscal 2007. The amount in fiscal 2007 includes a U.S.$21 million
reversal of impairment related to the reversal at our surface operations (Kalgold) and other
underground operations. Offsetting this credit, is a impairment recorded at the Free State
Refinery, which is no longer in operation and the carrying value has been written down to U.S.$nil.
These reversals and impairments resulted from changes in the expected life of mines and operations.
The increase in gold price would have a positive impact on the recoverable amount, where an
increase in costs would have a negative one. Where the recoverable amount, exceeded the carrying
value, the impairments previously recognized where reversed. Where the carrying amount exceeded the
recoverable amount, the asset was impaired down to the recoverable amount. The amount for fiscal
2006 includes reversal of impairments at our Free State, Evander, Bambanani and other underground
operations. Offsetting this is an amount of U.S.$16.0 million for the impairment recorded at
Lydenburg Exploration Limited on amounts previously capitalized as undeveloped properties for which
no future financial benefits are expected by management.
Exploration expenditure
Exploration expenditure increased from U.S.$11 million in fiscal 2006 to U.S.$27 million in
fiscal 2007, primarily due to increased exploration activity in PNG (Wafi and Hidden Valley areas).
Other expenses net
Other expenses increased from a charge of U.S.$97 million in fiscal 2006 to a credit of
U.S.$25 million in fiscal 2007. Profit on sale of property, plant and equipment increased U.S.$15
million from U.S.$10 million in fiscal 2006 to U.S.$25 million in fiscal 2007. This was primarily
due to the profit on the sale of Randfontein 4 shaft and the Deelkraal surface assets, resulting in
profits of U.S.$10 million and U.S.$14 million respectively. Also contributing is the decrease in
losses on financial instruments from a charge of U.S.$81 million in fiscal 2006 to a credit of
U.S.$6 million in fiscal 2007.
Loss from Associates
Loss from associates was U.S.$3 million in fiscal 2007, compared to U.S.$17 million in fiscal
2006. The amount in fiscal 2007 relates to our attributable share of losses in Western Areas for
the six months from July 1, 2006 to December 8, 2006. The amount in fiscal 2006 relates to our
29.2% attributable share of losses in Western Areas for the three months from March 9, 2006 until
June 30, 2006.
Profit on Sale of Investment in Associate
A profit of U.S.$33 million was recognized in fiscal 2007 (U.S.$nil in fiscal 2006). This was as a
result of the disposal of our interest in Western Areas in exchange for Gold Fields shares.
(Loss)/Profit on Sale of Listed Investments
We recorded a loss of U.S.$5 million in fiscal 2007 as compared with a profit of U.S.$45
million on the sale of listed investments in fiscal 2006. The loss in fiscal 2007 arose when we
disposed of a portion of our interest in Gold Fields through various transactions.
104
In fiscal 2006, we disposed of our remaining investment in Gold Fields for U.S.$362 million
acquired in prior years. The process was concluded through market disposals which commenced on
November 10, 2005 and an open market offering on November 15 and 16, 2005. The investment was
acquired at a cost of U.S.$316 million, resulting in a gain of U.S.$45 million.
Investment Income
Investment income decreased from U.S.$31 million in fiscal 2006 to U.S.$27 million in fiscal
2007. This is due to interest received decreasing from U.S.$29 million in fiscal 2006 to U.S.$24.
million in fiscal 2007. This decrease was attributable primarily to the decrease in interest earned
on bank and call accounts due to lower average balances through the year. This was partially offset
by an increase in South African interest rates.
Finance costs
Finance costs were U.S.$65 million in fiscal 2007 compared to U.S.$62 million during fiscal
2006. This decrease was due to the lower average interest bearing debt balance during the year,
primarily as a result of the redemption of the senior uncollateralized fixed rate bonds during June
2006 as well as the capitalization of interest for qualifying assets under construction. This
decrease was offset primarily by an increase in interest paid on the U.S.$140 million RMB loan
raised to finance the acquisition of the stake in Western Areas in March 2006.
Income and Mining Taxes
South Africa. We pay taxes on mining income and non-mining income. The amount of our South
African mining income tax is calculated on the basis of a formula that takes into account our total
revenue and profits from, and capital expenditures for, mining operations in South Africa. 5% of
total mining revenue is exempt from taxation in South Africa as a result of the application of the
applicable gold mine formula. The amount of revenue subject to taxation is calculated by deducting
qualifying capital expenditures from taxable mining income. The amount by which the taxable mining
income exceeds 5% of mining revenue constitutes taxable mining income. We and our subsidiaries each
make our own calculation of taxable income.
The tax rate applicable to the mining and non-mining income of a gold mining company depends
on whether the company has elected to be exempt from the Secondary Tax on Companies, or STC. The
STC is a tax on dividends declared and, at present, the STC tax rate is equal to 10% (previously
12.5%). To the extent we receive dividends, such dividends received are offset against the amount
of dividends paid for purposes of calculating the amount subject to STC. In 1993, all existing
South African gold mining companies had the option to elect to be exempt from STC. If the election
was made, a higher tax rate would apply for both mining and non-mining taxable income. In 2007, the
tax rates for companies that elected the STC exemption were 45% for mining income and 37% for
non-mining income, compared with 35% for mining income and 29% for non-mining income if the STC
exemption election was not made. In 2006, the tax rates were the same to that in 2007. In 1993, we
elected to pay the STC tax. All of our South African subsidiaries, excluding Avgold, elected the
STC exemption.
|
|
|
|
|
|
|
|
|
Income and Mining Tax |
|
2007 |
|
2006 |
Effective tax rate (expense)/benefit |
|
|
(25 |
)% |
|
|
24 |
% |
The effective tax rate for fiscal 2007 was lower than the statutory tax rate of 45% for us and
our subsidiaries as a whole. The most significant reason for the decrease in the effective tax rate
in fiscal 2007 relates to the non taxable income received by way of the profit realized on the
disposal of the investment held in Western Areas. Offsetting this amount is an increase in the
difference between the South African mining formula tax rate and the maximum mining statutory rate
on mining income. Contributing to the tax expense for fiscal 2007 are non-deductible expenses of
U.S.$8 million.
PNG. We are in the process of developing the Hidden Valley Project in PNG. We are also
reviewing other potential projects and carrying out extensive exploration.
PNG mining projects are taxed on a project basis. Therefore each project is taxed as a
separate entity, even though it may be one of a number of projects carried on by the same company.
In certain circumstances there is an ability to transfer the tax benefit obtained through
exploration expenditure between projects and wholly owned companies. Tax losses are generally
quarantined and cannot be transferred between projects.
PNG mining companies are taxed at a rate of tax of 30%.
105
Capital development and exploration expenditure incurred in PNG is capitalised for tax
purposes and can be generally deducted at 25% per annum on a diminishing value basis against
project income.
PNG imposes dividend withholding tax of 10% on dividends paid by PNG mining operations to non
residents. Although PNG also imposes interest withholding tax on interest off shore, PNG mining
operations may qualify for an exemption.
Discontinued operations
Revenue
Revenue increased by U.S.$45 million in fiscal 2007 from U.S.$327 million in fiscal 2006 to
U.S.$372 million as a result of a higher average gold price received.
Costs
Costs decreased in fiscal 2007 from U.S.$185.3 million in fiscal 2007 to U.S.$148.4 million. This
was primarily due to the decrease in losses from derivative instruments from U.S.$78.8 million in
fiscal 2006 to U.S.$4.6 million in fiscal 2007. This was offset by an increase of U.S.$19.5 million
in the depreciation charge in fiscal 2007 due to a reduction in reserves as well as an increase in
cash operating cost of U.S.$17.5 million.
Impairment of assets
During fiscal 2007, an impairment of assets (U.S.$56 million) was recorded on the Australian
operations on classification as held for sale.
Taxation
South Africa. We pay taxes on mining income and non-mining income. For a discussion on the
detail, see Income and mining taxation under the Continuing Operations section.
In 2007, the tax rates for companies that elected the STC exemption were 45% for mining income
and 37% for non-mining income, compared with 35% for mining income and 29% for non-mining income if
the STC exemption election was not made. In 2006, the tax rates were the same to that in 2007. In
1993, we elected to pay the STC tax. All of our South African subsidiaries, excluding Avgold,
elected the STC exemption.
Australia. Generally, Australia imposes tax on the worldwide income (including capital gains)
of all of our Australian incorporated and tax resident entities. The current income tax rate for
companies is 30%. Ongoing business, mining, exploration and rehabilitation costs incurred each year
are fully deductible. The cost of plant and capital mining expenditure may be depreciated and
deducted over its effective life.
The Australian legislature has introduced a Tax Consolidations Regime, under which from July
1, 2003, Harmony Gold Australia Proprietary Limited and its wholly owned Australian subsidiary
companies are recognised and taxed as a single entity. Under the consolidations rules all of the
Australian subsidiary companies are treated as divisions of Harmony Gold Australia. As a result all
inter company transactions between group members are ignored for tax purposes. This allows the
group to transfer assets between group members without any tax consequences, and to utilize all tax
losses incurred by each company in the group.
Mining operations (other than operations on freehold land) are also subject to a 2.5% gold
royalty because the mineral rights are owned by the state. All gold production from the Mt. Magnet
operations is subject to this royalty. Most of the production from the South Kalgoorlie operations
is from freehold land and is, accordingly, exempt from this royalty.
Withholding tax is payable on dividends, interest and royalties paid by Australian residents
to non-residents, which would include any dividends on the shares of our Australian subsidiaries
paid to us. In the case of dividend payments to non-residents, a 30% withholding tax applies.
However, where the recipient of the dividend is a resident of a country with which Australia has
concluded a double taxation agreement, the rate of withholding tax is generally limited to 15% (or
10% where the dividend is paid to a companys parent
company). Where dividends are fully franked, an effective credit is allowed against any withholding
tax otherwise payable, regardless of whether a double taxation agreement is in place.
Continuing and discontinued operations
Net Profit/(Loss)
Net profit was U.S.$51 million in fiscal 2007 compared with the loss of U.S.$91 million in
fiscal 2006. This decrease is attributed primarily to the factors described above.
106
Recent Accounting Pronouncements
In April 2007, the IASB issued IFRS 3 (Revised) Business Combinations and IAS 27 (Amended)
Consolidated and Separate Financial Statements, effective for the annual periods commencing after
July 1, 2009. The changes made to IFRS 3 and IAS 27 have the following effects: ( a) Partial
acquisitions on non-controlling interest are measured either as their proportionate interest in the
net identifiable assets or at fair value; (b) Goodwill is measured as the difference at acquisition
date between the fair value of any investment in the business held before the acquisition, the
consideration transferred and the net assets acquired for step acquisitions; (c )
Acquisition-related costs are generally recognised as expenses instead of included in goodwill; (d)
Contingent consideration must be recognised and measured at fair value at the acquisition date.
Subsequent changes in fair value are recognised in accordance with other IFRSs, usually in profit
and loss, rather than adjusting goodwill; (e) for transactions with non-controlling interests, the
changes in a parents ownership in a subsidiary that do not result in the loss of control are
accounted for as equity transactions. The effect of the revised IFRS 3 and amended IAS 27 will be
recorded in future periods when such transactions are entered into.
In June 2007, the International Financial Reporting Interpretation Committee (IFRIC) issued
interpretation 14 IAS 19 , The Limit on a Defined Asset Minimum Funding Requirements and their
Interaction. IFRIC 14 addresses three issues: (a) how to determine the limit placed by IAS 19
Employee Benefits on the amount of a surplus in a pension plan they can recognise an asset; (b) how
a minimum funding requirement affects that limit; ( c) and when the minimum funding requirement
creates an onerous obligation that should be recognised as a liability in addition to that
otherwise recognised under IAS 19. IFRIC 14 requires that an asset be recognised in relation to the
surplus on a consistent basis; and where there is both a strong minimum funding requirement and
restrictions over the amount, an entity can recover from the plan, either as refunds or a reduction
in contribution; entities have to recognise an additional liability. The interpretation is
effective for annual periods commencing on or after January 1, 2008. IFRIC 14 will not affect our
annual report as we only have defined contributions pension plans.
In September 2007, the IASB issued IAS 1 (Revised) Presentation of Financial Statements.
The statement was issued with the aim to aggregate information in the financial statements on a
basis of common characteristics, which resulted in the changes in equity to be presented separately
between those changes resulting from transactions with equity participants (owners), in their
capacity as owners, and those other non-owner equity transactions. The revised standard allows for
a statement of other comprehensive income, with the net income recognized directly in equity now
being moved to the statement of other comprehensive income, with the statement of changes in equity
reflecting a line item, total comprehensive income. The change is effective for annual periods
commencing on or after January 1, 2009. We have early adopted the disclosure requirements of IAS 1,
effective for the year ending June 30, 2008.
In November 2007, the IASB issued IFRS 8 Operating Segments. The statement was issued with
the aim to achieve convergence in accounting standards around the world. The IASB and the FASB
after review of the FASB statement 131 Disclosures about Segments of an Enterprise and Related
Information and IAS 14 Segment reporting collaborated and issued the new IFRS 8 Operating Segment.
IFRS 8 requires that an entity report on the financial and descriptive information about its
reportable segments. IFRS 8 requires that a measure of the operating profit or loss, the segment
assets and liabilities be reported. A reconciliation of total segments` reportable revenues, total
profit or loss, total assets, liabilities and other amounts disclosed for reportable segments to
corresponding amounts in the entitys annual financial statements should be reported. IFRS 8 also
requires entities to report on information about revenues derived from its products or services,
about countries in which they earn revenues and hold assets and the major customers. In addition, a
description of how each segment was determined, the products and services provided per segment and
any differences in determining the segment`s information.
Although IFRS 8 is effective for annual periods
commencing on or after January 1, 2009, we have decided to early adopt the standard from the year
ending June 30, 2008.
In December 2007, the IASB issued IFRS 2 (Amended) Share Based Payment on vesting conditions
and cancellations. The amendment deals with two matters: (a) it clarifies that vesting conditions
are service conditions and performance conditions only; (b) It specifies all cancellations, whether
by the entity or by other parties, should receive the same accounting treatment. IFRS 2 becomes
effective for annual periods commencing on or after January 1, 2009, early adoption is permitted.
The effect of the amended IFRS 2 will be recorded in future periods when such transactions
affecting vesting conditions and cancellations on share based payment occurs.
In January 2008, the IASB issued IAS 23 (Revised) Borrowing Costs. The statement eliminates
the choice regarding capitalization of borrowing costs. Where an asset is acquired, constructed or
produced as a qualifying asset, it has to capitalize the borrowing costs relating to the asset
against the cost price of the asset. All other borrowing costs are expensed. Excluded from the
amended statement are inventories that are manufactured, or otherwise produced in large quantities
on a repetitive basis; and qualifying asset measured at fair value. The
107
statement comes into effect for annual periods commencing on or after January 1, 2009. We have
early adopted the revised IAS 23 and the disclosures in this regard are included in our financial
statements.
In February 2008, the IASB issued amendments to IAS 32- Financial Instruments: Presentation
and IAS 1 Presentation of Financial Statements, the amendment aims to improve the accounting for
particular types of financial instruments that have characteristics similar to ordinary shares but
are at present classified as financial liabilities. IAS 32 requires a financial instrument to be
classified as a liability if the holder of that instrument can require the issuer to redeem it for
cash; currently these financial instruments are considered liabilities, rather than equity. The
amendments to IAS 32 addresses this issue and require entities to classify the following types of
financial instruments as equity, provided they have particular features and meet specific
conditions: (a) puttable financial instruments; (b) instruments, or components of instruments, that
impose on the entity an obligation to deliver to another party a pro rata share of the net assets
of the entity only on liquidation. The amendments become effective for annual periods commencing on
or after January 1, 2009 early application is permitted. We do not expect the adoption of these amendments to have an impact on our
consolidated financial statements.
In May 2008,IFRIC issued interpretation No.16, Hedges of a Net Investment in a Foreign
Operation (IFRIC 16),which provides guidance on: (a) identifying the foreign currency risks that
qualify as a hedged risk in the hedge of a net investment in a foreign operation; (b) where,
within a group, hedging instruments that are hedges of a net investment in foreign operation can be
held to qualify for hedge accounting; ( c) and how an entity should determine the amounts to be
reclassified from equity to profit or loss for both the hedging instrument and the hedged item.
IFRIC 16 applies to entities that hedges on foreign currency risk arising from net investments in
foreign operations and where the related hedge qualify for hedge accounting in accordance with IAS
39, Financial Instruments: Recognition and Measurement. The provisions of IFRIC 16 are effective
for annual periods commencing on or after October 1, 2008, the effect of the change will be
accounted for prospectively in future periods. We currently do not anticipate the change affecting
our financial statements as we do not have hedges on our net investments in foreign operations.
In May 2008 the IAS issued IFRS 1(Amended) First-time Adoption of International Financial
Reporting Standards and IAS 27 (Amended) Consolidated and Separate Financial Statement Cost of
an investment in Subsidiary, Jointly Controlled Entity or Associate. The amendments to IFRS 1 allow
first-time adopters, in their separate financial statements, to use a deemed cost option for
determining the cost (in terms of IAS 27, paragraph 38(a)) of an investment in subsidiary, jointly
controlled entity or associate. The deemed cost of such an investment shall be: (a) Fair value
(determined in accordance with IAS 39 Financial Instruments: Recognition and Measurement) at the
entitys date of transition to IFRSs; or (b) previous GAAP carrying amount at that date. The
amendments to IAS 27 remove the definition of the cost method from paragraph 4 of the standard.
In addition, when an entity reorganizes the structure of its group by establishing a new entity as
its parent ( subject to certain criteria), the amendments require the new parent to measure cost as
the carrying amount of its share of the equity items shown in the separate financial statements of
the original parent at the date of the reorganization. The standard becomes effective for annual
periods commencing on or after January 1, 2009, early adoption is permitted. The effect of the
amended IFRS 1 and IAS 27 will be recorded in future periods when such transactions are entered
into.
Liquidity and Capital Resources
We centrally manage our funding and treasury policies. There are no legal or economic
restrictions on the ability of our subsidiaries to transfer funds to us. We have generally funded
our operations and our short-term and long-term liquidity requirements from (i) cash generated from
operations, (ii) credit facilities and other borrowings and (iii) sales of equity securities.
Cash Resources
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
|
($ in millions) |
Continuing operations |
|
|
|
|
|
|
|
|
|
|
|
|
Operating cash flows |
|
|
165 |
|
|
|
176 |
|
|
|
38 |
|
Investing cash flows |
|
|
(313 |
) |
|
|
(318 |
) |
|
|
(291 |
) |
Financing cash flows |
|
|
78 |
|
|
|
132 |
|
|
|
8 |
|
Foreign exchange differences |
|
|
5 |
|
|
|
6 |
|
|
|
42 |
|
Total cash flows from continuing operations |
|
|
(65 |
) |
|
|
(4 |
) |
|
|
(203 |
) |
108
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal year ended June 30, |
|
|
2008 |
|
2007 |
|
2006 |
|
|
($ in millions) |
Discontinued
operations |
|
|
|
|
|
|
|
|
|
|
|
|
Operating cash flows |
|
|
71 |
|
|
|
(17 |
) |
|
|
17 |
|
Investing cash flows |
|
|
(16 |
) |
|
|
|
|
|
|
41 |
|
Financing cash flows |
|
|
|
|
|
|
|
|
|
|
(25 |
) |
Foreign exchange differences |
|
|
(7 |
) |
|
|
|
|
|
|
(6 |
) |
Total cash flows from discontinued operations |
|
|
48 |
|
|
|
(17 |
) |
|
|
27 |
|
Operations
Net cash provided by operations is primarily affected by the quantities of gold sold, the gold
price, the Rand-U.S. dollar exchange rate, cash costs per ounce and, in the case of the
International operations, the Australian dollar and Kina versus U.S. dollar exchange rate. A
significant adverse change in one or more of these parameters could materially reduce cash provided
by operations as a source of liquidity.
Net cash generated by operations was U.S.$236 million in fiscal 2008, as compared with
U.S.$159 million in fiscal 2007. This improvement is attributable primarily to the higher gold
price received during the year as well as the increase in interest received of U.S.$13 million.
Negating the effect of the improvement was the increase in interest paid of U.S.$26 million and
taxation paid of U.S.$16 million. An increase in the production costs of U.S.$82 million due to
inflationary pressures relating to labor, materials and energy supplies also negatively affected
the increase.
Net cash generated by operations was U.S.$159 million in fiscal 2007, as compared with U.S.$55
million in fiscal 2006. This improvement is attributable primarily to the higher gold price
received during the year. Contributing to the improvement was the decrease in the working capital
charges of U.S.$39 million. Negating the effect of the improvement was the decrease in interest
received of U.S.$8 million.
Investing
Net cash utilized by investing activities was U.S.$329 million in fiscal 2008, as compared
with U.S.$318 million in fiscal 2007. This increase was mainly due to the increase in capital
expenditure during fiscal 2008 by U.S.$169 million to U.S.$552 million. An increase of U.S.$129
million in fiscal 2008 from proceeds on disposal of listed investments offset the increase in cash
utilized during fiscal 2008. Also offsetting the amounts was an increase in proceeds on disposal of
mining assets, including the disposal of South Kalgoorlie (U.S.$9 million) and a increase in the
restricted cash balance (U.S.$32 million).
Net cash utilized by investing activities was U.S.$318 million in fiscal 2007, as compared
with U.S.$250 million in fiscal 2006. During fiscal 2006 capital expenditure increased by U.S.$108
million to U.S.$383 million, which decreased the cash generated from investing activities.
Financing
Net cash generated by financing activities was U.S.$78 million in fiscal 2008, as compared
with U.S.$132 million in fiscal 2007. This decrease was mainly due to the fact that we raised less
borrowings during the year.
Net cash generated by financing activities was U.S.$132 million in fiscal 2007, as compared
with the net cash utilized was U.S.$17 million in fiscal 2006. This increase was mainly due to the
raising of borrowings during the year as well as the decrease in repayment of borrowings.
Outstanding Credit Facilities and Other Borrowings
On July 30, 2003, Africa Vanguard Resources (Doornkop) (Proprietary) Limited (AVR) entered
into a term loan facility of R140 million (U.S.$19 million) with Nedbank Limited (Nedbank) for
the purpose of partially funding AVRs purchase of an undivided 26% share of the Mining titles, to
be contributed to the Doornkop South Reef Project with Randfontein. Interest at a fixed rate equal
to Johannesburg Interbank Agreed Rate (JIBAR) plus 2%, compounded monthly, and any stamp duties
and holding costs. The loan matures on July 30, 2008, at which date all loan amounts and any
interest accrued are to be paid. The loan is jointly and severally guaranteed by the Company and
several of its subsidiaries. The facility from Nedbank to AVRD is guaranteed by us and certain of
our subsidiaries. Interest capitalized during the fiscal 2008 was U.S.$4.1 million compared to
U.S.$2.2 million in fiscal 2007 (fiscal 2006 was U.S.$2.3 million). During fiscal 2005, Africa
Vanguard
109
borrowed an additional R18 million (U.S.$2.8 million) from its holding company Africa
Vanguard Resources to service working capital commitments. The loan is uncollateralized and interest free.
As there are no fixed repayment terms, the loan has no fixed maturity date.
On May 21, 2004, we issued R1.7 billion (U.S.$252.0 million) in international unsecured
fixed-rate convertible bonds in order to refinance our domestic Rand debt. We pay interest on the
convertible bonds of 4.875% per annum, payable semi-annually in arrears on May 21 and November 21
of each year. The bonds are convertible at the option of the bondholders into fully paid up
ordinary shares at any time on or after July 1, 2004 and up to, and including, May 15, 2009, unless
they have been previously redeemed, converted or purchased and cancelled by us. The trust deed for
the convertible bonds contains clauses that restrict certain of our activities, including a
negative pledge, according to which we will not create or permit any mortgage, charge, lien, pledge
or other form of encumbrance of security interest with respect to any part of our undertaking or
assets, present or future, to secure any relevant debt, guarantee or indemnity. In addition, the
trust deed contains covenants that require us to, among other things, maintain the listing of the
bonds with the UK Listing Authority and to all things necessary, in the opinion of the trustee, to
give effect to the trust deed. Including in the amortization charge as per the income statement is
U.S.$1.2 million compared to U.S.$1.2 million in 2007 and U.S.$1.4 million in 2006 for amortization
of the bond issue costs.
During July 2007, Morobe Consolidated Goldfields entered into a finance lease agreement with
Westpac Bank for the purchase of mining fleet to be used on the Hidden Valley project amounting to
U.S.$37 million. Interest is charged at U.S. LIBOR plus 1.25% per annum. Interest is accrued
monthly and lease instalments are repayable quarterly terminating June 30, 2013. The mining fleet
financed is used as collateral for these loans. The balance at June 30, 2008 was U.S. $33 million.
On September 28, 2007, we entered into a term loan facility of R2 billion (U.S.$283.9 million)
with Nedbank Limited, for the purpose of partially funding capital expenditure in respect of
projects, as well as to repay the short term bridging loan amounting to R500 million (U.S.$68.6
million). Interest accrues on a day to day basis over the term of the loan at a variable interest
rate, which is fixed for three month periods, equal to the JIBAR plus 2.75% plus banking costs. The
loan is repayable on December 29, 2008 and interest is repayable every quarter commencing on
September 28, 2007.
Recently Retired Credit Facilities and Other Borrowings
On April 15, 2005 the ARM Empowerment Trust entered into a term loan facility of R474 million
(U.S.$75.4 million) with Nedbank Limited for the purpose of funding the balance of the ARM
Empowerment Trusts acquisition of the ARM shares held by us. The loan bore interest, compounded
monthly, at a rate of JIBAR plus of 1.5%. We guaranteed this loan, subject to a maximum guaranteed
amount of R367.4 million (U.S.$50.4 million) plus interest. In addition, if the ARM Empowerment
Trust chose to dispose of 8,175,640 of its ARM Limited shares at cost, the maximum guaranteed
amount would be reduced to R214.9 million (U.S.$29.5 million) plus interest. We also entered into
an indemnity agreement with ARM Limited, pursuant to which ARM Limited indemnified us against 50%
of all claims under the guarantee, subject to a maximum of R107.4 million (U.S.$14.7 million) plus
interest thereon at the applicable rate from May 26, 2006. Interest capitalized during the year
ended 2008 amounted to U.S.$2.5 million, compared to U.S.$8.5 million for fiscal 2007. On September
28, 2007, the guarantee was cancelled by Nedbank and, consequently, we have no further obligation
to Nedbank in this regard.
On April 15, 2005, the ARM Empowerment Trust entered into a second term loan facility of R356
million (U.S.$56.7 million) with Nedbank Limited for the purpose of funding the ARM Empowerment
Trusts partial acquisition of the ARM shares held by us. The loan bore interest, compounded
monthly, at a rate of JIBAR plus 1.5%. Interest capitalized during the year ended 2008 amounted to
U.S.$2.1 million, compared to U.S.$6.7 million for fiscal 2007. On September 28, 2007, the
guarantee was cancelled by Nedbank and consequently we have no further obligation to Nedbank in
this regard.
On March 20, 2007, we arranged financing from RMB, collateralized by 5,747,000 shares in Gold
Fields, resulting in total cash proceeds of R750.3 million (U.S.$103.4 million). Of these proceeds,
R599.8 million (U.S.$82.3 million) were applied towards partial repayment of the R1.0 billion term
loan facility with RMB. See below in this section. Interest was payable at a rate equal to the
SAFEX Financial Derivatives overnight deposit rate (the Safex Overnight Rate) plus 35 basis
points. On August 24, 2007, we repaid the loan.
110
On March 20, 2007, Randfontein (our wholly-owned subsidiary) entered into a preference share
subscription agreement with RMB. According to the terms of the agreement, following the
satisfaction of certain conditions, Randfontein issued R550.0 million (U.S.$75.4 million) principal amount of preference shares to RMB
on April 5, 2007. Dividends on the preference shares were payable semi-annually on the principal
amount and were calculated at 35% of the South African Prime Interest Rate from the issue date
until August 31, 2007, 50% of the South African Prime Interest Rate from September 1, 2007 to
February 29, 2008 and 83% of the South African Prime Interest Rate thereafter. The preference
shares were guaranteed by us, Evander Gold Mines Limited, ARMgold/Harmony Freegold Joint Venture
Company (Pty) Limited, Avgold Limited and ARMgold/Harmony Joint Investment Company (Pty) Limited
(AHJIC), as well as certain future material subsidiaries.
In the subscription agreement for the preference shares, AHJIC also granted a security
interest over 6,196,863 Gold Fields shares held by it to secure its obligations under the
subscription agreement for the preference shares. In the subscription agreement for the preference
shares, AHJIC also undertook that, if the cover ratio of the value of the Gold Fields shares to the
redemption amount falls below 1.25, it would deposit additional Gold Fields shares or cash to bring
this ratio to 1.5. On or after March 1, 2008, if this ratio falls below 2.0, AHJIC will be required
to deposit cash equal to 75% of the redemption amount.
The preference shares were redeemable at the option of the holders on the final redemption
date, which is three years and one day after the issue date, and upon the occurrence of certain
events, including a failure by AHJIC to meet its obligations under the subscription agreement, a
delisting of the Gold Fields shares from the Johannesburg Stock Exchange, cross-defaults or other
events that are customary events of default for financing agreements. The preference shares were
also redeemable by Randfontein at any time. On August 24, 2007, the preference shares were
redeemed.
On June 29, 2007, we entered into a senior bridge loan facility for R500.0 million (U.S.$68.6
million) with RMB for the purpose of funding our capital expenditure requirements in respect to the
Hidden Valley mine project. The loan bore interest, compounded monthly at a rate equal to the Safex
Overnight Rate plus 2.4% until July 31, 2007, the maturity date. In the event that we elected to
extend the loan facility until September 30, 2007, the loan would bear interest at a rate equal to
the Safex Overnight Rate plus 3.6% during the extension period. On September 29, 2007, the loan was
settled in full.
On June 27, 2007, we entered into a draw down facility agreement with Westpac Bank for the PNG
operations. The limit was K3 million and interest was payable at 9.45%. During July 2007, the
facility was repaid and then cancelled.
On March 9, 2006, we entered into a term loan facility of R1.0 billion
(U.S.$159.7 million) with RMB, for the purpose of partially funding the acquisition of the 29.2%
stake in Western Areas. Interest is compounded at a rate equal to three-month JIBAR plus 1.5%. This
facility was partially repaid on March 27, 2007 from the net proceeds of a sale of Gold Fields
shares, and the balance was repaid on April 4, 2007 from the net proceeds from the issuance of
certain preference shares by our subsidiary Randfontein.
Contractual Obligations and Commercial Commitments
Our contractual obligations and commercial commitments consist primarily of credit
facilities, post-retirement healthcare and environmental obligations
Contractual Obligations on the Balance Sheet
The following table summarizes our contractual obligations as of June 30, 2008:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Payments Due by Period |
|
|
|
|
|
|
Less Than |
|
12-36 |
|
36-60 |
|
After 60 |
|
|
|
|
|
|
12 Months |
|
Months |
|
Months |
|
Months |
|
|
|
|
|
|
July 1, 2008 |
|
July 1, 2009 |
|
July 1, 2011 |
|
Subsequent |
|
|
|
|
|
|
to June 30, |
|
to June 30, |
|
To June 30, |
|
June 30, |
|
|
Total |
|
2009 |
|
2011 |
|
2013 |
|
2013 |
|
|
($million) |
|
($million) |
|
($million) |
|
($million) |
|
($million) |
Convertible uncollaterized bonds(1) |
|
|
229 |
|
|
|
229 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Africa Vanguard Resources(1) |
|
|
4 |
|
|
|
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nedbank AVR(1) |
|
|
25 |
|
|
|
25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Westpac Bank(1) |
|
|
33 |
|
|
|
4 |
|
|
|
6 |
|
|
|
23 |
|
|
|
|
|
Nedbank(1) |
|
|
256 |
|
|
|
256 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Post retirement health care(2) |
|
|
16 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
|
Environmental obligations(3) |
|
|
145 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
145 |
|
Total contractual obligations |
|
|
708 |
|
|
|
518 |
|
|
|
6 |
|
|
|
23 |
|
|
|
161 |
|
|
|
|
(1) |
|
See Item 5. Operating and Financial Review and Prospects Liquidity and Capital Resources Credit Facilities and Other Borrowings
Outstanding Credit Facilities and Other Borrowings. |
|
(2) |
|
This liability relates to post-retirement medical benefits of former employees who retired prior to December 31, 1996 and is based on
actuarial valuations conducted during fiscal 2008. |
|
(3) |
|
We make provision for environmental rehabilitation costs and related liabilities based on managements interpretations of current
environmental and regulatory requirements. See Item 5. Operating and Financial Review and Prospects Critical Accounting Policies. |
111
Contractual Obligations off the Balance Sheet
Our obligation with regards to operating leases is less than U.S.$1 million for the next
year and relates to the International office in Brisbane.
Capital Expenditure
The following table sets forth our authorized capital expenditure as of June 30, 2008:
|
|
|
|
|
|
|
$million |
Authorized and contracted for |
|
|
149 |
|
Authorized but not yet contracted for |
|
|
221 |
|
Total |
|
|
370 |
|
Commercial Commitments
The following table provides details regarding our commercial commitments as of June 30, 2008:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Amount of Commitments Expiring by Period |
|
|
|
|
|
|
Less |
|
|
|
|
|
|
|
|
|
|
|
|
Than 12 |
|
12-36 |
|
36-60 |
|
|
|
|
|
|
|
|
Months |
|
Months |
|
Months |
|
After 60 |
|
|
|
|
|
|
July 1, |
|
July 1, |
|
July 1, |
|
Months |
|
|
|
|
|
|
2008 to |
|
2009 to |
|
2011 to |
|
Subsequent |
|
|
|
|
|
|
June 30, |
|
June 30, |
|
June 30, |
|
to June 30, |
|
|
Total |
|
2009 |
|
2011 |
|
2013 |
|
2013 |
|
|
($million) |
|
($million) |
|
($million) |
|
($million) |
|
($million) |
Guarantees(1) |
|
|
24 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24 |
|
Capital commitments(2) |
|
|
149 |
|
|
|
149 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Total commitments expiring by period |
|
|
173 |
|
|
|
149 |
|
|
|
|
|
|
|
|
|
|
|
24 |
|
|
|
|
(1) |
|
Amount of Commitments Expiring by Period. |
|
(2) |
|
Capital commitments consist only of amounts committed to
external suppliers, although a total of U.S.$380 million
has been approved by the Board for capital expenditures. |
Trend Information
Information on recent trends in our operations is discussed in Item 4. Information on
the Company Business Strategy and Results of Operations above.
Working Capital and Anticipated Financing Needs
The Board believes that our working capital resources, by way of cash generated from
operations and existing cash on hand, are sufficient to meet our present working capital needs.
Several of the Growth projects will require a great deal of capital expenditure over the next two
to
112
three
years, and given the current cash position, we are re-evaluating the planned capital expenditure, together with project timelines.
Additional funding options are being investigated, including debt raising and the disposal of
certain assets. Should a decision be taken to reduce or cease capital expenditure on one or more
of the projects, the effect would be to delay the start of production, and therefore the associated
revenue stream. This could have an impact on available cash resources. For more information on our
planned capital expenditures, see Capital Expenditures above and Item 4. Information on the
Company Business Harmonys Mining Operations. We may, in the future, explore debt and/or
equity financing in connection with our acquisition strategy and/or major capital projects. See
Item 3. Key Information Risk Factors Harmonys strategy depends on its ability to make
additional acquisitions. Our Board believes that we will have access to adequate financing on
reasonable terms given our cash-based operations and modest leverage. Our ability to generate cash
from operations could, however, be materially adversely affected by increases in cash costs,
decreases in production, decreases in the price of gold and appreciation of the Rand against the
U.S. dollar. Access to financing could also be limited by provisions of our corporate bonds, under
which we may not permit encumbrances on our present or future assets or revenues to secure
indebtedness for borrowed money, without securing the outstanding bonds equally and ratably with
such indebtedness, except for certain specified permitted encumbrances. See Item 5. Operating and
Financial Review and Prospects Liquidity and Capital Resources Credit Facilities and Other
Borrowings Outstanding Credit Facilities and Other Borrowings. Future financing arrangements
would also be subject to the limits on the Boards borrowing powers described in Item 10.
Description of Ordinary Shares Memorandum and Articles of Association Directors Borrowing
Powers. In addition, South African companies are subject to significant exchange control
limitations, which may impair our ability to fund overseas operations or guarantee credit
facilities entered into by overseas subsidiaries. See Item 10. Additional Information Exchange
Controls and Other Limitations Affecting Security Holders.
Other Financial Information
Export Sales
In fiscal years 2007 and 2008, 100% of our gold produced in South Africa was refined by
Rand Refinery, which is owned by a consortium of the major gold producers in South Africa. In
fiscal 2006 approximately 84% of our gold produced in South Africa was refined by us with the
balance refined at the Rand Refinery. All of our gold produced in Australia in fiscal 2008, 2007
and 2006 was sold to AGR Matthey, a Perth-based refinery.
113
Item 6. DIRECTORS, SENIOR MANAGEMENT AND EMPLOYEES
Directors and Senior Management
The members of the Board, their principal past affiliations, information on their
business experiences and principal outside activities and selected other information are set forth
below:
Board of directors
|
|
|
|
|
Name |
|
Date of appointment |
|
Date of resignation |
Patrice Motsepe (1)
|
|
September 23, 2003
|
|
By rotation or resignation |
Bernard Swanepoel
|
|
May 16, 1995
|
|
Resigned on August 6, 2007 |
Frank Abbott (2)
|
|
October 1, 1994
|
|
By rotation or resignation |
Graham Briggs
|
|
August 6, 2007
|
|
By rotation or resignation |
Joaquim Chissano (1) (3)
|
|
April 20, 2005
|
|
By rotation or resignation |
Fikile De Buck(1) (3)
|
|
March 30, 2006
|
|
By rotation or resignation |
Ken Dicks (1) (3)
|
|
February 13, 2008
|
|
By rotation or resignation |
Cheick Diarra (1) (3)
|
|
March 5, 2008
|
|
By rotation or resignation |
Dr Simo Lushaba (1) (3)
|
|
October 18, 2002
|
|
By rotation or resignation |
Cathie Markus (1) (3)
|
|
May 1, 2007
|
|
By rotation or resignation |
Modise Motloba (1) (3)
|
|
July 30, 2004
|
|
By rotation or resignation |
Nomfundo Qangule
|
|
July 26, 2004
|
|
Resigned on August 21, 2007 |
Cedric Savage (1) (3)
|
|
September 23, 2003
|
|
By rotation or resignation |
André Wilkens (1)
|
|
August 6, 2007
|
|
By rotation or resignation |
|
|
|
(1) |
|
Non-executive directors |
|
(2) |
|
Frank Abbott served as a non-executive director until August 20, 2007 and
was appointed interim financial director on August 21, 2007. |
|
(3) |
|
Independent |
Non-Executive Chairman
Patrice Motsepe (46) BA (Legal), LLB. Patrice was appointed to the board in 2003. Patrice was
a partner in one of the largest law firms in South Africa, Bowman Gilfillan Inc. He was a visiting
attorney in the USA with the law firm, McGuire Woods Battle and Boothe. In 1994 he founded Future
Mining, which grew rapidly to become a successful contract mining company. He then formed ARMgold
in 1997, which listed on the JSE in 2002. ARMgold merged with Harmony in 2003 and
this ultimately led to the takeover of Anglovaal Mining (Avmin) by ARM. In 2002 he was voted South
Africas Business Leader of the Year by the CEOs of the top 100 companies in South Africa. In the
same year, he was winner of the Ernst & Young Best Entrepreneur of the Year Award. He is also the
Executive Chairman of ARM Limited and the Deputy Chairman of Sanlam. His various business
responsibilities included being President of Business Unity South Africa (BUSA) from January 2004
to May 2008, which is the voice of organised business in South Africa. He is also President of
Mamelodi Sundowns Football Club.
Executive Directors
Graham Briggs (55), BSc (Hons) (Geology), PrSciNat Chief Executive. Graham was appointed to
the board in August 2007. Graham has 36 years experience in the mining industry. He joined Harmony
as New Business Manager in 1995 and was promoted to Chief Executive Officer of Harmony Australia
and Regional Manager for Australasia from 2005 to 2007. He was appointed Acting Chief Executive
Officer in August 2007 and in January 2008 appointed as Chief Executive Officer in January 2008. He
began his career in geology as a field assistant in 1972 and was exposed to various exploration
projects. Before attending university, Graham spent most of his time on gold exploration in the
Free State, South Africa. While at Gengold he spent time on various mines in South Africa including
Buffelsfontein, West Rand Consolidated, Grootvlei and ending as an ore reserve manager at Beatrix.
Graham serves as a director of Harmonys subsidiaries.
114
Frank Abbott (53), BCom, CA (SA), MBL Interim Financial Director. Frank was appointed an
executive director in August 2007. Frank joined the Harmony board as a non-executive director in
1994, after which he was appointed as financial director of the company in 1997. Following the ARM
Limited/ARMI transaction, it was agreed by the board that Frank be appointed financial director of
ARM while remaining on Harmonys board as a non-executive director. In August 2007, Frank was
seconded to Harmony as interim financial director. Frank serves as a director of Harmonys
subsidiaries and is a non-executive director of ARM Limited.
Non-Executive Directors
Joaquim
Chissano (68) independent non-executive Director. Joaquim
was appointed to Harmonys Board in April 2005. Joaquim is the
former president of Mozambique. He has served Mozambique in many
capacities, initially as founding member of the Frelimo movement
during that countrys struggle for independence. Subsequent to
independence in 1975, he was appointed foreign minister, and on the
death of Samora Machel, assumed the office of the President. Frelimo
contested and won the multi-party elections in 1994 and 1999,
returning Joaquim to presidency on both occasions. He declined to
stand for a further term of office in 2004. His presidency commenced
during a devastating civil war and ended with a sustainable peace and
important economic growth. He served a term as chairman of the
African Union from 2003 to 2004. Mr. Chissano is also a non-executive
director of ARM Limited and TEAL.
Fikile De Buck (48), BA (Economics), FCCA (UK) Independent non-executive director. Fikile
joined the board on 1 April 2006. A certified chartered accountant, she is a fellow of the
Association of Chartered Certified Accountants (ACCA) (UK) and a member of the Association of
Chartered Certified Accountants (ACCA) (UK). In 1990, Fikile won the Stuart Crystal Prize, awarded
to the best accounting student at the Birmingham Polytechnic in the United Kingdom. She was the
chief operations officer and chief financial officer of the Council for Medical Schemes in South
Africa where she held various positions from September 2000 until February 2008, when she resigned
from her executive position. Prior to that, she was treasurer at the Botswana Development
Corporation. Fikile is also a non-executive director of Rand Uranium (Proprietary) Ltd. and Anooraq
Resources Corporation.
Dr Cheick Diarra (56), PHD (Mechanical and Aerospace Engineering) Independent non-executive
director. Dr Cheick Diarra joined the Board as non-executive director on 5 March 2008. He is the
chairman for Africa at Microsoft, responsible for Microsofts broad scale citizenship, education
and developmental activities on the continent. Dr Diarra graduated from Pierre & Marie Curie
University in Paris, France and went on to attain his PhD in mechanical and aerospace engineering
from Howard University, Washington DC, USA. After six years as an Assistant Professor at Howard, he
joined the National Aeronautic and Space Association (NASA) Jet Propulsion Laboratory. As an
interplanetary navigator, he oversaw five NASA missions, including the Magellan mission to Venus,
the Ulysses mission to the poles of the Sun, the Galileo mission to Jupiter and the Mars Observer
mission. He then served as the navigator and public outreach manager for the Mars Pathfinder
mission. In 1999, in his personal capacity, Dr Diarra created the Pathfinder Foundation for
Education and Development an organisation that encourages and supports female students in their
pursuit of scientific education. In 2002, he was appointed CEO of the African Virtual University
(AVU), an internationally respected organisation. Late in 2003, Dr Diarra returned home to Mali
and, began working on his farm to find solutions to the continents challenges with food security
and nutrition. He is a member of a number of international and African scientific organisations,
and has been awarded the African Lifetime Achievement award for outstanding Contributions to
Science.
Ken Dicks (69), Mine Managers Certificates (Metalliferous and Fiery Coal Mines); Management
Development Diploma and Management Diploma Independent non-executive director. Ken was appointed
to the Board with effect from 13 February 2008. He retired from Anglo American in 1997 after 37
years service. Ken has 39 years experience in the mining industry, 37 of which were spent in gold
mining. He has served in various senior management positions as well as on mining companies boards
namely Freegold Limited, Western Deep Levels and Elandsrand. He is also a non-executive director of
Aflease Gold Limited.
115
Dr Simo Lushaba (42), Bsc (Hon), MBA and DBA Independent non-executive director. Simo is an
entrepreneur and an executive business coach. He focuses on business and leadership development,
and has interests in businesses in telecommunications, financial services, energy, transport and
logistics. He has worked as General Manager Operations (Spoornet), Vice President Shared
Business Services (Lonmin plc) and as Chief Executive (Rand Water). He is also a member of the
Board of the Nepad Business Foundation (SA). He is also a non-executive director of Rand Uranium
(Proprietary) Ltd.
Cathie Markus (51), BA LLB Independent non-executive director. Cathie joined the board with
effect from 1 May 2007, bringing with her significant experience and a wealth of knowledge relating
to the mining industry. After graduating from the University of the Witwatersrand, Cathie served
articles at Bell Dewar and Hall and qualified as an attorney, notary and conveyancer before joining
the legal department of Dorbyl Limited. She joined Impala Platinum Holdings Limited (Implats) in
1991 as Legal Adviser and was appointed an Executive Director in 1998, and oversaw, among others,
the legal, administrative, public affairs and investor relations functions for the group. She
retired from Implats in 2007.
Modise Motloba (42), BSc, Diploma in Strategic Management Independent non-executive
director. Modise Motloba (42), Bachelor of Science, and Diploma in Strategic Management
Independent non-executive director. Modise was appointed to the board
in July 2004. Modise who is
currently the Chief Executive Officer of Quartile Capital (Pty) Ltd,
has more than 17 years local and
global experience in investment banking, treasury, fund management, management consulting and
information technology. He worked for both local and international
corporates such as PricewaterhouseCoopers, Rand Merchant Bank, African Merchant Bank, Africa
Harvest Fund Managers and Goldman Sachs. Modise is a former President of Association of
Black Securities and Investment Professionals (ABSIP) which he led
together with the Black Business Council,
in formulating and negotiating the historic Financial Services Charter in October 2003. He is the
recipient of the prestigious 2003 Black Business Quarterly Investment Specialist and ABSIPs
Pioneer in the Financial Sector awards. Modise is a member of the South Africa Reserve Banks Standing Committee on the
Revision of the Banks Act 1990. He gained experience in chamber business organisations while
serving as the President of the Johannesburg Chamber of Commerce (JCCI) in 2005 and as a member of
the Trade Committee of Business Unity South Africa (BUSA). His other
key directorships include those at
Rand Merchant Bank Structured Insurance, Deutsche Bank Securities SA (Pty) Ltd., Landbank and Small
Enterprise Foundation.
Cedric Savage (69), BSc (Eng), MBA, ISMP (Harvard) Independent non-executive director.
Cedric joined the Board in September 2003. He started his career in the United Kingdom in 1960 as a
graduate engineer with Fairey Aviation. He returned to South Africa in 1963 and worked in the oil
(Mobil), textile (Felt & Textiles) and chicken (Rainbow Chickens Limited) industries. He was
president of the South African Chamber of Business from 1993 to 1994. He has also served as
chairman of the Board of Governors of the University of KwaZulu-Natals Development Foundation and
as a member of Council of that university. He joined the Tongaat-Hulett Group Ltd in 1977 as
managing director of Tongaat Foods and progressed to executive chairman of the Building Materials
Division; he became chief executive officer of the group in 1991. In May 2000, he assumed the dual
roles of chief executive officer and executive chairman. He is currently non-executive chairman of
the group and serves on a number of other boards including those of the Datatec Limited and Denel
(Pty) Ltd. He also served on the Nedbank board from 2002 until 14 May 2008 when he retired as
non-executive director.
André Wilkens (58), Mine Managers Certificate of Competency, MDPA, RMIIA, Non-executive
director. André was appointed to the Board in August 2007. He is currently the chief executive
officer of ARM having formerly been the chief executive of ARM Platinum, a division of ARM. Prior
to this, he was the chief operating officer of Harmony, following the merger of the company with
ARMgold in 2003. He had served as chief executive officer of ARMgold after joining that company in
1998. The balance of his 34 years experience in the mining industry was gained with Anglo American
Corporation of South Africa, where he began his career in 1969 and which culminated in his
appointment as mine manager of Vaal Reefs South Mine in 1993.
Management
The members of our management, their principal past affiliations, information on their
business experiences and principal outside activities and selected other information are set forth
below:
Bob Atkinson (56), NHD (Metalliferous Mining). Bob joined Harmony as a production
manager in 1986 and served as Operations Director on the Executive Committee from June 2001 to May
2003. In 2004, he was appointed Chief Operating Officer at Harmony Gold Australia and was appointed
as Executive, Sustainable Development (Safety and Occupational Health) at Harmony in South Africa
in July 2004. He currently serves as
Operations Director of Projects and New Business. He has more than 30 years experience in the
mining industry.
116
Jaco Boshoff (39), BSc (Hons), MSc (Geology), MBA, PrSciNat. Jaco joined Harmony in April
1996. Since March 2004, he has served as the Reserves and Resources Executive and Competent Person.
Prior to this, he was an Ore Reserve Manager from 1998 to 2004 and before that was a geologist at
Harmony and at Gengold. Jaco is registered as a professional geological scientist with the South
African Council for Natural Scientific Professions and has worked in the mining industry for more
than 11 years.
Johannes van Heerden (35), BCompt (Hons), CA(SA). Johannes joined Harmony in 1998 as Financial
Manager of the Free State operations. Here he obtained broad financial management experience at an
operational level. He was subsequently appointed Group Financial Manager in 2001, before being
relocated to Harmony Australasia as Chief Financial Officer in 2003. Johannes presently holds the
position of Managing Director International Operations Chief Executive (South East Asia).
Mashego Mashego (44), BA Ed, BA (Hons), GEDP, JMDP. Mashego joined Harmony in July 2005 as
Group Human Resources Development Manager. Mashego, who has more than 19 years experience in the
field of Human Resources, started his career at Eskom where he was Human Resources Manager for nine
years. He then moved to JCI as Corporate Human Resources Manager. Thereafter, he was Senior General
Manager for three years at Atlantis Diesel Engines and Vice President of Human Resources at Foskor
Ltd for six years. He was promoted to General Manager at Harmonys Evander Operations in November
2005. Mashego was appointed Executive, Human Resources in August 2007.
Jackie Mathebula (37), B Admin Honours, MBA, Master of Management (MM, HR). Jackie joined
Harmony in September 2002 as an employee relations and industrial relations executive. In 2004, his
portfolio was changed to that of Training, Human Resource Development and Occupational Health, and
in 2005 to the position of Executive, Corporate Affairs. Prior to joining Harmony, he was a General
Manager in Human Resources for Gensec Bank, a Human Resources Manager at Gold Fields Ltd and he
also occupied various positions within the then Iscor group (now Mittal Steel South Africa). His
last position at Iscor was that of Works Manager, human resources for the specialised steel
products business. He also worked for the South African government in the Gazankulu Public Service
Commission.
Alwyn Pretorius (36), BSc Mining Engineering & BSc Industrial Engineering (UP). Alwyn, a
mine manager at ARMgold, joined the company when Harmony merged with ARMgold in 2003. He began his
career at Vaal Reefs Gold Mine as a mining graduate in training in 1993 and was appointed shift
boss in 1995, gaining experience in remnant mining. Alwyn obtained a Mine Managers Certificate of
Competence in 1997 and his BSc in Industrial Engineering in 1998. Alwyn joined ARMgold in 1999 at
its Orkney operations. He became a mine overseer at ARMgold and was later appointed section manager
at the same operation. He was appointed mine manager in 2003. Alwyn was appointed Executive, South
African Operations for Harmony in March 2007, and is the Chief Operating Officer for South African
operations, North Region.
Marian van der Walt (35), BCom (Law), LLB, Higher Diploma in Tax, Diploma in Corporate
Governance, Diploma in Insolvency Law, Certificate in Business Leadership. Marian has 11 years of
legal experience and was appointed Company Secretary on 3 February 2003. She completed her articles
at Routledges Modise Attorneys and was admitted as an attorney and conveyancer in 1998. She then
joined Deloitte and Touche as an insolvency
practitioner/administrator. She held legal positions at the
Standard Bank of South Africa Limited in the Commercial Properties
Division prior to joining Harmony in 2003. Marian was appointed to
the Executive Committee in October 2005 with responsibility for legal, compliance and risk
management. Internal audit and Sarbanes-Oxley compliance were added to her portfolio in September
2007. In October 2008, she was appointed executive: corporate and investor relations.
Tom Smith (52), NHD (Mine Surveying and Metalliferous Mining). Tom joined Harmony in 2002.
Tom began his career in the mining industry in 1975 as a sampler at Anglo Americans Vaal Reefs
mine. He progressed through the survey department to become chief surveyor in 1988. He made a
career change in 1991 to mining and worked as a section manager on Great Noligwa, Elandsrand and
Mponeng mines. He was also involved in projects at Tau Lekoa and Moab Khotsong. Tom was promoted to
Production Manager at Mponeng in 1998. He was appointed General Manager of Tshepong in 2000.
Following the merger with ARMgold he was involved in the Free State restructuring. He acquired work
experience in conventional, trackless, pillar- and deep-level mining. He joined the executive team
in September 2007 and is the Chief Operating Officer, South Region.
Abre van Vuuren (48), BComm, MDP, DPLR. Abre joined Harmony in 1997 from Grootvlei Mine, where
he was Human Resources Manager. He was appointed to the Executive Committee in November 2000 and is
responsible for Services. He has approximately 25 years experience in the mining industry.
117
Board and Management Changes
The members of the Board and Harmonys management that resigned from Harmony during and -post
fiscal year-end , their principal past affiliations, information on their business experiences and
principal outside activities and selected other information are set forth below:
Former
Executive Directors
Bernard Swanepoel (46), BSc (Mining Engineering), BCom (Hons). Bernard resigned as Chief
Executive of Harmony on August 6, 2007. He had started his career with Gengold in 1983, culminating
in his appointment as general manager of Beatrix Mine in 1993. He joined Randgold in 1995 as
managing director of Harmony. For the past 11 years, Bernard has led the team behind the companys
growth and acquisition initiatives.
Nomfundo Qangule (40), BCom, BCom (Hons) CTA, CA (SA), Member of CAIB (SA) and the Financial
Director of Harmony. Nomfundo resigned from the Board as an executive director on August 21, 2007.
Prior to joining Harmony, Nomfundo was the Executive Manager of Worldwide African Investment
Holdings (Pty) Ltd (WAIH). Other positions held by Nomfundo while at WAIH include chairperson of
the Board of Argil Holdings (Pty) Ltd and non-executive director of CS Holdings Limited where she
served as a member of the Remuneration, Audit and Investment committees. In addition, she was an
Executive Committee member and non-executive Director of Negotiated Benefits Consultants (Pty) Ltd.
She started her career in the Corporate and International Division of Nedcor Bank Limited as a
Credit Manager. Later she joined ABSA Corporate and Merchant Banks credit division. She is a
qualified Chartered Accountant, a member of the Institute of Bankers and holds a certificate in
financial markets from Acumen.
Former
Management
Boetie Swanepoel (47), BCompt (Hons), CA(SA). Boetie resigned from Harmonys management on 31
July 2007. Boetie joined Harmony from Beatrix Mine in 1995 as Financial Manager. He has more than
21 years financial services experience, mostly in the mining industry. He was appointed to the
Executive Committee in November 2000 and was responsible for the development of Harmonys shaft
financial managers, the financial control environment and the service delivery departments.
Board Practices
Our Articles of Association provide that the Board must consist of no less than four and
no more than twenty directors at any time. The Board currently consists of twelve directors.
Our Articles of Association provide that the longest serving one-third of directors
retire from office at each annual general meeting. Retiring directors normally make themselves
available for re-election and are re-elected at the annual general meeting on which they retire.
Members of our senior management who are also directors retire as directors in terms of the
Articles of Association, but their service as officers is regulated by standard industry employment
agreements. According to the Articles of Association, the Board meets not less than quarterly.
Details of directors service contracts are described under Compensation of Directors
and Senior Management and Directors Terms of Employment, below. We also describe significant
ways in which our corporate governance practices differ from practices followed by U.S. companies
listed on the NYSE on our website under Corporate Governance.
In order to ensure good corporate governance, the Board has formed an
Audit Committee, a Remuneration Committee, a Nomination Committee, an Investment Committee, an
Employment Equity Committee, Sustainable Development Committee and a Technical Committee. All of
the Board committees are comprised of a majority of non-executive directors.
Executive
Management Committee
Our Executive Committee comprises our executive directors and selected senior officers,
each with his or her own area of responsibility. The Executive Committee consists of 11 executives
who meet on a weekly basis and more often if required.
The
composition of the Executive Management Committee (with areas of responsibility indicated) is as
follows:
|
|
|
Graham Briggs
|
|
Chief Executive |
|
|
|
Frank Abbott
|
|
Interim Chief Financial Officer |
118
|
|
|
Bob Atkinson
|
|
Projects |
|
|
|
Jaco Boshoff
|
|
Ore Reserves |
|
|
|
Mashego Mashego
|
|
Human Resources |
|
|
|
Jackie Mathebula
|
|
Corporate Affairs |
|
|
|
Alwyn Petorius
|
|
Chief Operating Officer (North) |
|
|
|
Tom Smith
|
|
Chief Operating Officer (South) |
|
|
|
Marian van der Walt
|
|
Company Secretary; Legal and Compliance (as from
October 1, 2008, Corporate and Investor Relations) |
|
|
|
Johannes van Heerden
|
|
Chief Executive Officer South East Asia |
|
|
|
Abre van Vuuren
|
|
Corporate Services |
Audit Committee
Members:
In terms of its charter this committee must comprise at least three members.
As at June 30, 2008, the members of this committee were:
|
|
|
Cedric Savage
|
|
Chairman; appointed to the committee on January 26, 2004
and chairman as from August 5, 2005 |
|
|
|
Fikile de Buck
|
|
Appointed to the committee on March 30, 2006 |
|
|
|
Dr. Simo Lushaba
|
|
Appointed to the committee on January 24, 2003 |
|
|
|
Modise Motloba
|
|
Appointed to the committee on July 30, 2004 |
The internal and external auditors, the chief executive officer and executive managers are
all invited to the Audit Committee meeting.
Frequency of meetings:
The Audit committee is, in terms of its charter, required to meet at least four times a year,
or more frequently as circumstances dictate. During the financial year, the committee met on eight
occasions.
Purpose and function:
The Audit Committee was established to assist the board in discharging its duties relating to
the safeguarding of assets; the operation of adequate system and internal controls and control
processes; the preparation of accurate financial reporting and statements in compliance with all
applicable legal requirements, corporate governance and accounting standards. It also provides
support to the board on the risk profile and risk management of the group.
The Audit Committee reports and makes recommendations to the board, and the board retains
responsibility for implementing such recommendations.
Independence/compliance:
All members of the Audit Committee are independent, non-executive directors.
Currently, we do not have an individual audit committee financial expert as defined by the
rules of the SEC. It is our contention that the audit committee members, through their
collective experience, do meet the majority of the definitions of the SEC for an audit committee
financial expert in both the public and private sectors. The members have served as directors and
officers of numerous public companies and have over the
years developed a strong knowledge and understanding of IFRS,
overseeing the preparation, audit and evaluation of financial statements. We believe that the
combined knowledge, skills and experience of the Audit committee, and their
119
authority to engage
outside experts to provide them with advice on matters relating to their responsibilities as they
deem appropriate, enables them as a group to act effectively in the fulfillment of tasks and
responsibilities required under U.S. Sarbanes Oxley Act of 2002.
Empowerment Committee
Members:
The Empowerment Committee must comprise of at least three members.
As at June 30, 2008, the members of this committee were as follows:
|
|
|
Joaquim Chissano
|
|
Chairman; Appointed as chairman with effect from May 3, 2006 |
|
|
|
Modise Motloba
|
|
Appointed to the committee on May 3, 2006 |
|
|
|
Cathie Markus
|
|
Appointed to the committee on October 29, 2007 |
Bernard Swanepoel resigned from this committee on 6 August 2007.
The
chief executive officer and executive managers are all invited to
attend the Empowerment
Committee meetings.
Frequency of meetings:
The
Empowerment Committee met on two occasions.
Purpose and function:
The Empowerment Committee was established by the board to ensure that the company meets not
only regulations stipulated in the Employment Equity Act, the Labour Relations Act and the Mineral
and Petroleum Resources Development Acts Mining Charter Scorecard, but also in fulfilment of our
own empowerment imperatives.
The responsibilities of the Empowerment Committee include ensuring that a sustainable
organisational culture, structures and processes are in place to support the development of
empowerment in the company in line with the companys needs and requirements; to monitor the
development and progress of empowerment within the company; to address inequalities that may exist
in staff profiles and organisational practices; and to review and monitor whether appropriate
support is given to previously disadvantaged staff in order to equip them for successful careers in
the company.
Independence/compliance:
The committee is chaired by an independent non-executive director and comprises of
independent non-executive directors.
Investment Committee
Members:
The Investment Committee must comprise of at least three members.
As at June 30, 2008, the members were:
|
|
|
Dr. Simo Lushaba
|
|
Chairman; Appointed to the committee on January 26, 2004
and as Chairman with effect from August 5, 2005) |
|
|
|
Frank Abbott
|
|
Appointed to the committee on July 30, 2004 and resigned
from the committee following his appointment as Interim
Financial Director on August 21, 2007 |
|
|
|
Fikile De Buck
|
|
Appointed to the committee on May 3, 2006 |
|
|
|
Cedric Savage
|
|
Appointed to the committee on January 26, 2004 |
|
|
|
André Wilkens
|
|
Appointed to the committee on August 7, 2007 |
|
|
|
Cathie Markus
|
|
Appointed to the committee on October 29, 2007 |
|
|
|
Ken Dicks
|
|
Appointed to the committee on February 13, 2008 |
The chief executive officer and executive managers are invited to attend the meetings.
120
Frequency of meetings:
The committee should meet at least four times a year, but may, at its discretion, meet more
often depending on the circumstances. The committee met on eight occasions in fiscal 2008.
Purpose and function:
The Investment Committees purpose was reviewed, following the implementation of the Technical
Committee in February 2008. The primary purpose of the Investment Committee is to consider
projects, acquisitions and the disposal of assets in line with the Groups overall strategy. This
includes performing such other investment related functions as may be designated by the Board from
time to time, considering the viability of the capital project and/or acquisition and/or disposal
and the effect it may have on the Groups cash flow, as well as whether it will fit the Groups
overall strategy and ensuring that due diligence procedures are followed when acquiring or
disposing of assets.
Independence/compliance:
The Investment Committee consists of six non-executive members. Of the six non-executive members, five
are independent. The chairman is an independent, non-executive
director. Members of the Executive Committee and the chief executive
officer are invited to attend the meetings.
Nomination Committee
Members:
The Nomination Committee must comprise of at least three members.
As at June 30, 2008, the members of this committee were:
|
|
|
Patrice Motsepe
|
|
Chairman; Appointed to the committee on October 24, 2003 as Chairman |
|
|
|
Joaquim Chissano
|
|
Appointed to the committee on May 3, 2006 |
|
|
|
Frank Abbott
|
|
Appointed to the committee August 5, 2005 |
Frequency of meetings
Members of this committee are required to meet annually or more often at the committees
discretion, depending on prevailing circumstances. In view of the fact that only one member of the
committee is an independent non-executive director, any decisions by the Nomination Committee are
approved by the Board, either through a round robin resolution or at a Board meeting.
Purpose and function
The primary purpose of the Nomination Committee is to ensure that the procedures for
appointments to the board are formal and transparent, by making recommendations to the board on all
new board appointments and reviewing succession planning for directors. The duties and
responsibilities of this committee are set out in the Nomination Committee charter, with which the
committee is fully compliant.
Independence/compliance:
The chairman of the Nomination Committee is non-executive, but is not independent. To ensure
appropriate levels of governance, the potential directors identified by the nominations committee
are considered by the board as a whole, the majority of whom are non-executive, independent
directors.
Remuneration Committee
Members
The Remuneration Committee must comprise of at least three members.
As at June 30, 2008, the members of this committee were:
|
|
|
Cedric Savage
|
|
Chairman; Appointed to the committee on January 24, 2004,
and as chairman from May 3, 2006 |
121
|
|
|
Dr. Simo Lushaba
|
|
Appointed to the committee on August 5, 2005 |
|
|
|
Patrice Motsepe
|
|
Appointed to the committee on January 26, 2004 |
|
|
|
André Wilkens
|
|
Appointed to the committee on August 7, 2007 |
The chief executive, HR Executive and Company Secretary are invited to attend all meetings.
Frequency of meetings:
The Remuneration committee is expected to meet at least on a quarterly basis or to pass a
resolution in lieu of a formal meeting not held. In fiscal 2008, the committee met on one occasion
and a number of round-robin resolutions were passed.
Purpose and function:
The primary purposes of the Remuneration Committee are to ensure that the groups directors
and senior executives are fairly rewarded for their individual contributions to our overall
performance and to demonstrate to all stakeholders that the remuneration of our senior executive
members is set by a committee of board members who have no personal interest in the outcome of
their decisions, and who will give due regard to the interests of our shareholders and to our
financial and commercial health.
The committees primary objectives are to monitor and strengthen the objectivity and
credibility of our directors and senior executives remuneration system, and to make
recommendations to the board on remuneration packages and policies applicable to directors. A
formal reward philosophy was adopted by the Remuneration Committee in March 2006. This philosophy
is reviewed annually by the committee.
Independence/compliance:
The committee comprises four non-executive directors, of which two are independent. It is
therefore not compliant with King II which requires that the committee comprise independent
directors only. The chairman of the Remuneration Committee is, however, an independent
non-executive director and ensures that decisions are non-bias and fair. The chairman attended the
AGM which was held on November 26, 2007 to respond to any queries from shareholders.
Sustainable Development Committee
Members:
The Sustainable Development Committee must comprise of at least three members.
As at June 30, 2008, the following were members of this committee:
|
|
|
Modise Motloba
|
|
Chairman; Appointed as chairman on August 5, 2005 |
|
|
|
Joaquim Chissano
|
|
Appointed to the committee on May 3, 2006 |
|
|
|
Fikile de Buck
|
|
Appointed to the committee on May 3, 2006 |
The
chief executive officer and executive managers are invited to attend the
meetings.
Frequency of meetings:
The Sustainable Development Committee should meet at least four times a year, or more
frequently as circumstances dictate. In fiscal 2008, four meetings of this committee were held.
Purpose and function:
The objective of the Sustainable Development Committee is to assist the board in ensuring that
we are and remain a committed socially responsible corporate citizen. The committees primary role
is to supplement, support, advise and provide guidance on the effectiveness or otherwise of
managements efforts in respect of sustainable development.
The committee considers the following sustainable development issues: occupational health,
safety, HIV/Aids, social investment and environmental management.
Independence/compliance:
The committee comprises entirely of independent, non-executive directors.
122
Technical Committee
Members:
The Technical Committee must comprise of at least three members.
As at June 30, 2008, the following were members of this committee:
|
|
|
Andre Wilkens
|
|
Chairman; Appointed as chairman on February 13, 2008 |
|
|
|
Ken Dicks
|
|
Appointed to the committee on February 13, 2008 |
|
|
|
Modise Motloba
|
|
Appointed to the committee on February 13, 2008 |
|
|
|
Cedric Savage
|
|
Appointed to the committee on February 13, 2008 |
The chief executive and executive managers are all invited to attend the meetings.
Frequency of meetings:
The Committee should meet at least six times a year. The Committee, at its discretion, may
decide to change this requirement, depending on the circumstances. Bearing in mind that the
Technical Committee was only established in February 2008, three meetings of this committee were
held between then and end of fiscal 2008.
Purpose and function:
The Technical Committee was formed in February 2008 to provide a platform for the chief
executive officer to discuss the companys strategy, its
performance against targets, its operational results and
projects. The Technical Committee keeps the Board informed of the developments, progress and
challenges facing the companys operations. The strategic plans
are considered by the Technical Committee and recommended for
approval to the Investment Committee and the Board. In addition, the Technical Committee provides guidance
and support to Management to ensure that the Company remains sustainable and successful.
The committee considers and reviews the companys strategy, its performance targets and its
projects on an annual basis; reviews the performance of the company and the chief executive;
reports to the Board on the developments, progress and challenges facing the companys operations
on a quarterly basis and provides guidance and support to Management to ensure that the company
remains sustainable and successful.
Independence/compliance:
The committee comprises of three independent, non-executive directors. The chairman is not
independent, but it was agreed that he was best suited to be appointed as chairman, due to his vast
knowledge of the companys assets and his years of mining experience.
Compensation of Directors and Senior Management
The following table shows the compensation of directors and senior management for fiscal 2008:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Retirement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contributions |
|
|
|
|
|
|
Directors |
|
Salaries and |
|
during |
|
Bonuses |
|
|
|
|
fee (1) |
|
Benefits |
|
the year |
|
Paid |
|
Total |
|
|
($000) |
|
($000) |
|
($000) |
|
($000) |
|
($000) |
Name |
|
2008 |
|
2008 |
|
2008 |
|
2008 |
|
2008 |
Non-executive |
|
|
|
|
|
|
|
|
& |